Standard Lumber Co. v. Butler Ice Co.

146 F. 359, 76 C.C.A. 639, 1906 U.S. App. LEXIS 4105
CourtCourt of Appeals for the Third Circuit
DecidedJune 20, 1906
DocketNo. 45
StatusPublished
Cited by14 cases

This text of 146 F. 359 (Standard Lumber Co. v. Butler Ice Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Standard Lumber Co. v. Butler Ice Co., 146 F. 359, 76 C.C.A. 639, 1906 U.S. App. LEXIS 4105 (3d Cir. 1906).

Opinion

GRAY, Circuit Judge.

In the court below, the plaintiff in error, the Standard Lumber Company, a corporation of the state of Pennsylvania, brought an action ex contractu against the defendant, the Butler Ice Company, a corporation of the state of Delaware.' The statement of claim sets forth a certain contract in writing between plaintiff and defendant, whereby the plaintiff undertook to provide the materials and do all the work mentioned and shown in specifications and drawings, referred to in said contract, for the erection and completion of an ice plant, with certain exceptions therein stated; and in consideration thereof, the defendant agreed to pay plaintiff the sum of $10,808. It was also agreed that there should be paid $6.50 per perch for extra stonework, above that shown in said plans, and 50 cents per yard for extra excavating, subject to additions and deductions as in said contract provided. It is then alleged that plaintiff had provided all the materials, and had performed all the work stipulated for in said contract, in accordance with the terms thereof, and that defendant had accepted the same; that plaintiff had also done extra work under the contract, amounting to $2,838, so that the $10,808 agreed to be paid for the completion of the work specified in the contract, and the amount to be paid for the extra work, at the rate stipulated for therein, amounted to $13,-. 646. Against this sum, the plaintiff allows defendants credits to the amount of $11,624, leaving a balance of $2,022 claimed as due from defendant to plaintiff.

The written contract, as set out in the statement of claim and produced at the trial, was executed by the plaintiff, the Standard Lumber Company, under its seal and the signature of J. M. AVetherill, manager, and on the part of the Butler Ice Company, under the seal of said company and the signatures of Peter E. McCool, its president, and S. B. Plemies, its secretary. The affidavit of defense set out, and it was -proved at the trial, that the plaintiff company, by a letter addressed to P. E. McCool, then president of the defendant company, and signed by the Standard Lumber Company, “Per F. E. Brotherton,” agent of the plaintiff company, duly authorized in that behalf, proposed to build the ice plant for defendant company, according to the plans and specifications submitted, for the sum of $6,309.50; that the plans and specifications referred to in said bid, were the plans and specifications referred to in, and made part of, the contract between plaintiff and defendant companies, upon which suit was brought in the court below, and in which the consideration named for the, work included in this bid was $10,808, and that the bid for $6,309.50 was full price for said work. Subsequent to the making of said bid, by agreement between Peter F. McCool, president of the defendant company, and'the plaintiff company, acting through its manager, Wether ill, the said bid for said work was [361]*361increased to the sum of $10,808, and the contract upon which suit was brought was then entered into upon that consideration to be paid by the defendant company, it being understood by the said officers of the two companies, that when the consideration was paid by the defendant company, $2,000 of the difference between the original bid and the contract price, was to be paid to the said Peter F. McCool, and that the balance was to be divided between the said Wetherill and the said plaintiff company. The testimony as to this corrupt understanding and contract was uncontradicted, and it was not denied that the consideration of the written contracts was thus corruptly increased, or that the president of the defendant company conspired with the plaintiff company and its manager, Wetherill, to defraud the said defendant company for his own benefit.

The facts thus summarized not being denied, counsel for plaintiff contends that the defendant is bound by the action of its president and secretary, and that, inasmuch as the corporate seal was attached,as well as the signatures of the last-named officers, defendant cannot now avoid the obligation of the contract thus formally executed, and that plaintiff had a right to rely upon the signed contract under the corporate seal. The cases relied upon by plaintiff seem to be those in which corporate obligations duly executed have come into the hands of innocent third persons, where it is held that, inasmuch as there is a presumption that the seal was affixed by the proper authority, it is not to be overcome by the mere fact that no vote of the directors authorizing it is shown. We are not, however, dealing with a case of the innocent holder of such a contract, the undisputed facts being that the manager of the plaintiff corporation, with the knowledge of its directing and executive authorities, entered into a corrupt bargain with the president of the defendant company, to add more than 50 per cent, to the original bid, with the understanding that the amount by which the bid was thus increased should, when paid by the defendant company, be divided between the conspirators. It is too mild a characterization of such a transaction to say that it was fraudulent. It was a gross scheme for the abstraction of more than $4,000 from the treasury of the defendant company, to be converted to the use of the conspirators, the larger share of it to the defendant’s own president. The acts and conduct thus described are clearly in violation of two statutes of Pennsylvania, which provide as follows: Act of March 31, I860:

■‘If any two or more persons sliall falsely and maliciously conspire and agree to cheat and defraud any person or body corporate, of his or their moneys, goods, chattels or other property, or to do any other dishonest, malicious and unlawful act, to the prejudice of another, they shall be guilty of a misdemeanor, and on conviction, be sentenced to pay a fine, not exceeding five hundred dollars, and to undergo an imprisonment, by separate or solitary confinement at labor, or by simple imprisonment, not exceeding two years.” P. L. 413, § 128.

Act of June 12, 1878:

“Sec. 1. If any person, being an officer, director, superintendent, manager, receiver, employe, agent, attorney, broker, or member of any bank or other body corporate, or public company, municipal or quasi municipal corporation, [362]*362shall fraudulently take, convert, or apply to his own use, or the use of any other person, any of the money or other property of such hank, body corporate, or company, municipal or quasi municipal corporation or association, or belonging to any person or persons, corporation or association, and deposited therein, or in possession thereof, he shall be guilty of a misdemeanor.”
“Sec. 6. That every person found guilty of a misdemeanor under any or either of the preceding sections of this title, wherein the nature and extent of the 'punishment, is not specified, shall be sentenced to pay a fine not exceeding one thousand dollars, and to undergo an imprisonment by separate or solitary confinement at labor not exceeding six years.” P. L. 190, 197.

The contract was not only immoral, but it was illegal and criminal, and therefore void. No court would be justified in enforcing the whole or any part of such a contract. From an origin so flagitious, no right of action can arise. The maxim “ex turpi causa, non oritur actio,” founded as it is on sound morals, has been long recognized by courts in the practical administration of justice. Petrie v. Hannay, 3 T. R. 422; Collins v. Blantern, 2 Wils. 341.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

National Transformer Corp. v. France Mfg. Co.
215 F.2d 343 (Sixth Circuit, 1954)
Fitzsimons v. Eagle Brewing Co.
107 F.2d 712 (Third Circuit, 1939)
Babcock v. Warner Bros. Theatres, Inc.
240 A.D. 466 (Appellate Division of the Supreme Court of New York, 1934)
Eizen v. Stecker, Inc.
145 A. 606 (Supreme Court of Pennsylvania, 1929)
Anderson v. O'Briant
3 S.W.2d 842 (Court of Appeals of Texas, 1928)
Moore v. Moore
255 F. 497 (Third Circuit, 1919)
Haymond v. Hyer
92 S.E. 854 (West Virginia Supreme Court, 1917)
Fairbanks-Morse Co. v. City of Geary
1916 OK 398 (Supreme Court of Oklahoma, 1916)
The Washtenaw
163 F. 372 (E.D. New York, 1908)
Hoysradt v. Delaware, L. & W. R.
151 F. 321 (U.S. Circuit Court for the District of Middle Pennsylvania, 1907)

Cite This Page — Counsel Stack

Bluebook (online)
146 F. 359, 76 C.C.A. 639, 1906 U.S. App. LEXIS 4105, Counsel Stack Legal Research, https://law.counselstack.com/opinion/standard-lumber-co-v-butler-ice-co-ca3-1906.