Standard Accident Ins. v. United States Cas. Co.

1947 OK 390, 188 P.2d 204, 199 Okla. 530, 1947 Okla. LEXIS 752
CourtSupreme Court of Oklahoma
DecidedDecember 23, 1947
DocketNo. 31296
StatusPublished
Cited by3 cases

This text of 1947 OK 390 (Standard Accident Ins. v. United States Cas. Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Standard Accident Ins. v. United States Cas. Co., 1947 OK 390, 188 P.2d 204, 199 Okla. 530, 1947 Okla. LEXIS 752 (Okla. 1947).

Opinion

GIBSON, J.

Holbert Electric Company, a copartnership composed of P. A. Holbert and G. R. Holbert, hereinafter referred to as contractor, was engaged in the performance of three construction contracts. In each case performance and payment bonds were required and Standard Accident Insurance Company, a corporation, hereinafter referred to as surety, executed each of the bonds in that capacity. Each bond was conditioned that principal would pay all bills incurred for labor and material used in the performance of the contract. During the period said contractor was covered by two insurance policies issued by United States Casualty Company, a corporation, hereinafter referred to as plaintiff. One of the policies was a public liability policy, and the other what is designated as a standard workmen’s compensation policy which had for its purpose protection of the insured for any and all claims arising under the Workmen’s Compensation Law in the State of Oklahoma. The amount of the premiums on each policy was fixed on a payroll basis and to be arrived at by audit of the payrolls of the contractor covering period from beginning of the work to November 12, 1939, the expiration dates of the policies.

One of the projects was designated by the United States Rural Electrification Administration as “Oklahoma-25Al-Rogers” and involved the construction of distribution lines for electric energy in Tulsa and neighboring counties under contract with the Verdigris Valley Electric Co-Operative, Inc. Another contract was with the city of Anadarko for the rebuilding of the distribution system of the city’s electric light plant. And the other was with the A. & M. College at Stillwater.

The several projects were completed but the contractor failed to pay the premiums upon the insurance furnished by plaintiff and there was due and owning thereon a total of $7,882.86, consisting of $6,167.27 on the workmen’s compensation policy and $1,-715.59 on the public liability policy. The contractor further failed to pay divers obligations incurred for material purchased and used, which aggregated the sum of $27,741.21.

In pursuance of their rights so to do under the terms of the contracts. Verdigris Valley Electric Co-Operative, Inc., and the city of Anadarko each retained percentages of the contract price to be held until all bills were paid. The amount retained by the first named being $14,855, and that by the latter $693.79.

As part of the consideration for the execution by surety of said bonds, contractor entered into an agreement wherein it was agreed to indemnify surety against loss and assigned to surety all moneys, due contractor at the time of any breach or default by contractor of the terms of the bond. And, in compliance therewith, contractor, on or about June 20, 1940, assigned to surety all money due or to become due and payable to contractor under said contracts and other assets of said contractor and of the individual members thereof. Surety paid contractor’s obligations for material in the amount of $27,741.21, owing on the Verdigris project and $6,190,855 owing on the Anadarko project, and made demands for payment of the retained funds which were refused. Such was the situation when plaintiff, on July 11, 1940, instituted the present action to which all persons in interest were made or became parties.

No personal judgment was sought against any of the contractees. At the time of filing the action the A. & M. College contract had been completed and it developed that there was no retained percentage. By order of court, on stipulation, Verdigris Valley Electric Co-Operative, Inc., and the city of Anadarko were permitted to disburse the funds without prejudice to the issues between the remaining parties and [532]*532the action dismissed as to them. Under the terms of the order the fund retained by city of Anadarko was paid to surety and of the fund retained by Verdigris Valley Co-Operative, Inc'., $7,~ 500 was paid into court and the remainder, $7,355, paid to said surety.

On the issues plaintiff sought personal judgment against contractor for $7,882.86, the aggregate of the premiums owing on both policies and judgment declaring that $6,167.27, the amount of premium on workmen’s compensation policy, to be a lien upon both funds and prior to that of surety. Plaintiff also sought a personal judgment against surety for said aggregate amount of the premiums. Surety, on cross-petition, sought judgment, declaring it to have a lien superior to any claim of plaintiff upon all of said funds by reason of its payment of materialmen’s claims in excess of the amounts thereof.

The court decreed that plaintiff was entitled to a lien upon all of the assets of the contractor and of the individual members thereof and that such lien constituted a first and prior to lien upon the fund paid into court and directed payment thereof accordingly. It is from this finding and judgment that surety appeals. The court denied plaintiff a personal judgment against surety, and it is therefrom plaintiff files cross-appeal.

Although the parties appear to agree that the statutory laborer’s lien laws apply and compliance or,, noncompliance therewith are decisive of this appeal, we do not think they apply in the circumstances.

The question of the respective rights of plaintiff and surety in the fund and hence the correctness of the judgment thereon involved a construction of 85 O.S. 1941 §49, which is as follows:

“The right of compensation granted by this Act, and any claim for unpaid compensation insurance premium, shall have the same preference or lien, without limit of amount against the assets of the employer as is now or hereafter may be allowed by law for a claim for unpaid wages for labor.”

In support of the judgment it is urged by plaintiff that the section makes plaintiff’s claim for unpaid premiums a lien upon all of the assets of the contractor; that the lien being the same as that of labor is subordinate only to taxes and hence prior ■ to claim of surety; and that if filing of lien statements was necessary to preserve the same an equivalent therefor was had by the filing of this action within eight months.

For error in the judgment so rendered and in not rendering judgment for surety the latter urges that the quoted statute is not self-executing and hence no general lien obtains; that the statutory provisions for labor liens which alone could perfect the lien have no application and if applicable the lien was not preserved by filing statement; and that surety by reason of its assignment from the contractor and its payment of the material claims had an equitable right to payment from the fund on authority of the holding of this court in Fidelity National Bank v. United States Casualty Co., 191 Okla. 496, 131 P. 2d 75.

The contention that said section 49 is self-executing and therefore that plaintiff’s claim for insurance premiums is a lien upon all the assets of contractor and thus inclusive of the retained percentage of the contract price is contrary to our holding in Pauline Oil & Gas Co. v. Fischer, 185 Okla. 108, 90 P. 2d 411. Under the terms of the statute a claim for premiums occupies the same position as a claim for compensation. We there had under consideration a claim for compensation wherein a similar contention was made. Construing the section, which was then 13373, O. S. 1931, we held:

“Section 13373, supra, purports to grant a lien the same as a lien ‘for wages for labor.’ That latter lien is [533]*533provided for in section 11007, O. S. 1931, 42 Okla. St. Ann. sec.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stroud Oil Reclaiming Co. v. Community State Bank of Bristow
1970 OK 196 (Supreme Court of Oklahoma, 1970)
Champlin v. Frantz
1949 OK 278 (Supreme Court of Oklahoma, 1949)

Cite This Page — Counsel Stack

Bluebook (online)
1947 OK 390, 188 P.2d 204, 199 Okla. 530, 1947 Okla. LEXIS 752, Counsel Stack Legal Research, https://law.counselstack.com/opinion/standard-accident-ins-v-united-states-cas-co-okla-1947.