Standard Acc. Ins. v. Huddleston

51 F. Supp. 645, 1943 U.S. Dist. LEXIS 2223
CourtDistrict Court, M.D. Tennessee
DecidedAugust 3, 1943
DocketNo. 31
StatusPublished
Cited by1 cases

This text of 51 F. Supp. 645 (Standard Acc. Ins. v. Huddleston) is published on Counsel Stack Legal Research, covering District Court, M.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Standard Acc. Ins. v. Huddleston, 51 F. Supp. 645, 1943 U.S. Dist. LEXIS 2223 (M.D. Tenn. 1943).

Opinion

DAVIES, District Judge.

The cause was submitted upon the pleadings, ., evidence,, exhibits, argument and briefs of counsel for plaintiff .and defend-; ants, and after due consideration thereof, the ‘Court enters its findings of fact and conclusions of law as follows: •

Findings.

1. All parties, complainant and defendant/are properly identified in the pleadings, are-sui juris, and have filed proper pleadings herein to put this case at issue upon the merits.

-2. By contract dated October 3, 1939, defendant Putnam County, acting by its County Judge the defendant, B. C. Huddleston, thereunto duly authorized, agreed with West &-Reed, contractors, upon the terms for the -construction of certain school buildings, a-nd repairs to existing school buildings, all in Putnam County, being designated in the written contract as sub-projects, Nos. 6 to 12, inclusive. The County, as owner, .agreed to pay the contractor the sum -of Twenty-five Thousand Eight Hundred Twenty-eight and 90/100 Dollars ($25,828.90), “for the performance of the contract”-.

Progress payments were provided for upon a basis of 90% of the value of labor and materials in the work or stored at the site. In connection with such payments the contract provided in part: “The contractor shall submit to the architect an application for each payment and, if required, receipts or other vouchers showing his payments for materials and labor, including payments to the sub-contractors, as required by Article 37. * * * This schedule, when approved by the architect shall be used as a basis for certificates of payment, unless it be found to be in error.”

The contract further provides, in part:

- “Owner’s Right to Withhold Certain Amounts and Make Application Thereof:”
“If evidence is produced before the final settlement of all or any balances that the contractor has failed to pay laborers employed on his work or failed to pay for the materials used therein, or if the owner has reason to suspect the same, the owner may withhold such balances, and upon evidence satisfactory to the owner as to the amount due for such labor or materials the owner, acting as the agent of the contractor, may settle arid pay for’’the sarh’é,‘and charge the amounts to the’ contractor and deduct the same from the said balance or balances.” ’

The contract further provided:

’“Assignment:”

. .“The contractor shall not assign this contract or any part hereof, or any moneys due or to become due hereunder, without the approval of the owner, nor without the consent of the surety unless the surety has waived its right to notice of assignment.”

Said contract further provides, under the heading, “Acceptance and Final Payment” as follows:

“Final payment shall be due thirty (30) days after substantial completion of the work provided the work be then fully completed and the contract fully performed.
“Upon receipt of written notice that the work is ready for final inspection and acceptance, the architect shall promptly make such inspection and when he finds the work acceptable under the contract, and contract fully performed, he shall promptly issue a final certificate, over his own signature, stating that the work provided for in this contract has been completed and is accepted by him, under the terms and conditions thereof and that the entire balance found to be due the contractor and noted in said final certificate is due and payable.
“Before issuance of final certificate the contractor shall submit evidence satisfactory to the architect that all payrolls, material bills, and other indebtedness connected with the work have been paid.”

3. The said contract and contract documents filed in this case as complainant’s Exhibit No. 1 contain the legal notice to bidders, over the signatures of defendant Putnam County and defendant B. C. Huddleston, County Judge, and require, in part: “The successful bidder will be required to execute a performance bond covering and including labor and materials in the amount of 100j& of the contract price.”

The ’contract further requires, under its general conditions:

“Contract Security or Performance Bond:”
“The contractor shall furnish a surety bond executed by a surety company duly authorized to do business in the State of Ten[647]*647nessee in an amount at least equal to 100 per cent of the contract price as security for the faithful performance of this contract' and for the payment of all persons performing labor and furnishing materials in connection with this contract.”

4. Said construction project was in part financed by a grant from the Public Works Administration of the United States Government and in part was financed by a Bond Issue authorized by defendant Putnam County. The contract was designated as “PWA Docket No. Tenn.-1288-F; Sub-Projects Nos. 6 to 12, inclusive.” Marr & Holman of Nashville, Tennessee, were engaged by said County as Supervising Architects.

5. Pursuant to the above requirement of the defendant Putnam County and its officials, the contractor made application to complainant for a performance bond in the penalty of Twenty-five Thousand Eight Hundred Twenty-eight and 90/100 Dollars ($25,828.90) to secure the completion of said Projects; and also to “assure and protect all laborers and furnishers of material on said work”. Said application, which is in evidence in this cause as complainant’s Exhibit No. 1, reads, in part, as follows: “In further consideration of the execution of said bond, the undersigned does hereby agree, as of this date, that the said Standard Accident Insurance Company, shall as surety on said bond, be subrogated to all rights, privileges and properties of the undersigned as principal and otherwise in said contract, and does hereby assign, transfer and convey to said Company all the deferred payments and retained percentages, and any and all moneys and properties that may be due and payable at the time of such breach or default, or that may thereafter become due and payable to said undersigned on account of said contract, or on account of extra work and materials supplied in connection therewith, hereby agreeing that all such moneys and the proceeds of such payments and properties, shall be the sole property of the said Standard Accident Insurance Company, and to be by it credited upon any loan, cost, damage, charge and expense sustained, or incurred by it as above under its bond of suretyship.”

Pursuant to the terms of said application and in consideration of the protection offered the surety under the terms of said contract, the complainant executed its performance bond upon the form drawn and prescribed by the Public Works Administration. Said original bond is a part of the contract documents (complainant’s Exhibit No. 1), and two paragraphs from said bond read as follows:

. “But the Condition of the Foregoing Obligation or Bond Is This:”

“Whereas, the owner has engaged the said contractor for the sum of $25;828.90 to construct school buildings annd alterations and repairs to existing school buildings for Putnam County, Tennessee, Sub-Projects Nos.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Transmix Concrete of Rockdale v. United States
142 F. Supp. 306 (W.D. Texas, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
51 F. Supp. 645, 1943 U.S. Dist. LEXIS 2223, Counsel Stack Legal Research, https://law.counselstack.com/opinion/standard-acc-ins-v-huddleston-tnmd-1943.