Stalker Bros. v. Alcoa Concrete Masonry, Inc.

30 A.3d 885, 422 Md. 410, 2011 Md. LEXIS 641
CourtCourt of Appeals of Maryland
DecidedOctober 24, 2011
DocketNo. 57
StatusPublished
Cited by1 cases

This text of 30 A.3d 885 (Stalker Bros. v. Alcoa Concrete Masonry, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stalker Bros. v. Alcoa Concrete Masonry, Inc., 30 A.3d 885, 422 Md. 410, 2011 Md. LEXIS 641 (Md. 2011).

Opinion

MURPHY, J.

In' the Circuit Court for Montgomery County, Alcoa Concrete Masonry, Inc., Respondent, (“Respondent”) filed a complaint against Stalker Brothers, Inc., Robert Stalker, and Donald Stalker, Petitioners (“Petitioners”), in which Respondent alleged that it was entitled to a judgment in the amount that Petitioners had agreed to pay for home improvement work that Respondent had performed as a subcontractor for Petitioners. That complaint was dismissed by the Circuit Court, but reinstated by the Court of Special Appeals in Alcoa Concrete & Masonry, Inc. v. Stalker Brothers, Inc., 191 Md. App. 596, 993 A.2d 136 (2010). Petitioners then filed a petition for writ of certiorari, in which they presented this Court with three questions:

Whether an unlicensed subcontractor’s claim for nonpayment should be honored by a Maryland court in view of more than ninety years of Maryland Court of Appeals precedent refusing to honor claims of unlicensed entities under regulatory licensing requirements[?]
Whether the Court of Special Appeals erred in failing to adhere to principles of stare decisis and follow the precedent of the Court of Appeals[?]
Whether the Court of Special Appeals erred in interpreting the Maryland Home Improvement [Law (the Act), Maryland Code (1975, 2004 Repl.Vol.), §§ 8-101 through 8-702 of the Business Regulation Article (BR) ] in a manner inconsistent with Court of Appeals precedent, and in a manner which is internally eontradictory[?]

We granted the petition. 415 Md. 41, 997 A.2d 791 (2010). For the reasons that follow, our answer to Petitioners’ first [413]*413question is “yes, when the unlicensed subcontractor’s claim is asserted against the general contractor rather than against the homeowner,” and our answer to both Petitioners’ second and third questions is “no.” We shall therefore affirm the judgment of the Court of Special Appeals.

Background

The complaint at issue includes the following assertions:

3. From 2004 through 2007, Alcoa Concrete and Masonry, Inc. and the Stalker Brothers have been doing business together with the Stalker Brothers acting as General Contractor and Alcoa Concrete and Masonry, Inc. as a subcontractor on select Stalker Brothers construction projects.
4. In 2004, when the Parties began working together, all invoices submitted upon completion of work by Alcoa were paid by the Stalker Brothers in full on a regular basis[.]
5. In 2005, the payments from Stalker Brothers to Alcoa were paid on a less regular basis and/or were not paid in full as they had been at the onset.
6. Complaints from Alcoa to the Stalker Brothers were met with a response that the Stalker Brothers had financial difficulties and when they were resolved and/or a building they personally owned in Gaithersburg was refinanced, all past due invoices would be paid in full.
7. Thus, inasmuch as the Stalker Brothers had, at the onset, kept their word and promises regarding payment of invoices, Plaintiff Alcoa relied on this fact and never used its legal right to place liens on properties where they had done work as a subcontractor to the Stalker Brothers but had not been paid.
8. Furthermore, an agreement whereby Defendants Stalker Bros, would reimburse the Plaintiff Alcoa $1500/week for past due invoices plus all new invoices in full was reached between the parties.
9. In November 2006 Plaintiff Alcoa began working -with the Defendants on the Cahill project. Defendant informed Plaintiff that there would be sufficient profit in this project [414]*414to pay Plaintiff for all past due invoices plus the invoice for the Cahill job on time. Accordingly, assuming that the Defendant was acting in good faith, Plaintiff Alcoa took no further action to collect on past invoices at that time.
10. As Alcoa began the final work on the Cahill project, the Defendant informed Alcoa that they were closing their business and would be declaring bankruptcy.
11. In summer 2007 the Stalker Brothers stopped paying for both new work and previous invoices.
12. Plaintiff Alcoa immediately contacted Defendant Stalker Brothers who promised that all past work' done for their firm would be paid in full when the Gaithersburg building owed [sic] by Robert N. Stalker and Donald C. Stalker was sold.
13. According to information available through the Maryland Department of Assessments and Taxation, a building owned by the Stalker brothers (through Traverse LLC) was sold for the sum of $2,143,000 on or about January 2, 2008.
16. Plaintiff has information and belief that the Defendants signed Releases of Liens with all or some of the businesses and homeowners for whom the Plaintiff worked as a subcontractor for the Defendant and received full payment for work done by Alcoa for Stalker contracts.
17. These Releases of Liens included attestations by the owners of residences or businesses that the work contracted for had been done in a satisfactory manner and, in exchange acknowledgments were signed by Stalker Brothers that all subcontractors had been paid for their work on the projects.
18. The Stalker Brothers, Inc., and the Stalker brothers individually signed these documents knowing full well that they had failed to pay all their subcontractors—including Alcoa Concrete and Masonry, Inc.—and that by falsely signing these documents they were intentionally misrepresenting the facts to the property owners and using these [415]*415falsehoods to obtain (and keep funds) that were not their rightful property.
20. Alcoa Concrete has incurred a loss of $53,700 plus interest and attorney’s fees as a result of the breach of contract by Stalker Brothers, Inc. and Robert N. Stalker and Donald C. Stalker, individually.
22. Defendants Stalker Brothers accepted money from property owners for work completed by Plaintiff Alcoa and refused to pay Plaintiff Alcoa the money due on the contracts that had been performed by Alcoa as subcontractors on these jobs.
25. Defendant Stalker Brothers intentionally and maliciously committed fraud against Alcoa by continuously promising to make good on past due accounts when they knew hat they had no intention of keeping their promises.
26. Defendant Stalker Brothers intentionally paid invoices and made promises to Alcoa which they knew were untrue in order to coerce the Plaintiff into doing more work for the Defendant which the Defendants had no intention of paying for.
29. It is our information and belief that, irrespective of what the Stalker Brothers alleged, no bankruptcy was ever filed by or for the Stalker Brothers, Inc. and this was another fraudulent act, a subterfuge used by the Stalker Brothers to avoid paying Alcoa monies due for work completed and to try to coerce the Plaintiff into settling on pennies on the dollar rather than the full amount due for work done for the Stalker Brothers, Inc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Feldman's Medical Center Pharmacy, Inc. v. CareFirst, Inc.
898 F. Supp. 2d 883 (D. Maryland, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
30 A.3d 885, 422 Md. 410, 2011 Md. LEXIS 641, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stalker-bros-v-alcoa-concrete-masonry-inc-md-2011.