Staley v. Bogner Constuction Company, Unpublished Decision (01-30-2002)

CourtOhio Court of Appeals
DecidedJanuary 30, 2002
DocketC.A. No. 01CA0032.
StatusUnpublished

This text of Staley v. Bogner Constuction Company, Unpublished Decision (01-30-2002) (Staley v. Bogner Constuction Company, Unpublished Decision (01-30-2002)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Staley v. Bogner Constuction Company, Unpublished Decision (01-30-2002), (Ohio Ct. App. 2002).

Opinion

This cause was heard upon the record in the trial court. Each error assigned has been reviewed and the following disposition is made: Appellant, Pennie Graham-Staley, appeals from the decision of the Wayne County Court of Common Pleas, granting summary judgment to appellees, Bogner Construction Company ("Bogner") and Alfred Barto, d.b.a. Barto Decorating, ("Barto"). We affirm.

On January 5, 1999, Ms. Graham-Staley, who was employed by the J.M. Smucker Company ("Smuckers"), was being trained in a position referred to as PC cook. On the day in question, Ms. Graham-Staley had been training in her new position for five hours and was putting ingredients into a mixing bowl when she fell on the floor and injured herself. This was her first day of work since she had returned from her Christmas vacation. In her deposition, Ms. Graham-Staley stated that she had noticed that the floor was slippery earlier in the day and was told by a co-worker that a complaint had been made to the supervisor at Smuckers to remedy the situation.

At the time of the accident, Bogner had been acting as Smuckers' general contractor for several years and had been given a project in July of 1998 to undertake some repair work at the Smuckers plant during a plant shutdown period. As part of the floor repair project, Bogner hired Barto to act as a subcontractor. Barto's job entailed painting the entire floor area of the plant with paint and an aggregate, an abrasive grit substance which made the floor less slippery.

In his deposition, Charles Armbruster, a manager at Smuckers, stated that the plant floors are repainted approximately once every two years and that the wet floors in the plant should not be slippery due to the application of the aggregate. However, Mr. Armbruster acknowledged that, prior to the repainting of the floors in July of 1998, employees had fallen in the cookroom and complained that the floor surface was slippery. Mr. Armbruster explained that, in the process of making jelly, ingredients could fall on the floor and would need to be cleaned up with either water or chemicals. Mr. Armbruster stated that both Bogner and Barto came back at the end of December 1998 to work on the floors following their initial repair work done in July. As was the routine practice of Smuckers, after the floor was redone, Mr. Armbruster personally inspected the work and found that there was aggregate in every area that he looked. Specifically, in his deposition, Mr. Armbruster acknowledged that, while his personal experience would have led him to apply even more aggregate, his inspection led him to believe that the aggregate had been applied in a satisfactory manner.

Richard Stofer, who worked for Bogner prior to his retirement, stated in his deposition that he had met with Mr. Armbruster prior to the July work to discuss Smuckers' job specifications. He stated that Mr. Armbruster gave him job instructions and told him that Smuckers would provide the necessary materials. He also stated that Smuckers had asked both Bogner and Barto to come back at the end of December 1998 to redo part of the work completed in July of that year. Mr. Stofer explained that, as soon as the floor work was done in July, he received a call from Mr. Armbruster during which Mr. Armbruster told him that the floor work completed in July was not satisfactory. However, Mr. Stofer stated that, when Barto got the chance to redo the floors of the plant during the slowdown of the Christmas season, the aggregate was applied evenly over the surfaces of the floor and that he did not receive any complaints from Mr. Armbruster. Mr. Stofer further elaborated that, despite this even application of aggregate, he had been informed by Smuckers that employees had still slipped on the plant floors.

Alfred Barto, the owner of Barto Decorating, testified that his company had an ongoing business relationship with Bogner. When his company agreed to repaint the floors at Smuckers, Barto had not previously done this type of project, but Mr. Barto was assured by a Smuckers maintenance man that he would explain the entire process to Barto before the work was undertaken. Additionally, Mr. Barto stated that the preparatory work, such as washing and cleaning the floors, was completed by Smuckers prior to the paint application. Mr. Barto testified that Smuckers provided the necessary materials for the application of paint. Mr. Barto explained that his company did not get to properly complete their work in July 1998 due to numerous problems which included water and tools spread over the floor as well as interference caused by other people working in the Smuckers plant. Mr. Barto stated that his company informed Bogner of their inability to properly complete the job in July. The situation was remedied, Mr. Barto explained, when Barto was allowed to work on the entire floor area in December. Mr. Barto stated that, after Ms. Graham-Staley fell, he contacted Kurt Block, the manufacturer of the products supplied by Smuckers which were used to cover the floors. Mr. Block came to the Smuckers plant to inspect the work done in December 1998 and informed Mr. Barto that the paint and aggregate application had been done correctly.

In his deposition, Timothy Conyers, the person employed by Barto to repaint the floors, agreed that the work done in July of 1998 had not been properly completed because the floors were too wet. He stated that, though there were still a few puddles of water when he went back, he was able to apply the aggregate everywhere in his December application of the paint. Mr. Conyers admitted that he had never done a paint job in the manner required for this project; however, he stated that he followed the directions given to him by an employee of Smuckers. He also stated that the materials he used to paint the floor surface were already at the work site when he arrived. Mr. Conyers explained that, on his first day at the plant, he met with a Smuckers employee who showed him how to mix the products and where the mixing drill was located. According to Mr. Conyers, the Smuckers employee also showed him an example of a properly coated floor. This employee, Mr. Conyers stated, had even begun the trim work around the edges of the floor where Barto was supposed to paint. When asked, Mr. Conyers stated that he relied on the Smuckers employee in his paint application and that he received neither products nor advice from Bogner. Mr. Conyers acknowledged that, despite following the directions given to him and his even application of aggregate, some areas in the plant could still become slippery as the employees undertook their production tasks.

Daniel Facemire, employed in the maintenance department at Smuckers, stated in his deposition that he believed that the plant floor was very slippery in January 1999. He stated that he personally fell several times after he returned from the Christmas slowdown and that he informed his supervisors of the problem. Mr. Facemire related that, as employees of Smuckers fill the mixing kettles to make jelly and other products, there are spillovers which are constantly being hosed down with water. When asked, Mr. Facemire stated that the floor was in fact slippery due to the water.

On June 27, 2000, Ms. Graham-Staley filed a complaint in the Wayne County Court of Common Pleas, naming as defendants Bogner and Barto. On August 2, 2000, Bogner filed an answer to Ms. Graham-Staley's complaint denying liability. Barto also denied any liability in its response filed on August 17, 2000. Ms. Graham-Staley filed an amended complaint on November 27, 2000 to which both Bogner and Barto again denied liability.

On April 16, 2001, Bogner moved for summary judgment. A motion for summary judgment was also filed on behalf of Barto on the same date. On May 7, 2001, Ms. Graham-Staley filed a brief in opposition to the summary judgment motions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Feichtner v. City of Cleveland
642 N.E.2d 657 (Ohio Court of Appeals, 1994)
Henkle v. Henkle
600 N.E.2d 791 (Ohio Court of Appeals, 1991)
Keister v. Park Centre Lanes
443 N.E.2d 532 (Ohio Court of Appeals, 1981)
McKay v. Cutlip
609 N.E.2d 1272 (Ohio Court of Appeals, 1992)
Jackson v. City of Franklin
554 N.E.2d 932 (Ohio Court of Appeals, 1988)
Temple v. Wean United, Inc.
364 N.E.2d 267 (Ohio Supreme Court, 1977)
Menifee v. Ohio Welding Products, Inc.
472 N.E.2d 707 (Ohio Supreme Court, 1984)
Mussivand v. David
544 N.E.2d 265 (Ohio Supreme Court, 1989)
Dresher v. Burt
662 N.E.2d 264 (Ohio Supreme Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
Staley v. Bogner Constuction Company, Unpublished Decision (01-30-2002), Counsel Stack Legal Research, https://law.counselstack.com/opinion/staley-v-bogner-constuction-company-unpublished-decision-01-30-2002-ohioctapp-2002.