Stahlhut v. Sirloin Stockade, Inc.

568 S.W.2d 269, 1978 Mo. App. LEXIS 2111
CourtMissouri Court of Appeals
DecidedJune 12, 1978
DocketNos. KCD 28486, KCD 28502
StatusPublished
Cited by3 cases

This text of 568 S.W.2d 269 (Stahlhut v. Sirloin Stockade, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stahlhut v. Sirloin Stockade, Inc., 568 S.W.2d 269, 1978 Mo. App. LEXIS 2111 (Mo. Ct. App. 1978).

Opinion

ROBERT R. WELBORN, Special Judge.

Actions by subcontractors to establish mechanics’ liens and for recovery on surety bonds on construction project. Trial court upon trial of claims there consolidated refused to allow mechanics’ liens but entered judgment in favor of subcontractors on performance bond. Surety on bond appeals.

On September 18, 1972, C. F. Moreland Construction Company, a Missouri partnership composed of C. F. Moreland and Keith [271]*271Crawford, entered into a contract with Sirloin Stockade, Inc., for the construction by Moreland of a building for Sirloin in War-rensburg. The contract price was $82,-820.00. The contract required Moreland to furnish a bond to protect the owner against loss occasioned by mechanics’ liens and against loss on account of materials or labor furnished for the project.

Moreland obtained two bonds from The Home Indemnity Company. One was a performance bond, the other a payment bond.

Moreland began work on the project and completed the site work in January, 1973. The work was held up because of changes in the building plan.

On January 24, 1973, a corporation was organized under Texas law by three otherwise unidentified incorporators. The name of the corporation was T.M.C. Construction & Investment, Inc. Moreland, Crawford and Grady Truitt were named as original directors of the corporation. In April, 1973, Home issued endorsements on workmen’s compensation and contractor’s general liability policies issued by it to Moreland by which T.M.C. was added as a named insured under the policies.

Although there was no formal assignment of the contract between Sirloin and Moreland, according to Crawford, T.M.C. took over the Warrensburg project as the general contractor.

Under date of April 6, 1973, T.M.C. entered into three Sub-contract Agreements with Kenneth Stahlhut on the Warrensburg job. One was for complete roofing, at a contract price of $3,500.00. The second was for masonry work, at a contract price of $10,900.00. The third was for sheet rock at $2,600.00. Stahlhut began work on the project. He billed T.M.C. for progress payments and received payment from T.M.C. He also received one payment from More-land Crawford Corporation, Inc., by a check which was returned for insufficient funds. The amount of the check was eventually paid.

Some date prior to October 16, 1973, Stahlhut submitted his final request for payment to T.M.C. in the amount of $6,049.44. This included the amount due and unpaid under his three subcontracts, plus $246.21 claimed due for extra work. T.M.C., on October 16, 1973, advised Stahl-hut that it had paid Stahlhut’s suppliers $2,032.02 which should be credited against the amount claimed by Stahlhut. T.M.C. also rejected the claim for extra work and told Stahlhut that the amount owed him was $3,671.28.

On July 30, 1973, Martin Brothers Tile Company entered into a written subcontract agreement with T.M.C. under which Martin was to provide labor and material for installation of ceramic and quarry tile on the Warrensburg job for a contract price of $5,193.00. Martin began work under the contract on July 30 and completed its contract November 1, 1973.

As the Warrensburg job progressed, Sirloin dealt with T.M.C. It forwarded a revised plot plan for the project to T.M.C. on July 12, 1973. On July 25, 1973, it issued change orders to T.M.C. One payment for work was made by Sirloin to T.M.C.

The Warrensburg job was beset with difficulties almost from the outset. A problem arose with regard to the location of the building which required changes in the foundation and footings after they had been laid. As early as April, 1973, Sirloin advised Home that complaints had been received that the contractor was not paying his bills. Difficulties with the contractor continued and on September 6, 1973, an attorney for Home addressed a letter to Moreland and T.M.G. Construction & Investment, referring to the bonds issued by Home and complaints which had been received about unpaid bills. On the same date, Sirloin notified the attorney for Home that it appeared that the contractor would be able to finish the job.

Earl Ulmer, construction coordinator for Sirloin, first visited the job in the latter part of September, 1973. He found much of the work which had been done unacceptable. Little work was being done. Bills were unpaid. He could not find Mr. More-land or Mr. Crawford. He got in touch [272]*272with Home in October and told them he did not think the job was being done right. Home’s attorney asked him to work with Mr. Hudson. Ulmer and Hudson went over the job on October 28 and the decision was made to terminate the construction contract.

On November 1, Stahlhut entered into a fourth subcontract with T.M.C., dated November 1, 1973, by which Stahlhut agreed to do the work necessary to complete the building for $16,500.00. According to Stahlhut, he discussed the contract with Moreland and Crawford before it was executed on behalf of T.M.C. by the job superintendent.

Jim Jenkins, whom Sirloin had hired as their job superintendent, learned of Stahl-hut’s contract and got in touch with Ulmer. Ulmer and Hudson came to Warrensburg on November 7 and met with Stahlhut and some suppliers who had not been paid for materials used on the job. According to Stahlhut, he told them of the amount due under his first three contracts. The fourth contract was discussed. Ulmer first told him that he did not know whether he could go along with that contract or not. After a telephone call, presumably to a Sirloin superior in Oklahoma City, Ulmer said, according to Stahlhut, for Stahlhut to go ahead and finish the job as soon as possible and “that one of them (Sirloin or Home) would have to pay me.”

Ulmer’s version of the conversation was somewhat different. According to him, after he returned to Oklahoma City following the October 28th meeting with Hudson, notice of termination of the contract was prepared and mailed to all interested parties, including T.M.C., Moreland and Home. Under the terms of the contract, ten days’ notice of cancellation was required and that time had not passed at the time of the November 7th meeting. He told Stahlhut that, since Sirloin could not yet take over the job, he could not stop him from working and that if he felt that he had a bona fide contract with T.M.C. and was satisfied he was going to get his money, Sirloin could not at that time stop him from working. He told Stahlhut: “I’m assuming that somebody has got to pay you if you work, if you do this work and it is acceptable, why then someone is going to pay you and probably it would be the bonding company. It is certainly not going to be the Sirloin Stockade.”

By letter dated November 9, 1973, Sirloin’s general counsel advised Stahlhut that it had declared its contract with Moreland in default. “We have never been advised what TMC Construction and Investment, Inc. legally has to do with the construction of our building and, therefore, cannot recognize your subcontract with TMC * * .”

After receiving the letter, Stahlhut called Ulmer and talked to him. According to Ulmer, he again told Stahlhut that Sirloin could do nothing until the ten-day notice period had expired and that Ulmer could neither tell him to work or not to work on the job. He told Stahlhut that whatever work he did before the expiration of the notice period would have to be paid for by someone but that Sirloin would not pay him.

According to Stahlhut, he began working toward completion of the building.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Augusta Court Co-Owners' Ass'n v. Levin, Roth & Kasner, P.C.
971 S.W.2d 119 (Court of Appeals of Texas, 1998)
Kansas City NO Nelson Co. v. MID-WESTERN CONSTRUCTION CO. OF MO., INC.
782 S.W.2d 672 (Missouri Court of Appeals, 1989)
Kunkle Water & Electric, Inc. v. Nehai Tonkayea Lake Ass'n
639 S.W.2d 177 (Missouri Court of Appeals, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
568 S.W.2d 269, 1978 Mo. App. LEXIS 2111, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stahlhut-v-sirloin-stockade-inc-moctapp-1978.