Stahelin v. Sowle

49 N.W. 529, 87 Mich. 124, 1891 Mich. LEXIS 755
CourtMichigan Supreme Court
DecidedJuly 28, 1891
StatusPublished
Cited by20 cases

This text of 49 N.W. 529 (Stahelin v. Sowle) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stahelin v. Sowle, 49 N.W. 529, 87 Mich. 124, 1891 Mich. LEXIS 755 (Mich. 1891).

Opinion

Champlin, C. J.

The declaration claims damages for being prevented from performing a contract.

The plea was the general issue, with a notice that the plaintiff had violated his agreement as mentioned and set forth in his declaration, specifying with particularity wherein he had failed to comply with the agreement, and alleging that—

“At. the time the agreement was made the defendant had a large contract to furnish ties; that he purchased and owned the trees, 'logs, and timber on the ‘Schaffer lot,’ so called; that the same was purchased for the purpose of cutting up into ties; that the white-oak logs, trees, and timber thereon were contracted to plaintiff by defendant, to be cut and sawed up into ties and delivered to defendant; that plaintiff agreed to cut the same into ties for defendant; that plaintiff commenced to cut the said white-oak timber into lengths not suitable forties, and thereby wasted the same; that plaintiff cut the white-oak logs, timber, and trees thereon, and manufactured the same-into other kinds of lumber than for' ties, and sold and converted the same to his own use, . and deprived defendant of his profits and ties therein; ” and that he is indebted to the defendant for the price and value of such trees and lumber; and that [126]*126by reason of his not fulfilling the contract, defendant has sustained damages, which he would recoup against any claim the plaintiff might establish upon the trial.”

There were two contracts declared upon in the plaintiff’s declaration. The first bears date the 5th day of November, 1886, in which plaintiff agreed to move his saw-mill on to Michael Houser’s land, of Bridgman, Mich., and put the mill in good running order, and saw for defendant, and no other person, as long as defendant stocked the mill, for the sum of $8 per thousand feet for all logs except tie logs.' Ties were to be sawed for the sum of eight cents apiece. The side boards of the tie logs were to be sawed free and edged up. Plaintiff agreed not to buy or offer to buy any white or burr oak logs or timber for a term of 18 months, if the defendant stocked the mill. The contract contained other provisions not material to state here. The work of putting in the logs, sawingj and all work for both parties, was to be done in a workman-like manner. The plaintiff agreed to put all the logs on the Houser lot from the woods on skids at the sum of 2% cents for each 9-foot tie, and logs at the same ratio, 2|- cents for each 9 feet in length. The parties went on under this agreement, and the plaintiff put in a certain quantity of ties, for which he received his payment in full. He claims, however, that for the timber which he cut under that contract there was due him from the defendant $124. After this job was completed, they entered into another contract, as follows:

“Lake Tp., Berrien Co., Mich., March 18, 1887.
“We do hereby agree to sell to Charles W. Stahelin all the white oak timber that we buy in the neighborhood of his mill, except the Joshua Feather and Walton’s, at what it costs us, and charge him at the rate of ten per cent, interest from date of payment for said timber; and also agree to pay him for all of the timber [127]*127made into M. 0. E. E. ties, delivered on cars at Morris ■or Stevensville, if we can get the same rates at Stevens-ville as we have at Morris, 40 cents per No. 1, 20 cents per No 2, subject to the M. C. E. E. inspection; ties to he sawed six by ten, 9 feet long.
“J. M. Sowle & Co.”

The defendant, Joseph M. Sowle, was doing business ■under the name of J. M. Sowle & Co., and was engaged in getting out and furnishing ties to the Michigan Central Eailroad. Upon the trial of the cause it appeared that the defendant, Sowle, purchased two parcels of land for $650, and it was estimated that the quantity of ties upon these parcels of land would be 6,500, — 3,000 upon ■one piece, and 3,500 upon the other. The plaintiff testified that at the time the first contract was signed the ■defendant said to him:

“‘I want you to crowd things. You are a pusher, and I want you to crowd it ahead, because I have got to have a certain amount’ — I' think 'he said — ‘of ties ■out,’ so he would get his percentage, the 1st of January. The way I understood, he had three terms, — you might ■say three months, three distinct terms. He got in a certain amount every term; something that way.”

The witness further testified:

“Either a few days before or a few days after this paper [the second contract] was made, that Schaffer piece of timber was bought. I only knew it was bought by Sowle’s saying so. Sowle came to my house, and called my attention. Told me he had been over the Schaffer piece. Asked whether I was willing to stand the price, —one piece $300, and the other $350. I knew what the timber was pretty well. I was willing to pay the price. Sowle "said he would send' the money right away. The money came; cannot say whether it was two or three days, or a week, — a short time. Mr. Sowle’s foreman went over with me. Saw Mr. Schaffer. He showed us the lines to cut the timber. When I- went in first, I went to making roads. We made a road diagonally through the piece, and then cut branch roads. I kept a memorandum of the business of cutting out the roads. [128]*128It cost me about $25. The other work cost me in the neighborhood of $25. I commenced cutting the timber off probably that very afternoon. Tucker and Schaffer showed us the line. I furnished to Sowle, at Morris Station, in the neighborhood of 1,000 ties. Did not all come from the Schaffer lot. I furnished 1,000 No. 1 ties, equal to $400.”

The witness then testified tending to prove how much it cost to manufacture ties at his mill; what he paid cutters, hauling, and repairs at the mill, leather, oil, etc.; the number of teams he owned and hired, and what he had to pay for them. He also testified that his mill had a capacity and would cut in an average day’s work 400 ties a day; that, after he had been at work some 13-days, he received a notification forom J. M. Sowle & Co., as follows:

“Mr. Stahelin: Please stop cutting and hauling. If you want to, saw what is in the yard cut at nine cents for No. 1, four and one-half for No. 2. Our contract is broken, and we have another mill to cut those logs.
“J. M. Sowle & Co.”

He further testified that he continued to cut after receiving this notice, until he was prevented by their putting a gate across the road and locking it up, and sending men there to prevent his further continuing the job.

The defendant testified in his own behalf as follows:

My ■ business is general lumbering. Have been in that business 42 years. Have been stocking mills in Berrien county. Know Mr. Stahelin. I made the contract mentioned here. Saw Mr. Stahelin first here in Berrien Springs in the month of October, 1886, in reference to lumber. I was cutting and shipping ties to the Michigan Central Railroad. He asked me to come down there and buy timber around his mill, and stock him up. I went down after that, and bought some timber, the latter part of October, three or four little pieces, and went to putting it into the mill at Bridgman. After I bought [129]*129the Houser lot, he came to me twice, and wanted to do that sawing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Michigan Bank, National Ass'n v. William J. Kahlich, Inc.
179 N.W.2d 29 (Michigan Court of Appeals, 1970)
Baith v. Knapp-Stiles, Inc.
156 N.W.2d 575 (Michigan Supreme Court, 1968)
McCarty C. Mercury Metalcraft Co.
127 N.W.2d 340 (Michigan Supreme Court, 1964)
Martin v. Miller
57 N.W.2d 878 (Michigan Supreme Court, 1953)
Ehlinger v. Bodi Lake Lumber Co.
36 N.W.2d 311 (Michigan Supreme Court, 1949)
Beaman v. Testori
35 N.W.2d 155 (Michigan Supreme Court, 1948)
Brady v. Central Excavators, Inc.
25 N.W.2d 630 (Michigan Supreme Court, 1947)
Gladden v. Keistler
140 S.E. 161 (Supreme Court of South Carolina, 1927)
Sparks v. Lord
164 N.W. 490 (Michigan Supreme Court, 1917)
Paine v. Parkhurst
205 F. 740 (Sixth Circuit, 1913)
Smith v. Pickands
112 N.W. 122 (Michigan Supreme Court, 1907)
Beld v. Darst
109 N.W. 275 (Michigan Supreme Court, 1906)
McCall Co. v. Jacobson
102 N.W. 969 (Michigan Supreme Court, 1905)
Crowley v. Langdon
86 N.W. 391 (Michigan Supreme Court, 1901)
West v. Bechtel
51 L.R.A. 791 (Michigan Supreme Court, 1900)
Mouat v. Montague
81 N.W. 112 (Michigan Supreme Court, 1899)
Smiley v. Barker
83 F. 684 (Eighth Circuit, 1897)
Reynolds v. Manhattan Trust Co.
83 F. 593 (Eighth Circuit, 1897)
Milligan v. Sligh Furniture Co.
70 N.W. 133 (Michigan Supreme Court, 1897)

Cite This Page — Counsel Stack

Bluebook (online)
49 N.W. 529, 87 Mich. 124, 1891 Mich. LEXIS 755, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stahelin-v-sowle-mich-1891.