Staffco Const. v. Creative Sunroom, Unpublished Decision (10-15-1999)

CourtOhio Court of Appeals
DecidedOctober 15, 1999
DocketC.A. Case No. 17738. T.C. Case No. 98-CVF-2993.
StatusUnpublished

This text of Staffco Const. v. Creative Sunroom, Unpublished Decision (10-15-1999) (Staffco Const. v. Creative Sunroom, Unpublished Decision (10-15-1999)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Staffco Const. v. Creative Sunroom, Unpublished Decision (10-15-1999), (Ohio Ct. App. 1999).

Opinion

OPINION
This case is before us on the appeal of Creative Sunroom Designs, Inc. (Creative) from a judgment in the amount of $2,931.98, plus costs, in favor of Staffco Construction, Inc. (Staffco). The dispute between Creative and Staffco arose in connection with a renovation project at Masgig Middle School in Centerville, Ohio. Staffco prepared a bid for the Masgig project as a general contractor. According to the architect's specifications, three prefabricated greenhouse window units manufactured by Four Seasons were to be included in the bid. Because Creative was the local retailer for Four Seasons, Staffco's project manager, Susan Reenan, called Creative about submitting a bid for the greenhouse windows. Subsequently, Creative gave Staffco a bid of $14,498 for materials and labor. Staffco then used this bid as part of its overall bid on the project. After Staffco was awarded the project, Creative wanted more money for the greenhouse windows. When the matter could not be resolved, Staffco used a different window manufacturer and installer, and sued Creative for the additional expenses that were incurred.

Following a bench trial, the court found that Staffco had reasonably relied on Creative's bid and that the terms of the subcontract bid would be enforced under the doctrine of promissory estoppel. Creative now appeals, claiming as its single assignment of error that the trial court erred in finding Creative liable to Staffco. To support this assignment of error, Creative raises two issues. First, Creative contends that promissory estoppel cannot be used to alter the terms of a bid proposal submitted by a subcontractor to a general contractor. Second, Creative claims the trial court abused its discretion in this case by finding that Staffco reasonably interpreted the subcontract bid to include terms and specifications in the specification book. We find both these arguments without merit and affirm the judgment of the trial court.

I
As a preliminary point, we note that Creative has classified its promissory estoppel argument as one of "law," not fact. This potential distinction is important, because if a legal question is involved, we can substitute our judgment for that of the trial court. See, e.g., Lewis v. Ohio Real Estate Comm. (1997),121 Ohio App.3d 23, 28. On the other hand, we must give deference to factual findings, since the trial court has a better opportunity to assess credibility. Gibson v. Gibson (Mar. 26, 1996), Clark App. No. 95CA87, unreported. After considering the matter, we believe Creative's promissory estoppel argument is factual, not legal.

In this regard, we note that Creative concedes that promissory estoppel may bind a subcontractor to the terms of its original offer. This is consistent with the trial court's decision, which relied on the principle that:

[a] subcontractor who makes a `bid' or `quote' which constitutes an offer to a general contractor, who submits a bid in reliance upon such offer, is bound to perform in accordance with the terms of that offer when the general contractor (1) is awarded the contract and (2) within a reasonable time thereafter notifies the subcontractor that the offer is accepted.

Wargo Builders, Inc. v. Douglas L. Cox Plumbing Heating, Inc. (1971), 26 Ohio App.2d 1. See also, R.P. Carbone Constr. Co. v.N. Coast Concrete (1993), 88 Ohio App.3d 505. Despite agreeing with this general proposition, Creative says promissory estoppel is inapplicable because Staffco added terms and work to the original contract.

We consider this a fact-based argument, i.e., it depends on a choice between conflicting versions of the facts. For example, the trial testimony of Dale Thornberry, Creative's President, supports the claim that Staffco added to the original bid. By contrast, testimony from Staffco witnesses conflicts with Thornberry's account and supports a finding that Creative should be bound by the bid it submitted. Therefore, we interpret Creative's argument, regardless of how it is phrased, as a claim that the trial court decision was against the weight of the evidence. Our role in that event is to decide if the trial court's judgment is supported by "some competent, credible evidence going to all the essential elements of the case." Reed v.Key-Chrysler Plymouth (1998), 125 Ohio App.3d 437, 439 (citations omitted).

The dispute in the present case is based on the fact that Creative's original bid did not include the price of awning or vented windows, as required by the Masgig project specifications and plans. In this context, the following facts (and contested facts, where noted) are pertinent. After Staffco's project manager, Susan Reenan, first contacted Creative about a bid, she sent Creative some project specifications for the greenhouse window units. Project specifications come in a complete bound set and each division of work has a specific number. Because the greenhouse window units were a specialty item, they were in the speciality division. Complete copies of the specifications and drawings for a particular project are typically in the hands of all general contractors bidding on the project, as well as the architect. Subcontractors can review plans and specifications through these sources. They can also review them at the Builder's Exchange, or through the Dodge Report, which provides information on projects for a fee.

The specifications Reenan sent Creative were the particular pages dealing with the requirements for the greenhouse windows. Additionally, Reenan sent elevation drawings of the units. Creative's sales representative, Bill Hansford, then prepared and gave a bid to Staffco about two hours before Staffco's overall bid on the project was due. Consistent with procedures generally followed in the construction industry during bidding, Reenan incorporated this bid as one of many when making the overall bid ($1,396,000) for the project. Creative's bid was one of two Reenan received for the greenhouse windows, but the other bidder used windows from a different manufacturer. Consequently, Reenan decided not to use that bid, which was also higher than the Creative bid. At least fifteen different trades sent in subcontract bids the day the overall bid was due, and many trade areas had multiple bidders. According to Reenan, about 99% of subcontract bids come in on the due date for the overall bid, and the general contractor relies on subcontractors to prepare bids complying with the specifications and drawings for the project.

The Masgig specifications listed the required greenhouse window unit as "Model CLT 3GG," but did not explicitly mention vents. However, the elevation drawings showed an inverted "V" on some sections, meaning that the unit would contain an awning or operable vent. In the bid submitted to Staffco, Creative said it would supply and install three Model CLT 3GG sunrooms of the size indicated in the specifications, again for a price of $14,498. After the bid arrived, Reenan checked the model number on the bid and noted that it matched the model number in the specifications. Reenan testified that she had no reason to believe Creative's bid was inaccurate, since the model numbers matched.

On September 15, 1997, Staffco was awarded the contract. Staffco then sent Creative a standard subcontract agreement dated September 22, 1997. Construction was scheduled to start October 1, 1997, and was projected to last through the following summer, or until about August 22, 1998.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lewis v. Ohio Real Estate Commission
698 N.E.2d 1023 (Ohio Court of Appeals, 1997)
Reed v. Key-Chrysler Plymouth
708 N.E.2d 1021 (Ohio Court of Appeals, 1998)
R.P. Carbone Construction Co. v. North Coast Concrete, Inc.
624 N.E.2d 326 (Ohio Court of Appeals, 1993)
Wargo Builders, Inc. v. Douglas L. Cox Plumbing & Heating, Inc.
268 N.E.2d 597 (Ohio Court of Appeals, 1971)
Blakemore v. Blakemore
450 N.E.2d 1140 (Ohio Supreme Court, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
Staffco Const. v. Creative Sunroom, Unpublished Decision (10-15-1999), Counsel Stack Legal Research, https://law.counselstack.com/opinion/staffco-const-v-creative-sunroom-unpublished-decision-10-15-1999-ohioctapp-1999.