This text of 277 N.W.2d 769 (Stack Construction Co v. Continental Construction Corp.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stack Construction Co v. Continental Construction Corp., 277 N.W.2d 769, 88 Wis. 2d 637, 1979 Wisc. LEXIS 1972 (Wis. 1979).

Opinion

*639 HEFFERNAN, J.

The only question presented on this appeal is whether the plaintiff subcontractor, Stack Construction Company, which had no obligation under the original contract to dig post holes, entered into a subsequent agreement with the general contractor, Continental Construction Corp., whereby Stack agreed to dig the post holes and Continental agreed to pay for the work. We conclude that no contract of any nature for the digging of post holes was entered into between the parties. The judgment dismissing Stack’s complaint must therefore be affirmed.

The record shows that Continental Construction Corp. was the general contractor for the Willow Creek Homes Project. In March of 1971, the Stack Construction Company entered into a contract with Continental to do the earth work on the project. After the work was completed, Stack Construction Company commenced an action against Continental alleging that Continental owed it over $38,000 for contract work and extras. By stipulation of the parties, the various claims have been settled, with the exception of Stack’s "claim for compensation for digging more than 2,000 holes for fence posts. It is undisputed that the value of the work done in digging the fence-post holes is approximately $20,000.

At trial it was determined that Stack was not obligated under its contract to dig the post holes. The correctness of the trial court’s determination is not disputed on this appeal. The only question on this appeal is whether Stack was induced to dig the post holes and Continental agreed to pay for the work.

The original contract between the parties contained this provision in respect to Stack’s obligation:

“Excavate to elevations and dimensions indicated for footings, foundations, drives, walks and other works shown, plus sufficient space to permit erection of forms, shoring, dampproofing and inspection of foundations.”

*640 On the basis of commonly accepted usage in the contracting business, which was shown by evidence at trial, the court concluded that Stack had no obligation under the contract to dig the post holes. The factual basis for this conclusion was not contrary to the great weight and clear preponderance of the evidence. The court’s decision in that respect is not at issue on this appeal.

The record shows, however, that, in July of 1971, the parties disagreed about Stack’s obligation to dig the post holes. The president of Stack informed the president of Continental that Stack did not think that digging the post holes was an obligation under the contract. Continental’s president testified that he told Stack’s president that the hole digging was Stack’s obligation under the contract. Continental’s president stated that Stack’s president’s response was that he wanted to read over the contract and to think about it. Continental’s president testified, “The next thing I knew, he [Stack] was digging posts.”

Stack never disputed that the post-hole digging was a part of its contract obligation until after the contract was completed. Stack’s president at trial asserted, however, that he never acquiesced in Continental’s interpretation that the hole digging was a part of the contract, and he stated that he frequently told Continental’s representative that he was not obligated by the contract to dig the holes. Stack’s president testified that he did the work only because he was told by Continental that, if he did not do the work, someone else would be hired and that Stack would be “back charged.” Stack said that its experience was that “back charging” would be about four times as expensive as the cost to do the work.

The contract also contained the following provision:

“Subcontractor [Stack] shall make no claim for additional work or materials unless done in pursuance of Written orders from the Contractor [Continental], and *641 pro-rated billings for any such claims shall be given to the Contractor in writing before the next ensuing payment or shall be considered as abandoned.”

Continental submitted no written orders for the post-hole digging, and Stack submitted no pro-rated bills as the post-hole digging was in progress.

Because it is now agreed that the original contract did not contemplate that Stack do the post-hole digging, the only question on this appeal is whether anything in the conduct of the parties at or following the time of the contract dispute in July of 1971 created an additional or new contract obligating Continental to pay for any post-hole digging done by Stack. In respect to this portion of the transaction, the trial court made the following findings of fact:

“If it was the plaintiff’s intent, when it undertook to do the work, that it would be entitled to additional compensation if it was later determined that the work was not part of the contract, this intent was unilateral and not based upon any agreement with the defendant.
“The defendant thought that the plaintiff had accepted its interpretation of the contract from the commencement of the digging of the postholes in the summer of 1971 until December of 1973. This is underlined by the fact that during this period of time, billings were submitted for the redigging of postholes but not for the original digging.”

On the basis of these findings the trial court concluded that the controlling factor was the absence of any agreement on the post-hole work. We agree with that conclusion of the trial court.

Stack, on this appeal, seeks to recover for the post-hole work on the theory that a second informal contract was formed. Stack underpins its arguments with the “reliance” theory of the Restatement 1 of Contracts, sec. 90, p. 110 (1932). This section was referred to in Lazarus v. American Motors Corp., 21 Wis.2d 76, 83, 123 N.W.2d *642 548 (1963), and was given the specific approval of this court in Hoffman v. Red Owl Stores, Inc., 26 Wis.2d 683, 694 ff., 133 N.W.2d 267 (1965).

That section, as now modified in the Restatement of Contracts 2d, sec. 90, p. 215 (1973), provides in part:

“Sec. 90. Promise Reasonably Inducing Action or Forbearance.
“(1) A promise which the promisor should reasonably expect to induce action or forbearance on the part of the promisee or a third person and which does induce such action or forbearance is binding if injustice can be avoided only by enforcement of the promise. The remedy granted for breach may be limited as justice requires.”

This theory of an informal contract based on reliance is an exception to the general rule that the creation of a contract requires a bargain in which there is a mutual assent and consideration. Restatement 2d, sec. 19, p. 42 and sec. 19, comment e, p. 44.

In Hoffman v. Red Owl Stores, this court gave explicit recognition to the conditions which must exist to impose obligations upon parties when one acts in reliance upon the promise of another.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lazarus v. American Motors Corp.
123 N.W.2d 548 (Wisconsin Supreme Court, 1963)
Hoffman v. Red Owl Stores, Inc.
133 N.W.2d 267 (Wisconsin Supreme Court, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
277 N.W.2d 769, 88 Wis. 2d 637, 1979 Wisc. LEXIS 1972, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stack-construction-co-v-continental-construction-corp-wis-1979.