Stacey Properties v. Wixen

766 P.2d 1080, 98 Utah Adv. Rep. 61, 1988 Utah App. LEXIS 193, 1988 WL 142041
CourtCourt of Appeals of Utah
DecidedDecember 20, 1988
Docket880127-CA
StatusPublished
Cited by12 cases

This text of 766 P.2d 1080 (Stacey Properties v. Wixen) is published on Counsel Stack Legal Research, covering Court of Appeals of Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stacey Properties v. Wixen, 766 P.2d 1080, 98 Utah Adv. Rep. 61, 1988 Utah App. LEXIS 193, 1988 WL 142041 (Utah Ct. App. 1988).

Opinion

BENCH, Judge:

Plaintiff appeals from final judgment on an action to accelerate the balance due on a promissory note. Defendants appeal from final judgment on their counterclaim for breaches of warranty and contract. There are three issues presented for review. First, did the trial court err in dismissing plaintiff’s claim for acceleration of the balance owed on the promissory note? Second, did the court err in measuring damages to be awarded defendants on their counterclaim? Third, did the court err in failing to award attorney fees? We affirm in part, reverse in part, and remand.

This dispute stems from the sale in May 1984 of several commercial properties located in and around Ogden, Utah. Stacey Properties Ltd. (Stacey), a Utah limited partnership, and J. Ron Stacey, general partner, sold the properties to defendants Ben and Francine Wixen and Bernie and Bonnie Goler, general partners of Golwix Properties (Golwix). The total purchase price exceeded $3.5 million, most of which was paid through Golwix’s assumption of existing debt. Golwix also executed a promissory note in the amount of $80,000 payable in monthly installments to Stacey.

The terms of the promissory note included an offset provision, an acceleration clause, and a provision for Stacey’s attorney fees in the event enforcement of the note became necessary. In conjunction with the note, a letter agreement memorializing the terms of the sale provided for, inter alia, express warranties on certain aspects of the properties and for Golwix’s *1082 attorney fees for any breach of those warranties.

The note and agreement were executed on May 22, 1984. On September 5, 1984, Golwix asserted an offset against payments due under the note. A week later, Stacey notified Golwix that the entire balance due under the note was being accelerated because of Golwix’s “default.” Stacey filed suit on December 5, 1984, and Golwix counterclaimed.

Trial before the court commenced on May 28,1986. After three days of testimony, the trial court determined that Golwix had failed to make a total of $16,099.38 in payments on the note by the time of trial. The court further determined that Golwix had established offsets totaling $6,727.33 for replacement of an air conditioner and repair of a sewer system. Golwix was also awarded $12,250 in damages on its counterclaim for replacement of a roof. The trial court found that there had been no default and denied Stacey’s demand to accelerate the balance due on the note. Neither party was found to be entitled to an award of attorney fees. Both parties appeal the judgment.

ACCELERATION OF THE PROMISSORY NOTE

Although an acceleration clause “will be enforced in accordance with the agreement of the parties,” KIXX, Inc. v. Stallion Music, Inc., 610 P.2d 1385, 1388 (Utah 1980), the remedy is a harsh one “not favored in the law.” Williamson v. Wanlass, 545 P.2d 1145, 1147 (Utah 1976).

Stacey contends on appeal that it should have been permitted to accelerate the due date of the principal balance of the promissory note according to the note’s terms. The pertinent provision of the note states:

In the event this Note, or any obligation provided to be satisfied or performed under any agreement, instrument or document connected with or related to this Note, now existing or otherwise, is breached or is not satisfied, performed or paid, at the time and in the manner required, [Stacey], at its option and without notice, may declare the unpaid principal balance and accrued interest immediately due and payable and [Golwix] agreefs] to immediately pay the same.

We examine this provision as we would a contract, since “[p]romissory notes ... are contracts between the parties, and the rules of construction applicable to contracts apply to them.” First Nat’l Bank & Trust Co. v. Lygrisse, 231 Kan. 595, 647 P.2d 1268, 1272 (1982). Furthermore, “[t]he interpretation of contract language presents us with a question of law on which we need not defer to the trial court’s construction but are free to render our independent interpretation.” Faulkner v. Farnsworth, 714 P.2d 1149, 1150 (Utah 1986); see also Ted R. Brown & Assoc., Inc. v. Carnes Corp., 753 P.2d 964, 968 (Utah App.1988).

Stacey claims on appeal that th,e ruling below discourages unsecured loans, creates a precedent opposed to the policy of prompt notification of default, and weakens the enforceability of acceleration provisions in general. We disagree. The essence of the ruling of the trial court is merely that acceleration was premature at the time of notification and unwarranted later because of the amount of Golwix’s offset.

At the time Golwix notified Stacey of its offset claim, two of the four monthly installment payments due had been paid. There is testimony in the record that the parties had agreed to postpone payment of the initial monthly installment for one year. The remaining unpaid installment was due on September 1, 1984, four days before Golwix sent notification of its offset. Prior to submission of its offset claim, Golwix had already paid or deferred three of the four installment payments due. On those facts, the court could reasonably find that no default had occurred at the time of the attempted acceleration.

The court also found that acceleration was unwarranted because the amount of offsets asserted by Golwix exceeded the amount in arrears on the note. It is clear from the record that Golwix bargained for and received a contractual right of offset. The operative provision of the promissory note states:

*1083 [Golwix] shall have the right to offset against any amounts due or to become due to [Stacey] under this Note any such reimbursement due to [Golwix] under Section 17 of said letter agreement or under any other provision thereof or of any document executed in conjunction therewith, provided, however, that [Gol-wix] give[s] [Stacey] written notice of the amount to be offset and the specific reasons therefor.

The trial court considered this provision along with the following provision of the letter agreement:

The properties have been inspected by [Golwix] and are purchased “as is”.... [Stacey] agree[s] to remedy any latent defects in materials or workmanship which arise within a one year period from the date of closing. We represent and warrant to you that all heating, cooling, electrical, plumbing and sewer systems at the properties are in working order and will be operative at closing and that the footings and foundations are free from material structural defects.... We will perform all necessary repairs to the roof of the Post Office building which are reasonably required to maintain a water tight roof surface for a period of sixty seven [sic] months from the date of closing at our sole cost and expense.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Beesley v. Brinton
D. Utah, 2025
Highlands at Jordanelle, LLC v. Wasatch County
2015 UT App 173 (Court of Appeals of Utah, 2015)
Cache County v. Beus
2005 UT App 204 (Court of Appeals of Utah, 2005)
Saunders v. Sharp
840 P.2d 796 (Court of Appeals of Utah, 1992)
Brown v. Richards
840 P.2d 143 (Court of Appeals of Utah, 1992)
Schuhman v. Green River Motel
835 P.2d 992 (Court of Appeals of Utah, 1992)
Occidental/Nebraska Federal Savings Bank v. Mehr
791 P.2d 217 (Court of Appeals of Utah, 1990)
Cobabe v. Crawford
780 P.2d 834 (Court of Appeals of Utah, 1989)
Mountain States Broadcasting Co. v. Neale
783 P.2d 551 (Court of Appeals of Utah, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
766 P.2d 1080, 98 Utah Adv. Rep. 61, 1988 Utah App. LEXIS 193, 1988 WL 142041, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stacey-properties-v-wixen-utahctapp-1988.