Stabile v. General Enterprises

246 N.W.2d 375, 70 Mich. App. 711, 1976 Mich. App. LEXIS 907
CourtMichigan Court of Appeals
DecidedAugust 24, 1976
DocketDocket 25251
StatusPublished
Cited by4 cases

This text of 246 N.W.2d 375 (Stabile v. General Enterprises) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stabile v. General Enterprises, 246 N.W.2d 375, 70 Mich. App. 711, 1976 Mich. App. LEXIS 907 (Mich. Ct. App. 1976).

Opinion

W. Van Valkenburg, J.

We are called on here to determine whether the 10-year statute of limitations set forth in MCLA 600.5809; MSA 27A.5809 is applicable on the facts of this case. The statute as it stood at the time the action was brought read:

"Sec 5809. No person may bring or maintain any action to enforce non-contractual money obligations unless after the claim first accrued to himself or to someone through whom he claims he commences the action within the periods of time prescribed by this section.

"(1) The period of limitations is 2 years for actions for the recovery of any penalty or forfeiture based on any penal statute brought in the name of the people of this state.

"(2) The period of limitations is 10 years for actions founded upon judgments or decrees rendered in any *713 court of record of the United States, or of this state, or of any other state of the United States, from the time of the rendition of the judgment. Within this period an action may be brought upon the judgment for a new judgment, which, in its turn, will be subject to the provision of this section.” 1

The plaintiffs brought suit on April 11, 1957, seeking to enjoin the defendants, General Enterprises and defendants Bauer and Pennell from continuing to obstruct and divert the normal flow of the Clinton River. The defendants Bauer and Pennell were assignees of the interests of General Enterprises.

On September 10, 1959, a consent decree was filed in the Macomb Circuit Court. The decree provided in part:

"WHEREAS, The defendants were engaged in erecting and are noe (sic) operating a sewage disposal plant on their property, and did construct on their lands to the north of said sewage disposal plant a canal or channel causing most waters of the Clinton River to pass through said canal rather than through the old Clinton River bed separating the plaintiffs’ and defendants’ land, and further that the defendants caused to be *714 erected a roadway and did lay certain sewage conduits across the Clinton River bed downstream from the plaintiffs’ property * * * ;

"NOW, THEREFORE, IN CONSIDERATION of the premises in the sum of ONE ($1.00) DOLLAR and other valuable consideration paid by the defendants to the plaintiffs, which are as follows:

"1. That upon entrance of this Decree, the defendants will pay the sum of SIX THOUSAND FIVE HUNDRED ($6500.00) DOLLARS to the plaintiffs.

"2. That within Six (6) months from the date of the entrance of this Decree, the defendants shall cause to be erected a barrier of spillway separating the new canal or dredge dug by the defendants and the old canal separating the plaintiffs’ and defendants’ land. Said barrier or spillway is to be erected in such a fashion as to cause no less than approximately sixty-six and two-thirds per cent (66 2/3%) of the waters of the Clinton River, at its lowest seasonal level, to be diverted into the original Clinton River bed separating the plaintiffs’ and defendants’ lands. Further, the defendants for themselves, their heirs, administrators, executors and assigns, do hereby agree and promise to the plaintiffs and their heirs, administrators, executors and assigns, to maintain said barrier in order that the full water will be divided as hereinabove mentioned and leave a necessary opening between the original Clinton River bed and the new canal in order that the plaintiffs, their heirs, administrators, executors and assigns will have navigation to said canal towards Lake St. Clair.

"3. That the defendants for themselves, their heirs, administrators, executors and assigns, do hereby agree and promise to keep the conduits under the roadway they erected downstream from the plaintiffs’ property, east of their sewage disposal plant, free and clear of debris and foreign matter in order that the flow of water through the original bed separating plaintiffs’ and defendant’s land will be able to flow unhampered and in a normal manner.

"4. Further, that the defendants will dig one deep well on plaintiffs’ property within six months from the date of this decree, having a minimum casing of four (4) *715 inches, and the well shall be dug to a minimum depth of one hundred thirty feet (130) unless usable water is obtained prior thereto. The plaintiffs shall provide their own pump and pipe to connect the pump. Should a depth of one hundred thirty (130) feet be reached without reaching usuable water, the defendants will be discharged from any further liability under this section.

"5. That shall the defendants, their heirs, administrators, executors and assigns, fail to continue to perform the provisions providing for the continual maintenance of said barrier hereinbefore mentioned, and to keep the conduits under the roadway free and clear from debris and foreign matter hereinbefore mentioned, that the plaintiffs may petition this Court and upon proof of the defendants’, their heirs, administrators, executors and assigns, failure to so perform said duties, the plaintiffs will be entitled to a mandatory injunction for relief against the defendants, their heirs, administrators, executors and assigns.

”6. A true copy of this Decree may be registered in the Office of the Register of Deeds, Macomb County, Michigan.”

The money was paid to the plaintiffs and the defendants completed the well drilling project soon after the decree was entered. Defendant Clinton Township acquired the interests of the other defendants by purchase of the property in question in February, 1966. The waters of the Clinton River have not been restored to the plaintiffs as required in paragraph 2 of the decree.

On August 4, 1960, plaintiffs sought a mandatory injunction requiring compliance with the decree. The lower court record does not indicate to us whether there was a hearing held in this matter. No further action occurred in this case until November 12, 1970. On that date, plaintiffs petitioned for an order to show cause why the prior decree should not be enforced, requiring restoration of two-thirds of the flow of the Clinton River *716 to the plaintiffs and for damages to compensate the plaintiffs and for punitive damages. On January 18, 1973, the Macomb County Circuit Court ordered the defendants to comply with the decree of September 10, 1959. Plaintiffs again entered a default against the defendants General Enterprises and Bauer, but this was set aside on May 23, 1975. The defendants filed a motion to dismiss the petition and for an order to show cause. A dismissal was granted by the trial court on July 28, 1975. The plaintiffs appeal from this dismissal.

The trial judge held in a written opinion that the plaintiffs’ action was barred by the 10-year statute of limitations in RJA § 5809; MCLA 600.5809; MCA 27A.5809. We disagree.

The plain language of the statute applicable here is:

"No person may bring or maintain any action to enforce noncontractual money obligations.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J a Bloch and Company v. Ann Arbor Township
Michigan Court of Appeals, 2022
Leon v. Bonner v. City of Brighton
Michigan Court of Appeals, 2014
Village of Dimondale v. Grable
618 N.W.2d 23 (Michigan Court of Appeals, 2000)
Attorney General v. Thomas Solvent Co.
380 N.W.2d 53 (Michigan Court of Appeals, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
246 N.W.2d 375, 70 Mich. App. 711, 1976 Mich. App. LEXIS 907, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stabile-v-general-enterprises-michctapp-1976.