St. Paul Structural Steel Co. v. ABI Contracting, Inc.

364 N.W.2d 83, 40 U.C.C. Rep. Serv. (West) 789, 1985 N.D. LEXIS 267
CourtNorth Dakota Supreme Court
DecidedMarch 13, 1985
DocketCiv. 10746
StatusPublished
Cited by9 cases

This text of 364 N.W.2d 83 (St. Paul Structural Steel Co. v. ABI Contracting, Inc.) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
St. Paul Structural Steel Co. v. ABI Contracting, Inc., 364 N.W.2d 83, 40 U.C.C. Rep. Serv. (West) 789, 1985 N.D. LEXIS 267 (N.D. 1985).

Opinion

ERICKSTAD, Chief Justice.

ABI Contracting, Inc. (ABI) has filed an appeal from a judgment of the District Court of Burleigh County awarding St. Paul Structural Steel Company (St. Paul) damages, together with costs and disbursements, in the amount of $415,057.12 for ABI’s breach of a sales contract. We affirm in part, reverse in part, and remand for modification of the judgment.

The parties have stipulated that this case is governed by Minnesota law.

During 1978, ABI contracted with Basin Electric Power Cooperative to construct a coal-fired electric generating facility called the Antelope Valley station. ABI entered a subcontract agreement with St. Paul to purchase approximately $5,000,000 of structural steel materials. All of the steel was delivered by St. Paul and accepted by ABI. The dispute on this appeal involves the payment terms. ABI asserts that under the agreement it was permitted to retain 10% of the purchase price for delivered steel until the project was completed. St. Paul asserts that the parties reached no agreement on a retainage term.

*85 The trial court, upon finding that the parties “failed to reach agreement on payment-retainage terms”, concluded that under Section 336.2-310, Minn.Stat., St. Paul was entitled to receive full payment for materials three days after delivery to ABI. The trial court determined that St. Paul was entitled to recover, as incidental damages, interest payments for money St. Paul was required to borrow to continue its operations as a result of ABI’s failure to make timely payments.

ABI has raised the following issues on appeal:

(1) Whether the trial court erred in construing the payment terms of the contract;
(2) Whether the trial court erred in awarding St. Paul interest as an element of incidental damages;
(3) Whether the trial court erred in awarding interest damages in excess of the 6% rate allowed under Section 334.01, Minn.Stat.;
(4) Whether the trial court erred in its determination that St. Paul did not waive its right to seek damages for ABI’s breach; and
(5) Whether the trial court erred in admitting Exhibits 43 and 44a for use in determining the amount of damages to which St. Paul was entitled.

The primary issue raised on appeal is whether the trial court erred in construing the payment terms under the sales agreement between St. Paul and ABI. Having reviewed the transactions between the parties and the relevant Uniform Commercial Code (UCC) provisions, we conclude that the trial court’s analysis in construing the agreement was fundamentally correct but that the court unnecessarily supplied terms involving progress payments different from those upon which the parties had agreed.

ABI’s first purchase order for steel materials from St. Paul, dated October 31, 1978, included a provision authorizing ABI to withhold, as a retainage, 10% of the purchase price for the materials supplied by St. Paul until Basin Electric made its final acceptance of the project. The phrase “Retention Applies” was typed onto the right-hand column of the first page of the purchase order. The trial court found that during negotiations, which occurred prior to ABI’s transmittal of the October purchase order, St. Paul had advised ABI that it would not agree to permit a retainage. The trial court further found that after St. Paul received the October purchase order its vice president of sales and engineering, Robert Clemens, objected to the retainage term in the purchase order through telephone conversations with ABI officials. The ABI officials agreed to “check on it and get back to Mr. Clemens” but ABI did not subsequently respond to St. Paul’s objection. Clemens then sent a letter to ABI, dated December 5, 1978, proposing the following resolution to their disagreement about retainage:

“90% of our monthly invoice for materials delivered during that month would be due in 30 days. The remaining 10% could be retained for a period not to exceed 120 days.”

Clemens signed and returned the October purchase order to ABI after making a hand-written change on the first page of the order stating, “retention applies per SPSS letter dated 12/6/78.”

The trial court found that the parties never reached an agreement regarding re-tainage. All of the contracted steel was delivered by St. Paul and accepted by ABI, and 90% progress payments were made by ABI on the steel accepted by it. During this period of performance by St. Paul and ABI, which extended beyond two years, there were ongoing objections, discussions, and negotiations regarding the retainage issue. St. Paul continued to assert that retainage was not part of the agreement and ABI continued to assert that the agreement authorized them to retain 10% of the purchase price until completion of the project.

The trial court found that the October purchase order constituted an offer by ABI to enter into a sales contract with St. Paul. *86 The court further found that St. Paul’s return of the signed purchase order, together with the notation which incorporated by reference the December 5, 1978, letter written by Clemens to ABI, constituted a definite expression of acceptance of the contract. The trial court concluded that the parties had entered into a valid sales agreement but that they had failed to agree on retainage terms. The court, applying Minnesota’s codification of the relevant UCC provision, determined that St. Paul and ABI’s retainage terms cancelled out.

ABI asserts that the trial court erred in determining that the different retainage terms in ABI’s offer and St. Paul’s acceptance had the effect of cancelling out those terms under the agreement. ABI asserts that the retainage term proposed in St. Paul’s acceptance of ABI’s offer did not become part of the contract because it was a material term which was not accepted by ABI, and therefore the 10% retainage term in ABI’s purchase order became part of the agreement. We disagree.

The relevant UCC provision is codified as Section 336.2-207, Minn.Stat.:

“336.2-207 Additional Terms in Acceptance or Confirmation.
“(1) A definite and seasonable expression of acceptance or a written confirmation which is sent within a reasonable time operates as an acceptance even though it states terms additional to or different from those offered or agreed upon, unless acceptance is expressly made conditional on assent to the additional or different terms.
“(2) The additional terms are to be construed as proposals for addition to the contract. Between merchants such terms become part of the contract unless:
(a) The offer expressly limits acceptance to the terms of the offer;
(b) They materially alter it; or
(c) Notification of objection to them has already been given or is given within a reasonable time after notice of them is received.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

William Ballou v. Asset Marketing Services, LLC
46 F.4th 844 (Eighth Circuit, 2022)
R & D Properties, LLC v. Altech Const. Co.
776 N.W.2d 493 (Nebraska Supreme Court, 2009)
Flender Corp. v. Tippins International, Inc.
830 A.2d 1279 (Superior Court of Pennsylvania, 2003)
Reilly Foam Corp. v. Rubbermaid Corp.
206 F. Supp. 2d 643 (E.D. Pennsylvania, 2002)
Richardson v. UNION CARBIDE IND. GASES, INC.
790 A.2d 962 (New Jersey Superior Court App Division, 2002)
Hart Honey Co. v. Cudworth
446 N.W.2d 742 (North Dakota Supreme Court, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
364 N.W.2d 83, 40 U.C.C. Rep. Serv. (West) 789, 1985 N.D. LEXIS 267, Counsel Stack Legal Research, https://law.counselstack.com/opinion/st-paul-structural-steel-co-v-abi-contracting-inc-nd-1985.