St. Paul Fire & Marine Insurance v. James I. Barnes Construction Co.

267 Cal. App. 2d 931, 73 Cal. Rptr. 618, 1968 Cal. App. LEXIS 1472
CourtCalifornia Court of Appeal
DecidedDecember 9, 1968
DocketCiv. No. 25051
StatusPublished

This text of 267 Cal. App. 2d 931 (St. Paul Fire & Marine Insurance v. James I. Barnes Construction Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
St. Paul Fire & Marine Insurance v. James I. Barnes Construction Co., 267 Cal. App. 2d 931, 73 Cal. Rptr. 618, 1968 Cal. App. LEXIS 1472 (Cal. Ct. App. 1968).

Opinion

BROWN (H. C.), J.

This is the second appeal in this case. The original complaint was filed by St. Paul Fire & Marine Insurance Company (St. Paul) on November 27, 1959 alleging that James I. Barnes Construction Co. (Barnes), after notice, had improperly paid money to Stewart & Nuss, Inc. (Stewart) that was due it under an assignment from Stewart. The trial court decided in favor of St. Paul in the amount of $37,964.10 and the Court of Appeal affirmed the decision. The Supreme Court reversed and remanded for retrial of the action. (St. Paul Fire & Marine Ins. Co. v. James I. Barnes Constr. Co., 59 Cal.2d 691, 697 [31 Cal.Rptr. 52, 381 P.2d 932].)

The second trial without a jury resulted in a judgment in favor of St. Paul on January 30, 1967, in the amount of $1,540.64.

A detailed statement of facts is contained in the opinion of the court in St. Paul Fire & Marine Ins. Co. v. James I. Barnes Constr. Co., supra, 59 Cal.2d 691, and for the purpose of this opinion is summarized.

Barnes was the general contractor for the construction of [933]*933the Fresno County Hospital. Stewart was the subcontractor for the paving and grading work. Barnes required that Stewart obtain a performance bond, the premium to be paid by Barnes. Stewart obtained a bond issued by St. Paul in favor of Barnes with Stewart as principal. The application for the bond contained the following provision: 11 ‘For the better protection of the Company, [Stewart agrees] to assign, transfer and convey, and does hereby assign, transfer and convey to . . . [St. Paul] . . . but only in the event of any breach, delay, or default on the part of . . . [Stewart] in the performance of the contract covered by said bond or bonds, failure or inability of . . . [Stewart] to promptly pay, satisfy and discharge any and all obligations which might constitute possible claim under the bond or bonds, or breach of any of the terms of this agreement,’ all of Stewart’s right, title and interest in and to the contract together with all sums due or to become due thereunder.” (St. Paul Fire & Marine Ins. Co. v. James I. Barnes Constr. Co., supra, at p. 695.)

Under the contract between Barnes and Stewart, payments for Stewart’s work in the total sum of $52,733.32 were to be made in installments as the work progressed. The first progress payment was made on November 20, 1957 in the sum of $14,769.22. On that date St. Paul advised Barnes that it held Stewart’s assignment and requested that Barnes withhold further payments to Stewart. Barnes acknowledged the letter and requested advice as to how future payment was to be made. On January 12,1958 St. Paul repeated its November 20 letter and further informed Barnes that Stewart intended to file bankruptcy. Barnes replied stating no further monies would be paid Stewart until authorized by St. Paul.

When the time came for further performance, Barnes called upon Stewart to proceed and the work was completed late in 1959. Barnes continued to pay Stewart in installments as the work progressed as follows: $30,317.77 on December 29, 1958 $2,373 on May 20, 1959, and $5,273.33 on February 12, 1960. Barnes did not call upon St. Paul to make any payment on account of Stewart or to perform any act under its bond. However, St. Paul made payments to two of Stewart’s subcontractors, Elias and Decker, early in 1958 for services performed prior to November 1957.

St. Paul brought an action against Barnes for losses it suffered on bonds it had issued for Stewart on other jobs, and in the first trial received judgment for $37,964.10. This was [934]*934the amount Barnes had paid to Stewart after he had received notice of the assignment. The Supreme Court reversed this decision on the ground that the assignment was a conditional assignment for security rather than an absolute assignment. (St. Paul Fire & Marine Ins. Co. v. James I. Barnes Constr. Co., supra, at p. 692.) The Supreme Court held that when an assignment is for security and the debtor pays the assignor after notice, the assignee can recover from the debtor of the assignor only if its security has been adversely affected, that is, only if it has suffered a loss. The Supreme Court reversed the judgment of the trial court with the following conclusions and directions: “For these reasons we conclude that: (1) the language of the assignment did not create a present transfer, but only a conditional transfer in the event that it became necessary for St. Paul to pay or perform under its bond; (2) that there remains an unresolved question as to whether that condition ever existed, and as to which the trial court must make findings; (3) that the trial court must also make findings on the issue of whether Barnes was excused (because of either fraud, mutual mistake of fact or St. Paul’s subsequent default) from any obligation to St. Paul because of its agreement to withhold payments for St. Paul’s account; (4) that there is no finding on the question of whether Barnes’ payments after notice were necessary to enable the assignor [Stewart] to complete its contract; (5) that there is no finding on the issue of whether St. Paul suffered any detriment by reason of Barnes’ payments to Stewart; ...” (St. Paul Fire (& Marine Ins. Co. v. James I. Barnes Constr. Co., supra, atp. 702.)

At the second trial St. Paul produced evidence (after amending its complaint) that it had suffered loss in the sum of $45,084.61 on approximately ten other construction jobs of Stewart’s for which it had written additional indemnity bonds. Included in the total loss were two losses attributable to the Stewart-Barnes contract, i.e., the amounts due two parties named Elias and Decker.

The trial judge found that Stewart was unable to pay and meet its obligations to Elias and Decker; that these obligations constituted possible claims under the bond written by St. Paul; and concluded that St. Paul was justified in paying the claims and, therefore, was entitled to the sum of $1,540.64. ($705.49 to Elias, $146.33 to Decker, and expenses and fees in connection with said payments in the sum of $688.82.)

[935]*935The trial judge also found that Barnes had made no demands upon St. Paul for performance under the bond; that Barnes paid Stewart after notification of the assignment; that such payments were necessary for the completion of the work contracted for; that if payments had not been made to Stewart, performance of the work contracted for would have been rendered impossible and that liens and stop-notices would have been filed against the hospital which was a public works job; and that if Stewart had not been paid by Barnes, St. Paul would have been contractually obligated to provide the performance under the Stewart-Bames contract and to expend monies therefor.

Appellant St. Paul in this appeal presents the same contention that was before the Supreme Court on the first appeal, i.e., that the assignment by Stewart, of which Barnes was repeatedly notified, was for the protection of St. Paul against losses on the other bonds which it wrote for Stewart.

The Supreme Court regarded the assignment as conditional in this sense: “The sole question that is controlling ... is whether the purported assignment was absolute . . . , or was a conditional assignment which never became operative.” (P. 698.) It also regarded the assignment as conditional in the sense that it was for security only.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fricker v. Uddo & Taormina Co.
312 P.2d 1085 (California Supreme Court, 1957)
Auer v. Frank
227 Cal. App. 2d 396 (California Court of Appeal, 1964)
Benton v. Hofmann Plastering Co.
207 Cal. App. 2d 61 (California Court of Appeal, 1962)
Polk v. Polk
228 Cal. App. 2d 763 (California Court of Appeal, 1964)
Peden Iron & Steel Co. v. McKnight
128 S.W. 156 (Court of Appeals of Texas, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
267 Cal. App. 2d 931, 73 Cal. Rptr. 618, 1968 Cal. App. LEXIS 1472, Counsel Stack Legal Research, https://law.counselstack.com/opinion/st-paul-fire-marine-insurance-v-james-i-barnes-construction-co-calctapp-1968.