St. Louis County Water Co. v. State Highway Commission

411 S.W.2d 218, 1966 Mo. LEXIS 573
CourtSupreme Court of Missouri
DecidedDecember 30, 1966
DocketNo. 51953
StatusPublished

This text of 411 S.W.2d 218 (St. Louis County Water Co. v. State Highway Commission) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
St. Louis County Water Co. v. State Highway Commission, 411 S.W.2d 218, 1966 Mo. LEXIS 573 (Mo. 1966).

Opinion

HIGGINS, Commissioner.

Proceeding under Section 536.100 et seq., V.A.M.S., for judicial review of an order of the State Highway Commission, affirmed by the circuit court, directing St. Louis County Water Company to relocate certain of its facilities located in state highway right of way at a cost to the Company in excess of $15,000.

This is the second appeal in this matter, the first being reported at 386 S.W.2d 119; and, in order to provide background and continuity, much of the case as there stated is set out.

“Commission Project F-610(ll) was for the improvement of some 8200 feet of Lindbergh Boulevard (Route 66TR) in the vicinity of its intersection with Page Boulevard in St. Louis County. The plans called for elimination of a number of curves in Lindbergh, the construction of a cloverleaf interchange at the Page Boulevard intersection and an underpass under tracks of the Rock Island Railroad. The reconstructed highway was to consist of two 24-foot roadways, paved with concrete and separated by a medial strip, with stabilized shoulders.

“In 1947, pursuant to a permit issued by the commission, the company had installed a 20-inch water main in the highway right-of-way for more than 6 miles along Lindbergh, which included the area involved in Project F — 610(11). The permit called for the installation of the main 8 feet west of the west edge of Lindbergh Boulevard. This main is the principal facility involved in the proceeding under review.

“After conferring with water company representatives, the commission, on May 31, 1961, through its district engineer, issued an order approving plans for the location of the water company’s facilities in the improvement area. Of some 8200 feet of 20-inch line involved, some 2000 feet in locations not affected by the new construction were to remain in place. The company agreed to the relocation of some 2000 feet of the line situated in sites in which the grade of the existing roadway was to be changed, including the Page Boulevard and Rock Island underpasses. Some 4200 feet of the 20-inch line were to be abandoned and relocated, along with 580 feet of 8-inch line.

“The order, pursuant to Section 227.240, supra,1 notified the company that a hearing [220]*220would be held on the commission’s proposal involving the company’s facilities. A hearing was held at which evidence was presented by representatives of the highway department and of the company. Following the hearing, the commission issued the order presently involved, requiring the abandonment of some 2775 feet of 20-inch line in three separate locations and approximately 300 feet of 8-inch line.

“The first location in which changes in the company’s facilities were ordered was in the vicinity of the intersection of Dorsett Road with Lindbergh. There the roadway was to be widened by the adding of new pavement on both sides of the existing pavement. The order called for the retirement of some 1275 feet of 20-inch main which would have been under the new pavement at distances, measured from the west edge of the pavement, of from 10 to 20 feet. It also called for the retirement of 300 feet of 8-inch main which would have been under the new pavement by a maximum of 20 feet and a minimum of 10 feet from its west edge.

“The second and third locations were in areas where curves in the existing road were straightened. In both the second and third relocation sites, the 20-inch main would have crossed the new roadway beneath new pavement at oblique angles which would have placed some 550 feet of main under the roadway in the second relocation site. In that site some 650 feet of 20-inch main were to be retired, consisting of the 550 feet which would have been under the pavement and 100 feet which would have been in the shoulder of the roadway. In the third site, 450 feet of 20-inch main which would have been beneath the new paved roadway and some 400 feet of the main which would have been in the shoulder of the new roadway were ordered retired or removed.

“The order submitted approved reloca-tions of the mains to be retired or removed. Generally, the relocations were near the edge of the right-of-way of the highway as improved. Where crossings of the new roadway were to be made to rejoin portions of the main left in use, the lines crossed the roadway at angles which made the portion of the line beneath the pavement approximately the same length as the width of the pavement at the point of crossing.

“By its final order, the commission found that the highway improvement involved the construction of a hard surface highway; that facilities of the company ordered relocated would be either covered with hard surface pavement or incorporated in the shoulders of the roadway; that some of the facilities, if left in place, would cross [221]*221under the new paved roadway ‘on a sharp skew angle, thereby creating a crossing of considerable length; that other parts of the facilities, if let (sic) in place, will be under the shoulder of the roadway or under the pavement to varying extents; and that the presence of a part of said facilities will interfere with the proper and economical construction and maintenance of said highway and will impede the lawful traffic thereon after reconstructed * *

“ * * * On this appeal, the company first contends that the relocation order is unsupported by competent and substantial evidence upon the whole record and is arbitrary, capricious and unreasonable. The company contends further that the order of the commission is in excess of its authority and not authorized by law because it was based not upon the evidence adduced at the hearing but upon a previously adopted policy of the commission. Inasmuch as we conclude that this second contention is dispositive of this appeal, we turn to it.

“At the hearing, the commission placed in evidence a pamphlet entitled ‘A POLICY ON LOCATION OF UTILITY FACILITIES ON STATE HIGHWAYS.’ According to the pamphlet, the policy had been established by the Missouri State Highway Commission on October 14, 1958. The witness who identified the pamphlet stated that the provisions under portions of the policy statement dealing with ‘HIGH TYPE ROADS’ applied in this case. The portions which he pointed out as being applicable were as follows:

“ ‘II. HIGH TYPE ROADS.
“ ‘A. Existing Roadway Included in Final Improvement and Existing Utility Facilities on Present Right-Of-Way.
“ T. Relocate all parallel surface installations and parallel underground installations carrying pressure to near the new right-of-way lines.
“ ‘3. All underground mainline pipes under pressure crossing the roadway shall be encased from shoulder to shoulder of roadway as a minimum.’

“The statement of policy is prefaced as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Ex Rel. State Highway Commission v. Weinstein
322 S.W.2d 778 (Supreme Court of Missouri, 1959)
St. Louis County Water Co. v. State Highway Commission
386 S.W.2d 119 (Supreme Court of Missouri, 1964)
Stein v. State Tax Commission
379 S.W.2d 495 (Supreme Court of Missouri, 1964)
State ex rel. Henry v. Malhman
386 S.W.2d 1 (Supreme Court of Missouri, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
411 S.W.2d 218, 1966 Mo. LEXIS 573, Counsel Stack Legal Research, https://law.counselstack.com/opinion/st-louis-county-water-co-v-state-highway-commission-mo-1966.