St. Joseph Professional Building Corp. v. American National Insurance Co.

511 S.W.2d 578, 1974 Tex. App. LEXIS 2488
CourtCourt of Appeals of Texas
DecidedJune 26, 1974
Docket895
StatusPublished
Cited by6 cases

This text of 511 S.W.2d 578 (St. Joseph Professional Building Corp. v. American National Insurance Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
St. Joseph Professional Building Corp. v. American National Insurance Co., 511 S.W.2d 578, 1974 Tex. App. LEXIS 2488 (Tex. Ct. App. 1974).

Opinion

CURTISS BROWN, Justice.

This suit arises out of an alleged breach of contract and civil conspiracy.

A number of plaintiffs brought this action below; three appealed from instructed verdicts for defendants and will be referred to collectively as St. Jo. Defendants below were the American National Insurance Company (ANICO) and the Texas Commerce Bank National Association (the Bank). St. Jo alleged a cause of action for breach of contract against ANICO and a cause of action for civil conspiracy against ANICO and the Bank.

St. Jo began plans in 1962 to build a professional building in Houston, Texas. It obtained a commitment for long-term financing from New York Life Insurance Company for $3,600,000. In 1964, during construction, St. Jo ran into difficulties in meeting the terms of that commitment and sought financing with ANICO. ANICO issued a loan commitment for a total of $3,800,000. The ANICO commitment provided for funding of $3,200,000 when the shell of the building was completed and certain named tenants were obtained and had approved their leased areas. The remaining $600,000 was to be funded in six *580 $100,000 installments when “guaranteed annual rentals” produced from five-year leases reached certain dollar levels.

Using the ANICO commitment as security, St. Jo entered into a Loan Agreement with the Bank in August 1964 and executed a note and deed of trust covering the building and land to the Bank for $3,800,000. The Bank then entered into a Participation Agreement with ANICO, whereby ANICO agreed to purchase the Bank’s interest in the $3,800,000 note and deed of trust as St. Jo complied with the ANICO commitment for funding. The Bank agreed to apply loan payments between the parties ratably based on proportionate ownership of the note.

In October 1964 the building was completed and the named tenants had accepted their completed space. ANICO therefore funded the first $3,200,000. St. Jo applied at that time for the first $100,000 installment. Marc Cuenod, mortgage supervisor for ANICO, indicated by letter to St. Jo and the Bank that funds for the additional draws would not be advanced until tenants comprising “guaranteed annual rental” were in occupancy. St. Jo now claims that this letter added a new requirement and constituted a breach of the contract between ANICO and St. Jo as set out in the ANICO commitment. St. Jo complied with this requirement on all of its funding, and by December 15, 1965, ANI-CO had funded three $100,000 installments. The commitment expired on that day by its terms, but, on request of St. Jo, ANICO extended it to June 1, 1966. This extension gave St. Jo six extra months to qualify for the three additional $100,000 draws, and it also extended the interest-only provisions of the agreement to that date. Two days later, ANICO funded the fourth increment after determining that a sufficient occupancy level had been attained.

In April 1966, St. Jo wrote to ANICO claiming sufficient occupancy for the fifth increment. Marc Cuenod inspected the building for ANICO to determine compliance.' After the inspection Cuenod told H. M. Bennett and John Bennett, representatives of St. Jo, that it appeared that St. Jo had qualified for the fifth increment. He further stated that ANICO would probably have to extend their commitment to December 15, 1966, to allow St. Jo to qualify for the sixth increment. St. Jo made a formal request for an extension by letter to ANICO’s Finance Committee on May 23, 1966.

On May 31, 1966, the Finance Committee decided not to extend its commitment beyond June 1, 1966, and so notified the Bank. On June 1, 1966, the Bank made written demand for full payment of its $3,800,000 loan, pursuant to the Loan Agreement, by June 6, 1966. St. Jo offered to pay the Bank $200,000, which was the Bank’s remaining interest in the note. Since it was obligated under its Participation Agreement to apply all funds proportionately, such a payment would not have extinguished St. Jo’s debt; the Bank therefore refused to accept it. St. Jo appealed again to ANICO for an extension. ANI-CO responded by offering a Modification Agreement, which was executed by St. Jo on June 10, 1966. This agreement changed the terms of ANICO’s commitment by raising the interest rate on the permanent loan. It also agreed to accept full payment by September 10, 1966, at 101 percent of par to allow St. Jo to refinance. In return ANICO agreed to allow payment to the Bank of the $200,000 without a proportionate distribution to ANICO.

To pay off the Bank and prevent foreclosure, St. Jo turned to Allied Concord Finance Corporation (Allied) for a $200,000 loan on a demand note. St. Jo had borrowed $400,000 from Allied in 1965, giving a second mortgage on the building. ANICO took no further action, and in the spring of 1967 Allied foreclosed on its second lien and took control of the building. In 1968 Allied abandoned its position; ANICO foreclosed and purchased the building at the public sale.

*581 St. Jo complains on appeal that it offered sufficient evidence on both its breach of contract and civil conspiracy theories to preclude the granting of an instructed verdict. The standard of review in this case, then, is whether, indulging all reasonable inferences for the appellant, there was any evidence of probative value on which this case should have been submitted to the jury. Triangle Motors of Dallas v. Richmond, 152 Tex. 354, 258 S.W.2d 60 (1953).

St. Jo claims two instances in which ANICO breached its contract. First, as mentioned previously, St. Jo claims that the requirement of tenant occupancy under the six incremental draws was a breach of the agreement in the commitment. The pertinent language of the commitment is contained in paragraph 8 and is as follows:

8. The balance of the loan is to be disbursed prior to December 15, 1965 in not more than 6 additional fundings as follows:
A. $100,000 additional loan will be available when guaranteed annual rentals from satisfactory five-year or longer leases reach $420,000 from basement, first floor, and parking garage plus not more than 53,900 square feet of net rentable office area.
B. For each $20,000 in guaranteed annual rental produced by satisfactory five year leases from not more than 4,000 S.F. of net rentable office area, over and above the $420,000 annual rental referred to in A above, an additional $100,000 loan amount will be available up to and including a maximum total loan of $3,800,000.

The question to be decided is whether the terms “guaranteed annual rental produced by satisfactory five year leases” include the requirement of tenant occupancy.

The commitment clearly requires completion and tenant acceptance for the original $3,200,000 funding. It does not expressly provide for completion, accept-anee, or occupancy for the six increments. It does provide for rental produced, which could imply an occupancy requirement. This would be a permissible construction, which, in the case of an unambiguous contract, is a matter for the court. Tower Contracting Company v. Flores, 157 Tex. 297, 302 S.W.2d 396 (1957).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Canales v. State
221 S.W.3d 194 (Court of Appeals of Texas, 2006)
Lee v. Hunt
483 F. Supp. 826 (W.D. Louisiana, 1979)
Howard v. State
599 S.W.2d 597 (Court of Criminal Appeals of Texas, 1979)
Zeller v. University Savings Ass'n
580 S.W.2d 658 (Court of Appeals of Texas, 1979)
Hunt v. Coastal States Gas Producing Co.
570 S.W.2d 503 (Court of Appeals of Texas, 1978)
Samford v. Allstate Insurance Co.
529 S.W.2d 84 (Court of Appeals of Texas, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
511 S.W.2d 578, 1974 Tex. App. LEXIS 2488, Counsel Stack Legal Research, https://law.counselstack.com/opinion/st-joseph-professional-building-corp-v-american-national-insurance-co-texapp-1974.