St. Joseph Light & Power v. United Electric Cooperative

43 S.W.3d 330, 2001 Mo. App. LEXIS 99, 2001 WL 50127
CourtMissouri Court of Appeals
DecidedJanuary 23, 2001
DocketNo. WD 58140
StatusPublished

This text of 43 S.W.3d 330 (St. Joseph Light & Power v. United Electric Cooperative) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
St. Joseph Light & Power v. United Electric Cooperative, 43 S.W.3d 330, 2001 Mo. App. LEXIS 99, 2001 WL 50127 (Mo. Ct. App. 2001).

Opinion

ELLIS, Judge.

Appellant St. Joseph Light & Power (“SJLP”) appeals from a judgment entered in the Circuit Court of Nodaway County holding that Respondent United Electric Cooperative (“UEC”) had the right to continue to provide permanent retail electric service to a housing project being constructed by Respondent Homestead Cooperative of Maryville (“HCM”).

SJLP is a public utility holding an exclusive franchise to provide retail electric service within the City of Maryville, Missouri. UEC is a rural electric cooperative under Chapter 394, RSMo 1994, which provides retail electric service to rural areas in Nodaway County, Missouri.

HCM is a cooperative corporation that owns a tract of land on the edge of Mary-ville, Missouri. At all times relevant to this action, HCM was in the process of building a housing facility on that property.

On December 18, 1997, HCM entered into a contract with UEC under which UEC would provide all of the retail electric power for the proposed housing facility. On March 9, 1998, HCM filed a petition with the City Council of Maryville, Missouri, requesting that this property be annexed into the city.

On April 27, 1998, site preparation and “dirt work” for the construction project began on the property. On May 7, 1998, UEC installed a pad-mounted transformer and meter on the property. After its installation, the transformer was energized and operational.

On June 8, 1998, the City of Maryville annexed the property. At that time, the concrete footings had been poured for the building and some preliminary plumbing had been installed. None of the floors or walls had been constructed, and there was no roof. In addition to the transformer and meter that had been installed on the property, the electrical contractor had placed three temporary construction power panels on the western side of the construction site to provide “single phase” electricity to power construction tools and provide temporary lighting. These temporary power panels were electrical breaker boxes and outlets mounted on a plywood board and placed on a wooden post driven into the ground. The temporary power panels were placed about 20 to 30 feet outside the perimeter of the concrete footings. Also, several electrical conduits (plastic pipes) had been buried in a trench running from the transformer to an area within the concrete footings. “Pull wires” had been placed inside the conduits. Pull wires are not used to transmit electricity and are used at a later date to pull the actual electrical conductors through the conduits.

[332]*332On July 17, 1998, SJLP filed its “Petition for Permanent Injunction, Preliminary Injunction and Application for Temporary Restraining Order” in the Circuit Court of Nodaway County. SJLP sought to prevent UEC from providing permanent electrical service to the housing project. In its petition, SJLP claimed to be the only lawful supplier of electricity within the City of Maryville and asked the court to restrain UEC from providing electricity to the housing project.

The case was tried to the court on August 25, 1999. On December 13, 1999, the trial judge entered his “Findings of Fact, Conclusions of Law, and Judgment.” The trial judge found that, as of the date of annexation, UEC had installed all of the permanent facilities necessary for it to provide electrical service to the housing project and that any remaining electrical equipment to power the buildings was to be installed by the electrical contractor. The trial court also found that UEC was providing electricity to a “structure” on the date of annexation because electrical construction equipment plugged into the temporary power panels with extension cords had been used within the perimeter of the building’s footings. Based on these findings, the court held that UEC was entitled to continue providing electricity to the structure under §§ 394.080.1 and 394.315.1

On appeal, SJLP argues that the trial court erred in finding that UEC had the right to provide permanent retail electric service to the housing project. When reviewing a court-tried case, this Court will affirm the judgment of the trial court unless there is no substantial evidence to support the judgment, the judgment is against the weight of the evidence, or the trial court erroneously declares or applies the law. Butler Supply, Inc. v. Coon’s Creek, Inc., 999 S.W.2d 748, 749 (Mo.App. W.D.1999).

“Pursuant to section 394.080.1(4), a rural electric cooperative has the authority to sell electricity to its members in rural areas.” Farmers’ Elec. Co-op., Inc. v. Missouri Dept. of Corrections, 977 S.W.2d 266, 269 (Mo. banc 1998). “Rural areas” include any area “not included within the boundaries of any city, town, or village having a population in excess of fifteen hundred inhabitants.” § 394.020(3). Prior to its annexation into the City of Maryville, the property owned by HCM was within a rural area under the statutory definition, and UEC could properly provide electric services to it. However, because the City of Maryville had a population in excess of 1,500 inhabitants, once the property owned by HCM was annexed into the city, the property ceased to be located in a “rural area” as defined by statute. Union Elec. Co. v. Platte Clay Elec. Co-op., Inc., 814 S.W.2d 643, 644 (Mo.App. W.D.1991).

Where a rural electric cooperative has already started providing permanent electric service to a property which is annexed by a city, Section 394.080.1(4) contains a “grandfather provision” which allows the cooperative to continue to provide electricity to that property after its annexation. “Under this • section, when a rural area served by a cooperative is annexed into a city, the cooperative has the authority to continue selling electricity to its members in the formerly rural area.” Farmers’ Elec. Co-op., Inc., 977 S.W.2d at 270.

Section 394.315 serves to limit a rural cooperative’s grandfather rights under § 394.080. Id. Section 394.315.2 provides that “[ojnee a rural electric cooperative ... lawfully commences supplying retail electric energy to a structure through per[333]*333manent service facilities, it shall have the right to continue serving such structure, and other suppliers of electrical energy shall not have the right to provide service to the structure ... ”2 “Section 394.315.1(2) states that ‘[n]othing in this section shall be construed to confer any right on a rural electric cooperative to serve new structures on a particular tract of land because it was serving an existing structure on that tract.’ ” Farmers’ Elec. Co-op., Inc., 977 S.W.2d at 270. Accordingly, once the land at issue is annexed into a city with a population over 1,500, the rural electric cooperative no longer has the right to provide electric service to any new structures constructed on the land after the date of annexation. Id. at 271. Therefore, the relevant inquiry in determining whether UEC had a right to provide permanent retail electric service to the housing project is whether UEC had commenced supplying retail electric energy to that “structure” through “permanent service facilities” prior to the date of annexation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Union Electric Co. v. Platte-Clay Electric Cooperative, Inc.
814 S.W.2d 643 (Missouri Court of Appeals, 1991)
Butler Supply, Inc. v. Coon's Creek, Inc.
999 S.W.2d 748 (Missouri Court of Appeals, 1999)
Skinner v. Henderson
556 S.W.2d 730 (Missouri Court of Appeals, 1977)
Slate v. Boone County Board of Adjustment
810 S.W.2d 361 (Missouri Court of Appeals, 1991)
State v. Scilagyi
579 S.W.2d 814 (Missouri Court of Appeals, 1979)
Utilicorp United Inc. v. Platte-Clay Electric Cooperative, Inc.
799 S.W.2d 108 (Missouri Court of Appeals, 1990)
Empire District Electric Co. v. Southwest Electric Cooperative
863 S.W.2d 892 (Missouri Court of Appeals, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
43 S.W.3d 330, 2001 Mo. App. LEXIS 99, 2001 WL 50127, Counsel Stack Legal Research, https://law.counselstack.com/opinion/st-joseph-light-power-v-united-electric-cooperative-moctapp-2001.