SR CONSTR., INC. v. PEEK BROS. CONSTR., INC.

2022 NV 41
CourtNevada Supreme Court
DecidedJune 2, 2022
Docket82786
StatusPublished

This text of 2022 NV 41 (SR CONSTR., INC. v. PEEK BROS. CONSTR., INC.) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SR CONSTR., INC. v. PEEK BROS. CONSTR., INC., 2022 NV 41 (Neb. 2022).

Opinion

138 Nev., Advance Opinion 14 I IN THE SUPREME COURT OF THE STATE OF NEVADA

SR CONSTRUCTION, INC., A NEVADA No. 82786 DOMESTIC CORPORATION, Appellant, vs. FILE 011 PEEK BROTHERS CONSTRUCTION, INC., A NEVADA DOMESTIC JUN 0 2022 CORPORATION, ELI Respondent. CLERK BY DEPUTY CLERK

Appeal from a district court order denying a motion to compel arbitration. Second judicial District Court, Washoe County; Barry L. Breslow, Judge. Reversed and remanded.

Allison Law Firm Chtd. and Noah G. Allison and Heather Caliguire Fleming, Henderson, for Appellant.

Viloria, Oliphant, Oster & Aman LLP and Nathan J. Aman and Ernilee N. Hammond, Reno, for Respondent.

BEFORE THE SUPREME COURT, SILVER, CADISH, AND PICKERING, JJ.

SUPREME COURT OF NEVADA

4(71 1947A jz-

77V., • OPINION

By the Court, PICKERING, J.:

This is an appeal from an order denying a motion to compel arbitration. Appellant SR Construction, Inc., argues that the district court erroneously denied its motion to compel because its master subcontract

agreement (MSA) with respondent Peek Brothers Construction, Inc., includes a valid arbitration provision that applies to the parties underlying dispute. Peek contends the district court properly held that the underlying dispute falls outside the bounds of the parties' arbitration agreement. The parties do not contest the validity of the MSA or its arbitration provision, thus posing a single question to this court in this appeal: Does the parties'

dispute fit within the scope of the arbitration provision contained in the MSA?

I. SR (a general contractor) and Peek (a subcontractor) executed the MSA to establish the general terms and conditions of their future work together. The MSA includes an arbitration provision:

(a) Contractor and Subcontractor shall not be obligated to resolve disputes arising under this Subcontract by arbitration, unless: (i) the prime contract has an arbitration requirement; and (ii) a particular dispute between Contractor and Subcontractor involves issues of fact or law which the Contractor is required to arbitrate under the terms of the prime contract. (emphasis added). S.R later executed an agreement (the prime contract) with Sparks Family Medical Center, Inc., an affiliate of United Health

SUPREME COURT OF NEVADA 2 011 I947A *L gelca

,

• Services of Delaware (UHS, the project owner), to construct a major medical center in Reno (the project). The prime contract consists of two documents—American Institute of Architects (AIA) Document A133-2009 and AIA Document A201-2017—each of which incorporates the other by reference. The prime contract is a "cost-plus" agreement with a guaranteed maximum price (GMP), meaning that UHS as the project owner bears all project costs up to the GMP. Cost-Plus Contract, Black's Law Dictionary (11th ed. 2019) ([A] contract in which payment is based on a fixed fee or a percentage added to the actual cost incurred; esp., a construction contract in which the owner pays to the builder the actual costs of material and labor plus a fixed percentage over that amount."). The parties may seek to increase the GMP and recover additional "necessarily incurred" costs using written change orders. If costs exceed the GMP as modified by any approved change orders, then SR is responsible for the excess costs. The prime contract also includes an arbitration provision, which states as follows: Arbitration shall be utilized as the method for binding dispute resolution in the Agreement[.] [A]ny Claim subject to, but not resolved by, mediation shall be subject to arbitration which, unless the parties mutually agree otherwise, shall be administered by the American Arbitration Association in accordance with its Construction industry Arbitration Rules in effect on the date of the Agreement. (emphasis added). A "claim" under the contract is "a demand or assertion by one of the parties seeking, as a matter of right, payment of money, a change in the Contract Time, or other relief with respect to the terms of the Contract . . . [and] other disputes and matters in question between the

SUPREME COURT OF NEVADA 3 10 I 947A 44111;*>

• Owner and Contractor arising out of or relating to the Contract." (emphasis added). The prime contract further permits SR to include subcontractors in arbitration of a claim: Arbitration, at the Contractor's election, may include Subcontractors to Contractor that Contractor deems relevant to the matter in dispute and upon Contractor's request, the Arbitrator shall decide all or a particular portion of a dispute between the Contractor and a Subcontractor and, as Contractor may request, the Arbitrator shall speak to the extent to which the Arbitrator's decisions regarding a dispute between Contractor and Owner and the dispute between Contractor and Subcontractor are inter-related. After executing the prime contract with UHS, SR executed a work order with Peek to complete the core and shell civil work for the project, which included bringing the building pad to the proper subgrade elevation. SR agreed to pay Peek $3,062,000 for its work, and the work order expressly incorporated the MSA's terms and obligations by reference. The dispute underlying SR's motion to compel arbitration arose when—for reasons the parties contest—Peek deviated from the means and methods it used to bid the project in elevating the building pad. Peek states that it bid the project assuming it would mass-grade the building pad to a few feet below the required elevation, dig the building footings and plumbing trenches, and then use the "spoils" from excavating the footings and trenches to backfill and grade the pad to the proper subgrade elevation. Instead, Peek imported approximately 150,000 square feet of additional material to raise the pad to the proper subgrade elevation before digging the footings and trenches. Peek alleges that it deviated from its bid-based plans when an SR employee directed it to obtain extra material to raise the pad

4 earlier because SR did not want to wait for Peek to excavate the footings and trenches. SR alleges that Peek did not know the pad's elevation from the start and thus imported additional material under the incorrect assumption that it needed it. The above-described changes added $140,000 to Peek's costs, which it sought to recover from SR after the fact in two written change orders. SR relayed the change orders to UHS, who deemed the changes unnecessary, rejected the change orders, and directed SR to initiate dispute resolution with Peek. Before SR could do so, Peek sued SR in district court, alleging breach of contract, unjust enrichment, and violation of NRS Chapter 624 and seeking over $140,000 in damages and attorney fees. SR filed a demand for arbitration with the American Arbitration Association (AAA), in which it named UHS and Peek as defendants, and in tandem with its demand, SR moved to compel arbitration in district court. The district court denied SR's motion. It held that the prime contract required arbitration only of disputes between UHS and SR, so Peek's dispute with SR was not arbitrable under the MSA because it did not involve UHS and, therefore, could not involve common issues of fact or law that SR must arbitrate under the prime contract. SR appeals, and we reverse.1 11. On appeal, SR argues that Peek's dispute involves issues of fact and law about the reasonableness of its additional costs that SR must arbitrate with UHS under the prime contract, so this dispute is therefore

'This court stayed litigation below pending resolution of this appeal, which order we now vacate.

SUPREME COURT OF NEVADA 5 1947A arbitrable as between SR and Peek under the MSA provision.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

At&T Technologies, Inc. v. Communications Workers
475 U.S. 643 (Supreme Court, 1986)
Cummings v. Fedex Ground Package System, Inc.
404 F.3d 1258 (Tenth Circuit, 2005)
Christopher L. Gore v. Alltel Commu
666 F.3d 1027 (Seventh Circuit, 2012)
Holcomb Condominium Homeowners' Ass'n v. Stewart Venture, LLC
300 P.3d 124 (Nevada Supreme Court, 2013)
Phillips v. Parker
794 P.2d 716 (Nevada Supreme Court, 1990)
Clark County Public Employees Ass'n v. Pearson
798 P.2d 136 (Nevada Supreme Court, 1990)
Pueblo of Laguna v. Cillessen & Son, Inc.
682 P.2d 197 (New Mexico Supreme Court, 1984)
Exber, Inc. v. Sletten Construction Company
558 P.2d 517 (Nevada Supreme Court, 1976)
Kerner v. Gilt
296 So. 2d 428 (Louisiana Court of Appeal, 1974)
State Ex Rel. Masto v. SECOND JUDICIAL DIST. CT.
199 P.3d 828 (Nevada Supreme Court, 2009)
Papalote Creek II, L.L.C. v. Lower Colorado River
918 F.3d 450 (Fifth Circuit, 2019)
Eversole v. Sunrise Villas VIII Homeowners Ass'n
925 P.2d 505 (Nevada Supreme Court, 1996)
State v. Second Judicial District Court
199 P.3d 828 (Nevada Supreme Court, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
2022 NV 41, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sr-constr-inc-v-peek-bros-constr-inc-nev-2022.