SPS Ltd. Partnership, LLLP v. Sparrows Point, LLC

122 F. Supp. 3d 239, 2015 U.S. Dist. LEXIS 103590, 2015 WL 4724883
CourtDistrict Court, D. Maryland
DecidedAugust 7, 2015
DocketCivil No. JFM-14-589
StatusPublished
Cited by3 cases

This text of 122 F. Supp. 3d 239 (SPS Ltd. Partnership, LLLP v. Sparrows Point, LLC) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SPS Ltd. Partnership, LLLP v. Sparrows Point, LLC, 122 F. Supp. 3d 239, 2015 U.S. Dist. LEXIS 103590, 2015 WL 4724883 (D. Md. 2015).

Opinion

MEMORANDUM

J. FREDERICK MOTZ, District Judge.

Plaintiffs SPS Limited Partnership LLLP and SPS 35, LLC (“SPS”) bring this lawsuit against defendants Sparrow Point, LLC and Sparrow Point Terminal, LLC (“SP Terminal”) (collectively “defendants”), seeking recovery under the Comprehensive Environmental Response, Compensation, and Liability Act (“CERCLA”), 42 U.S.C. § 9601 et seq.; and four Mary[241]*241land common law claims — negligence, trespass, nuisance, and strict liability. SPS alleges that defendants have caused “ongoing and continuous discharge of pollutants” from their ■ “Steel Mill Site” onto SPS’s “Shipyard Site” in Sparrows Point, Maryland. ■ Pending is a."partial motion to dismiss filed by SP Terminal which argues that SPS’s state law claims are barred by issue preclusion (collateral estoppel) and, alternatively, Maryland’s applicable statute of limitations. (ECF No. 42). ,

The motion is fully briefed, and no oral argument is necessary. See Local ’Rule 105.6. For the reasons set forth below, the motion is denied.

BACKGROUND

This dispute involves the alleged continuous flow of hazardous chemicals from’ the Steel Mill Site onto the adjacent parcel of land referred to as the Shipyard Site. SPS acquired title to the Shipyard Site in early March 2004, which constitutes approximately 131.5 acres of dry land and a 13.4 acre excavated dry dock. (Id. ¶¶ 18-19). The Steel Mill, now owned and operated by SP Terminal, surrounds the Shipyard Site on three sides. Originally both sites were owned by the Bethlehem Steel Corporation (“BSC”) but after a series of transactions both parcels became owned by independent parties. In February 1997 the federal EPA and Maryland Department of the Environment (“MDE”) sued BSC for violating federal and state environmental law by causing “a release of hazardous wastes ... substances and/or ... constituents into the environment at and/or from the Steel Mill Site” including benzene, naphthalene, toluene, arsenic and lead. (Id. ¶¶21, 24-25). BSC entered into a Consent Decree with the EPA and MDE on October 8, 1997 pursuant to which BSC “agreed to investigate and address certain. environmental conditions at the Steel Mill- Site and the Shipyard Site.” (Id. ¶ 22).1 The EPA removed the Shipyard Site from the Consent Decree in June 2006, but the Steel Mill Site remains bound by it. (Id. ¶ 23).

When SPS purchased the Shipyard Site in 2004 it “inherited an NPDES [National Pollutant Discharge Elimination System] permit that had 'béen in draft form for a numbér of years.” (Id. ¶ 32). As part of that permit, the amount of benzene associated with the “dewatering/trim pumps at the Graving Dock” on the Shipyard Site was specifically limited. Id. In 2007 the MDE asked SPS to sample the benzene levels at its “underdrain -pumps,” after which the .parties finalized a revised NPDES permit which included a benzene limit at the underdrain pumps effective February 1, 2010. (Id. ¶¶ 33-35). In order to comply with the benzene limit at the underdrain pumps, SPS installed a waste-water treatment system - which “has amounted to more than $700,000 and is expected to cost an additional $20,000 per month in operating and maintenance costs.” (Id. ¶ 38). SPS attributes the continued elevated benzene levels at the Shipyard Site to discharges from the Steel Mill, and alleges that despite the Consent Decree apparently remaining in force, “the discharges continue to flow onto the Shipyard Site.” (Id. ¶ 37). ’

On September 17, 2010, SPS filed a lawsuit against several defendants including the owner and operator of the Steel Mill at that time — Severstal Sparrows Point, LLC — alleging the identical conduct and causes of action (“the Severstal case”) as it does now.2 Defendants filed a motion to [242]*242dismiss which I granted in part on July 5, 2011, dismissing SPS’s four claims under Maryland law (negligence, trespass, nuisance, and strict liability) for falling outside of the applicable three-year statute of limitations. SPS Ltd. P’ship v. Severstal Sparrows Point, LLC, 808 F.Supp.2d 794, 814-815 (D.Md.2011). I held that SPS was on inquiry notice, if not actual notice, of the alleged hazardous discharge from the Steel Mill Site on February 22, 2014 because various public documents, including an environmental assessment that SPS attached to its VCP application, indicated possible benzene contamination of the Shipyard Site. Id. On July 31, 2013, I signed a settlement order proposed by the parties which dismissed the case.

SPS filed the complaint in the present case on February 28, 2014 against several defendants, including Sparrows Point, LLC (who had acquired the Steel Mill in 2012). After SP Terminal purchased the Steel Mill from Sparrows Point in 2014, SPS filed a second amended complaint which named it as a defendant, retained Sparrows Point, LLC, and dismissed all other defendants. SP Terminal has filed a partial motion to dismiss (ECF No. 42) which seeks dismissal of SPS’s four claims under Maryland common law.

STANDARD

When ruling on a motion brought under Rule 12(b)(6), the court must “accept the well-pled allegations of the complaint as true,” and “construe the facts and reasonable inferences derived therefrom in the light most favorable to the plaintiff.” Ibarra v. United States, 120 F.3d 472, 474 (4th Cir.1997). “Even though the requirements for pleading a proper complaint are substantially aimed at assuring that the defendant be given adequate notice of the nature of a claim being made against him, they also provide criteria for defining issues for trial and for early disposition of inappropriate complaints.” Francis v. Giacomelli, 588 F.3d 186, 192 (4th Cir. 2009). “The mere recital of elements of a cause of action, supported only by conclu-soiy statements, is not sufficient to survive a motion made pursuant to Rule 12(b)(6).” Walters v. McMahen, 684 F.3d 435, 439 (4th Cir.2012) (citing Ashcroft v. Iqbal, 556 U.S. 662, 678, 129 S.Ct. 1937, 173 L.Ed.2d 868 (2009)). To survive a motion to dismiss, the factual allegations of a complaint “must be enough to raise a right to relief above the speculative level ... on the assumption that all the allegations in the complaint are true (even if doubtful in fact).” Bell Atl. Corp. v. Twombly, 550 U.S. 544, 555, 127 S.Ct. 1955, 167 L.Ed.2d 929 (2007) (internal citations and alterations omitted). “To satisfy this standard, a plaintiff need not ‘forecast’ evidence sufficient to prove the elements of the claim.... However, the complaint must allege sufficient facts to establish those elements.” Walters, 684 F.3d at 439 (internal citations and quotation marks omitted). “Thus, while a plaintiff does not need to demonstrate in a complaint that the right to relief is ‘probable,’ the complaint must advance the plaintiffs claim ‘across the line from conceivable to plausible.’ ” Id. (quoting Twombly, 550 U.S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
122 F. Supp. 3d 239, 2015 U.S. Dist. LEXIS 103590, 2015 WL 4724883, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sps-ltd-partnership-lllp-v-sparrows-point-llc-mdd-2015.