Sprint PCS v. Washington County

63 P.3d 1261, 186 Or. App. 470, 2003 Ore. App. LEXIS 199
CourtCourt of Appeals of Oregon
DecidedFebruary 19, 2003
DocketLUBA 20-02042; A119313
StatusPublished

This text of 63 P.3d 1261 (Sprint PCS v. Washington County) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sprint PCS v. Washington County, 63 P.3d 1261, 186 Or. App. 470, 2003 Ore. App. LEXIS 199 (Or. Ct. App. 2003).

Opinion

KISTLER, J.

John and Sharon Fritz petition for review of a Land Use Board of Appeals (LUBA) decision. They assert that LUBA erred when it remanded a Washington County decision that rejected Sprint PCS’s application to site a cell phone tower on exclusive farm use (EFU) land. We affirm LUBA’s decision as modified below.

Sprint provides wireless telecommunication services. Having decided to improve its wireless communications coverage along a portion of Highway 219, it applied for a permit from Washington County to locate a cell phone tower on EFU land. In its application, Sprint identified three objectives for the proposed tower: enhance telecommunications service along the identified section of Highway 219; enhance telecommunications service to the rural area surrounding the section of Highway 219; and create antenna space to be leased to other wireless communications service providers. Sprint determined that an antenna with a height between 825 and 875 feet above mean sea level was necessary to provide the desired coverage. It identified a “search ring” that encompassed the area where the facility could be located to provide the necessary coverage.1

There were 63 potential sites within the search ring; 26 were zoned AF-102 and the rest were zoned EFU. Sprint rejected 17 of the AF-10 sites because the elevations were too low to site a 100- to 150-foot antenna. It contacted the owners of the nine remaining AF-10 sites to lease land for its tower but was unable to do so. Based on its inability to secure a lease for any of the nine AF-10 sites, Sprint determined that the sites were not reasonable alternatives and that, to meet its identified objectives, it was necessary to site its cell phone [473]*473tower on EFU land. Sprint accordingly submitted an application to Washington County for a permit to site a 154-foot monopole tower with 12 antennas on a designated parcel of EFU land.

The county planning staff, after reviewing Sprint’s application, initially recommended that the permit be denied because Sprint had failed to justify both its coverage needs and the starting point of the search ring that it had used. On December 20, 2001, a county hearing officer conducted a hearing at which Sprint presented additional evidence regarding its coverage needs. The Fritzes intervened and presented evidence at this hearing, mainly in the form of testimony from an engineer, Donald Weber. Weber questioned several aspects of Sprint’s request, including elevation determinations made by Sprint, tower height, search ring size, and location. Weber explained that one possible alternative would be collocating Sprint’s antenna on an existing tower.

Sprint asked that the hearing record be held open and, on January 18, 2002, presented rebuttal evidence to Weber’s testimony. On February 1, 2002, the Fritzes responded to Sprint’s rebuttal with additional testimony from Weber and a memorandum from their attorney urging the hearing officer to deny the application. On February 1, 2002, the county planning staff issued an addendum to its staff report, recommending approval of Sprint’s application based on the information that Sprint provided. On February 8, 2002, Sprint submitted additional information to the county that included an analysis of 15 additional sites outside its initial search ring. On March 13, 2002, the hearing officer issued a decision denying the application. The hearing officer did not make independent findings of fact or conclusions of law in his decision but instead adopted the Fritzes’ February 1, 2002, memorandum.

Sprint appealed the county’s decision to LUBA, asserting that the county had improperly interpreted ORS 215.275. LUBA agreed with Sprint, finding that the county had erred (1) in balancing farmland preservation against the technical and engineering feasibility and land options available to Sprint; (2) in considering alternatives that were outside the scope of ORS 215.275; and (3) in not making independent findings and conclusions. LUBA remanded the case [474]*474to the county to make findings in light of its explanation of the applicable legal principles.

On judicial review, the Fritzes focus primarily on LUBA’s explanation of the legal principles that the hearing officer should apply on remand. Specifically, they argue that (1) LUBA incorrectly held that there was no need to balance competing interests such as farmland preservation and technological feasibility in determining whether it is necessary to site a utility facility on EFU land; (2) LUBA erroneously determined that the county was precluded from examining any reasonable alternatives not contemplated in the utility’s business plan; and (3) LUBA erred in remanding the decision because there were valid bases for denial in the decision that Sprint had not challenged.

We begin with the Fritzes’ first assignment of error — that LUBA erred in holding that local governments should not balance the need to preserve farmland in interpreting the terms of ORS 215.275.3 Two statutes are relevant. ORS 215.283(1)(d) provides that “utility facilities necessary for public service” may be sited on EFU land. ORS 215.275(1) provides that a utility facility is necessary for public service within the meaning of ORS 215.283(1)(d) “if the facility must be sited in an exclusive farm use zone in order to provide the service.” ORS 215.275(2) sets out what an applicant must prove in order to demonstrate that a utility facility is necessary. An applicant must show that “reasonable alternatives have been considered” and that the facility “must be sited in an exclusive farm use zone due to one or more of the following [six] factors.” ORS 215.275(2). Among those factors are “technological and engineering feasibility.” ORS 215.275(2)(a).

Relying on McCaw Communications, Inc. v. Marion County, 96 Or App 552, 773 P2d 779 (1989), the Fritzes argued below that the terms “reasonable alternatives” and “feasibility” in ORS 215.275(2) and ORS 215.275(2)(a) should be interpreted in light of the goal of preserving farmland set out in ORS 215.243. LUBA disagreed with that argument, reasoning:

[475]*475“[I]n adopting ORS 215.275

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McCaw Communications, Inc. v. Marion County
773 P.2d 779 (Court of Appeals of Oregon, 1989)
Dayton Prairie Water Ass'n v. Yamhill County
11 P.3d 671 (Court of Appeals of Oregon, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
63 P.3d 1261, 186 Or. App. 470, 2003 Ore. App. LEXIS 199, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sprint-pcs-v-washington-county-orctapp-2003.