Springfield Engine & Thresher Co. v. Kennedy

34 N.E. 856, 7 Ind. App. 502, 1893 Ind. App. LEXIS 282
CourtIndiana Court of Appeals
DecidedSeptember 27, 1893
DocketNo. 730
StatusPublished
Cited by22 cases

This text of 34 N.E. 856 (Springfield Engine & Thresher Co. v. Kennedy) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Springfield Engine & Thresher Co. v. Kennedy, 34 N.E. 856, 7 Ind. App. 502, 1893 Ind. App. LEXIS 282 (Ind. Ct. App. 1893).

Opinion

Lotz, J.

The appellant was the plaintiff below, and began this action to recover judgment on certain notes, and to foreclose a chattel mortgage securing the same. Pending the suit, the mortgaged property was seized and sold by the appellant under the stipulations contained in the said mortgage, so that the only controversy in this court is as to the right of appellant to a money judgment [504]*504for the remainder due on the notes. The appellee answered in eleven paragraphs.

1st. That the notes in suit were executed without any consideration.

To the second a demurrer was sustained.

3d. That the notes were paid since the institution of -the suit.

4th. Payment in full before suit.

„ 5th. Breach of an implied warranty in the sale of a machine for which the notes in suit were executed.

6th. Breach of a verbal warranty in the sale of said machine.

7th. Also breach of verbal warranty in sale of said machine.

8th was withdrawn.

9th. Breach of a written warranty alleged to be lost.

10th and 11th. Breaches of written warranty, coupled with averments showing that the plaintiff waived the performance of certain conditions in the contract of warranty resting upon the defendants.

A demurrer was sustained to the second and overruled as to the other paragraphs. The plaintiff replied in two paragraphs, and a demurrer was sustained to the second. There was a trial of the issues by the court. The court, at the request of appellant, made a special finding of the facts, and stated the conclusions of law thereon. The conclusion of law was that the consideration of the notes in suit had wholly failed, and that the defendants were entitled to judgment for costs.

Appellant assigns as errors the overruling of the demurrers to the 5th, 6th, 7th, 9th, 10th and 11th paragraphs of answer; the sustaining of the demurrer to the second paragraph of reply; and that the court erred in its conclusions of law. There was no motion for a new trial, and the evidence is not in the record. A motion [505]*505for a new trial calls in question the correctness of the finding of facts, but does not challenge the conclusions of law stated on the facts. An exception to the conclusions of law properly precedes the motion for a new trial, and concedes, for the purpose of securing a decision upon the facts stated in the finding, that the facts are found as the evidence requires. Elliott’s App. Proced., section 793.

The facts not being challenged by a motion for a new trial, this court, in the condition of the record, will conclusively presume that the findings of facts are as the evidence requires.

An examination of the record and special findings affirmatively shows that the findings and judgment of the court are based upon the 10th paragraph of the answer and the answer of payment. It is a rule well established, that, where the complaint or answer consists of two or more paragraphs, the overruling of a demurrer to a bad paragraph is not reversible error, if the record affirmatively shows that the findings and judgment of the court rest on other paragraphs of the pleading- that are good. Blessing v. Blair, 45 Ind. 546; Keegan v. Carpenter, 47 Ind. 597; Blasingame v. Blasingame, 24 Ind. 86; Nave v. Wilson, Admr., 33 Ind. 294; Wolf v. Schofield, 38 Ind. 175; Peery v. Greensburgh, etc., Turnpike Co., 43 Ind. 321; Hawley, Admr., v. Smith, Admr., 45 Ind. 183; McComas v. Haas, 93 Ind. 276; State, for Use, v. Julian, 93 Ind. 292; Bartlett v. Pittsburgh, etc., R. W. Co., 94 Ind. 281; Louisville, etc., R. W. Co. v. Davis, 94 Ind. 601; City of Aurora v. Bitner, 100 Ind. 396; Sohn v. Cambern, 106 Ind. 302.

Under these authorities, it is unnecessary for us to determine the sufficiency of any of the paragraphs of the answer, except the tenth. The action of the court, in [506]*506overruling the demurrers to the other answers, is not reversible error.

The tenth paragraph charges, in brief, that the notes declared on were given for the purchase of one steam vibrating separator, with all the necessary appliances usually furnished with such machines; that said sale was made in pursuance of a written contract entered into , between plaintiff and defendants, by which contract the plaintiff warranted that said machinery, with proper use and management, would do as good work as any of its size made for the same purpose, and to be of good materials and durable with proper care; that if said machine should fail to fill said warranty, written notice should be given to plaintiff at Springfield, Ohio, and also to the local agent of whom the machine was purchased, stating wherein it failed to fill said warranty, and a reasonable time allowed to remedy such defect; that if the machine could not be made to fill the warranty, it should be returned to the plaintiff, and plaintiff would cause it to perform good work or return the money and notes given for the same. It was further stipulated that the continued use of said machinery should be evidence of the fulfillment of the warranty and of full satisfaction on the part of the purchasers, who agreed thereafter to make no claim on the plaintiff; and, further, that if the'machinery, or any part thereof, should be delivered before settlement should be made as agreed, the defendants should waive all claims under the warranty.

It is further charged, that said machine would not, with proper usage, do as good work as any of the size made for that purpose, and was not properly constructed, and of good materials, and durable with proper care; that, by reason of its defective and imperfect construction, it continuously cut and crushed the wheat, rendering it of little value; that, by reason of its defective construction, [507]*507it wasted the wheat, and would not properly separate it from the straw, but continually left large amounts of the wheat remaining in the straw, and the same was carried away with the straw, threshed and unthreshed; that the plaintiff failed and refused to cause said machine to do good work and comply with said warranty, and failed to send a competent workman and to make said machine do good work, and failed to cancel and return said notes and mortgage, although defendants repeatedly applied for that purpose to plaintiff’s agent who sold them the machine, and failed to furnish another machine; that defendants offered to return said machine and demanded their notes. There are other averments in the paragraph which show how the defendants came to accept the machine before the notes were executed, and why the defendants failed to give written information of the defects to the plaintiff at its home office, and of the efforts made by the plaintiff through its agents to make said machine do good work after notice to them, and of their failure so to do.

As to this paragraph, appellant’s counsel say it is defective in that there is no averment that the defendants notified the plaintiff in writing at its home office in Springfield, Ohio. But there is an averment that its general agent was notified, and that through its agent it accepted and acted upon such notice. By such action, the appellant waived the written notice. Nat’l Bank and Loan Co. v. Dunn, 106 Ind. 110; Gaar, Scott & Co. v. Rose, 3 Ind.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schaefer v. Fiedler
63 N.E.2d 310 (Indiana Court of Appeals, 1945)
Maxwell Implement Co. v. Fitzgerald
146 N.E. 883 (Indiana Court of Appeals, 1925)
Leroy v. Hagen
175 N.W. 718 (North Dakota Supreme Court, 1919)
Ventura Manufacturing & Implement v. Warfield
174 P. 382 (California Court of Appeal, 1918)
Georgia Life Insurance v. Otter Creek Coal Co.
119 N.E. 151 (Indiana Court of Appeals, 1918)
International Harvester Co. of America v. Haueisen
118 N.E. 320 (Indiana Court of Appeals, 1918)
Laramore v. Blumenthal
108 N.E. 602 (Indiana Court of Appeals, 1915)
Acme Harvesting Machine Co. v. Barkley
118 N.W. 690 (South Dakota Supreme Court, 1908)
Siebe v. Heilman Machine Works
77 N.E. 300 (Indiana Court of Appeals, 1906)
Marion Manufacturing Co. v. Harding
58 N.E. 194 (Indiana Supreme Court, 1900)
Aultman & Co. v. Richardson
52 N.E. 86 (Indiana Court of Appeals, 1898)
Port Huron Engine & Thresher Co. Engine v. Smith
52 N.E. 106 (Indiana Court of Appeals, 1898)
Burke v. Keystone Manufacturing Co.
48 N.E. 382 (Indiana Court of Appeals, 1897)
Levi v. Allen
43 N.E. 571 (Indiana Court of Appeals, 1896)
Kern v. Saul
42 N.E. 496 (Indiana Court of Appeals, 1895)
Germania Fire Insurance v. Stewart
42 N.E. 286 (Indiana Court of Appeals, 1895)
Milwaukee Mechanics' Insurance v. Stewart
42 N.E. 290 (Indiana Court of Appeals, 1895)
Watts v. Moffett
40 N.E. 533 (Indiana Court of Appeals, 1895)
Ellinger v. Rawlings
40 N.E. 146 (Indiana Court of Appeals, 1895)
Walter A. Wood Mowing & Reaping Machine Co. v. Irons
36 N.E. 862 (Indiana Court of Appeals, 1894)

Cite This Page — Counsel Stack

Bluebook (online)
34 N.E. 856, 7 Ind. App. 502, 1893 Ind. App. LEXIS 282, Counsel Stack Legal Research, https://law.counselstack.com/opinion/springfield-engine-thresher-co-v-kennedy-indctapp-1893.