Spring Industries, Inc. v. Ohio Department of Transportation

555 N.E.2d 339, 51 Ohio Misc. 2d 6, 1989 Ohio Misc. LEXIS 10
CourtOhio Court of Claims
DecidedJune 14, 1989
DocketNo. 87-12871
StatusPublished

This text of 555 N.E.2d 339 (Spring Industries, Inc. v. Ohio Department of Transportation) is published on Counsel Stack Legal Research, covering Ohio Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Spring Industries, Inc. v. Ohio Department of Transportation, 555 N.E.2d 339, 51 Ohio Misc. 2d 6, 1989 Ohio Misc. LEXIS 10 (Ohio Super. Ct. 1989).

Opinion

Shoemaker, J.

On December 30, 1987, plaintiff, Spring Industries, Inc., filed this action against defendant, the Ohio Department of Transportation (“defendant” or “ODOT”). This action is one of three cases between the parties which were consolidated for trial. For identification purposes this action shall be known as the “Flagpersons” case.

Plaintiff alleges defendant failed to meet its obligation arising from a contractual relationship entered into by the parties on or about February 21, 1986, known as Project No. 106-86 (“project”). Plaintiff also alleges defendant has been unjustly enriched because plaintiff provided defendant with labor and materials for the project and defendant has benefited from said performance without payment therefor.

This cause came on for trial on January 17, 1989. The court has considered the evidence and arguments presented by counsel and renders the following decision.

Findings of Fact

Plaintiff was a contractor in the business of constructing, manufacturing, hauling and placing of highway materials at the time of the incident in question, and defendant was the agency for the state of Ohio responsible for the maintenance and construction of the state’s highway transportation system at the time of the incident in question. On or about February 21, 1986, plaintiff contracted with defendant for a roadway paving job as part of the project. This controversy involves the roadway resurfacing of sections of State Route 39, a two-lane secondary roadway in Holmes County, Ohio.

The parties agree that the Agreement, Proposal and Contract Bond (“agreement”), the State of Ohio Department of Transportation Construction and Material Specification Manual (“manual”) dated January 1, 1985, and the project plan, particularly page thirteen pertaining to traffic control (“traffic control plan”), are essential components of the contract for the project.

Plaintiff was responsible for traffic control of the construction zone while it was performing the pavement work. Traffic control guidelines were established by defendant to ensure public safety while the roadway was under construction, and plaintiff was re[7]*7quired to adhere to traffic control guidelines established by the traffic control plan while performing the pavement work. The traffic control plan provided a diagram for the placement of traffic control devices within the construction zone, including the placement of two flagpersons. Flag-persons were placed at strategic locations within the construction zone and were under the control and direction of plaintiff. Flagpersons are responsible for the management of traffic flow within a construction zone.

General Note No. 7 of the traffic control plan states that “[fjlagmen shall be used to control traffic continuously for as long as one lane operation is in effect” and “within the length of closure, provision shall be made to control traffic entering from intersecting streets and major driveways as necessary to prevent wrong-way movements and to keep vehicles off of new pavement not ready for traffic.”

At all times on said project plaintiff provided at least two designated flagpersons on the roadway paving job. Plaintiff also utilized other laborers to assist in traffic control by acting as flagpersons when not performing labor duties and specifically instructed one laborer to act as a flagperson when not performing labor duties.

Section 105.09 of the manual provides the defendant’s project engineer with the authority to suspend any work that is improperly performed. In the early morning of August 6, 1986, plaintiff began working on State Route 39 with three flagpersons on the job. The hours of 7:00 a.m. through 11:00 a.m. and 3:00 p.m. through 5:00 p.m. were the periods of the day involving the most traffic. At approximately midday the third flagperson was removed from the job. Soon thereafter, defendant’s project supervisor, Larry Arnold, telephoned his supervisor, Robert Giauque, ODOT’s District Construction Engineer, and informed him that plaintiff could not maintain traffic control with two flagpersons. Giauque told Arnold that he was to shut down the project if traffic control was not maintained. Accordingly, plaintiff was informed that it would have to discontinue work on the project if the third flagperson was not returned to the construction zone. Plaintiff did not perceive any traffic problems due to its actions and, therefore, continued paving, and proceeded with two flagpersons on the job. Defendant again opposed said action.

Later that afternoon, an employee of defendant, pursuant to Larry Arnold’s directive, placed a truck in front of plaintiff’s pavement equipment, thus physically preventing plaintiff from proceeding with the project. Sometime later, defendant removed the vehicle from blocking the plaintiff’s pavement equipment; however, it is unclear how long defendant prevented plaintiff’s pavement work.

Plaintiff’s president, Glenn Straub, and defendant’s agent, Robert Giauque, had a final discussion at approximately 2:00 p.m. on said day concerning the dispute. As a result of their discussion and because defendant’s truck was preventing any further paving progress, plaintiff agreed to stop working on the project.

The pertinent asphalt production plant was informed by plaintiff to shut down the production of asphalt material immediately. The asphalt plant was approximately twenty miles from the project site. At that time, however, there were four truckloads of asphalt en route to the project site. Plaintiff’s trucks had been delivering asphalt to the jobsite continuously throughout the day at five-to-twelve-minute intervals. Asphalt paving [8]*8material is extremely hot (over three hundred degrees) and must be removed from the truck to prevent damaging it.

Defendant departed the project site at approximately 2:30 p.m. Within one hour after defendant’s departure, plaintiff dumped and placed on the job site the aforementioned four truckloads (fifty-seven cubic yards) of asphalt.

The four truckloads of asphalt placed on the roadway have performed to the satisfaction of the defendant. However, plaintiff- has not been paid for the work involved in the placement of the four truckloads of asphalt material and, as a result, plaintiff has not been reimbursed for expenses equal to $3,800.

Finally, no accidents or traffic problems occurred in the area on the day of the incident.

Conclusions of Law

As aforementioned, the traffic control plan was an essential element of the agreement between plaintiff and defendant and the terms in said plan pertain to the issue at bar. The terms of the plan should be interpreted in observance of their plain meaning.

“Contracts are to be construed according to the sense and meaning of the terms which the parties have used. Words in a written contract are to be interpreted according to their common, ordinary, and usual meaning. It has been said the grammatical and ordinary sense of words and phrases used in a contract must be followed unless it would lead to manifest absurdity, repugnance, or inconsistency. * * *” (Footnotes omitted.) 18 Ohio Jurisprudence 3d (1980) 24-25, Contracts, Section 141.

Defendant contends that the utilization of three flagpersons was necessary to continue paving the roadway because of alleged heavy, congested side traffic and tourist traffic within the construction zone. Defendant cites to General Note No. 7 of the traffic control plan in support of its position. Note No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McClanahan v. McClanahan
72 N.E.2d 798 (Ohio Court of Appeals, 1946)
Hummel v. Hummel
14 N.E.2d 923 (Ohio Supreme Court, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
555 N.E.2d 339, 51 Ohio Misc. 2d 6, 1989 Ohio Misc. LEXIS 10, Counsel Stack Legal Research, https://law.counselstack.com/opinion/spring-industries-inc-v-ohio-department-of-transportation-ohioctcl-1989.