IN THE COURT OF APPEALS OF IOWA
No. 23-0647 Filed July 3, 2024
SPRING CREST TOWNHOMES WDM, LLC, Plaintiff-Appellee/Cross-Appellant,
vs.
MICKLE ELECTRIC & HEATING CO., INC. d/b/a MICKLE ELECTRIC & HEATING, LLC, Defendant-Appellant/Cross-Appellee. ________________________________________________________________
Appeal from the Iowa District Court for Dallas County, Charles C. Sinnard,
Judge.
A subcontractor appeals a ruling determining that it breached a construction
contract. The developer cross-appeals the ruling awarding the subcontractor an
offset for unbilled labor. AFFIRMED ON APPEAL AND CROSS-APPEAL.
Billy J. Mallory and Trevor A. Jordison of Mallory Law, West Des Moines,
for appellant/cross-appellee.
John F. Fatino and Parker Howe of Whitfield & Eddy, P.L.C., Des Moines,
for appellee/cross-appellant.
Heard by Ahlers, P.J., and Chicchelly and Buller, JJ. 2
AHLERS, Presiding Judge.
After a developer terminated a contract with a subcontractor, the two parties
disagree over who breached the contract and is responsible for the additional cost
incurred by the developer to hire a new subcontractor to finish the job.
I. Background Facts and Prior Proceedings
Spring Crest Townhomes WDM, LLC (Spring Crest) contracted with Mickle
Electric & Heating, LLC (Mickle) to complete electrical work on three buildings
within its townhome development. The contract provided that Mickle had twenty-
one days from “the date of commencement” to complete all work. The contract
defined the date of commencement as “the date that the Construction Manager
notifies the Subcontractor in writing or email when the work is to commence.”
As to the start date, Mickle’s written bid, which was incorporated into the
terms of the written contract between the parties, included a note stating, “if you
choose to go with us, please let me know as soon as possible. We would like to
get material ordered.” Shortly after the contract was signed, representatives from
the two companies had a phone conversation wherein Mickle shared it wanted to
get to work right away because it had workers waiting for work. Ultimately, Mickle
began work within a day or two after the contract was finalized despite not receiving
notification in “writing or email” stating that work was to begin. As the contract was
signed by Mickle on April 19, 2021, and by Spring Crest on April 20, and Mickle
started work on the project within a day or two, the electrical work would have
needed to be completed by around May 14 if the twenty-one-day period had begun
to run. 3
The electrical work was not completed by that time. Spring Crest provided
Mickle with extensions to complete the work. But on August 3, Spring Crest’s
construction manager confronted Mickle in a text message noting no one from
Mickle was doing any electrical work on the project. A Mickle employee responded
by email, noting that Mickle was behind schedule because the townhomes were
not ready for the trim work when its employees went to install it. She then provided
Spring Crest with a “loose schedule” for the remaining electrical work. Under that
schedule, work on one townhome would be completed on August 12 with the rest
of the work on the other townhomes completed by August 31.
But by August 12, work on the first townhome was not completed as
provided for in the schedule provided by Mickle’s employee. That was the final
straw for Spring Crest. Its attorney sent a letter to Mickle on August 13, informing
Mickle that it had until 4:00 p.m. on August 15 to complete all outstanding work.
Mickle did not complete the work by August 15. On August 16, Spring Crest sent
notice to Mickle that it was terminating their contract for cause. Spring Crest
contracted with two other electricians to complete the remaining electrical work on
the townhomes.
Spring Crest then brought this action against Mickle to recover the
difference between its contracted cost with Mickle and the amount it spent to have
the townhomes finished by the different electricians. Mickle responded with a bill
to Spring Crest for work it had completed before termination of the contract but
had yet to bill. It brought a counterclaim against Spring Crest for payment for those
amounts. 4
The case proceeded to a bench trial. The district court determined that
Mickle breached the contract and awarded Spring Crest damages. However, the
court offset that award by the amount Mickle was due for work completed prior to
Mickle’s termination. The court determined that, under the contract, Spring Crest
was the prevailing party entitled to attorney fees.
Mickle appeals, arguing it did not breach the contract and that Spring Crest
is not the sole prevailing party entitled to attorney fees. Spring Crest cross-
appeals, arguing that the court erred by awarding Mickle an offset for unbilled work.
II. Standard of Review
“[O]ur review of the district court’s contract interpretation and construction
is at law.” Homeland Energy Sols., LLC v. Retterath, 938 N.W.2d 664, 683 (Iowa
2020). “The district court’s factual findings have the effect of a special verdict and
are binding on us if supported by substantial evidence.” Metro. Prop. & Cas. Ins.
Co. v. Auto-Owners Mut. Ins. Co., 924 N.W.2d 833, 839 (Iowa 2019). “We view
the evidence in the light most favorable to the judgment when a party argues the
trial court’s ruling is not supported by substantial evidence.” Meincke v. Nw. Bank
& Tr. Co., 756 N.W.2d 223, 227 (Iowa 2008). “Evidence is substantial when
reasonable minds accept the evidence as adequate to reach a conclusion.” Id.
“Evidence is not insubstantial merely because we may draw different conclusions
from it; the ultimate question is whether it supports the finding actually made, not
whether the evidence would support a different finding.” Id. (citation omitted).
III. Discussion
Generally, when interpreting a contract, we look to the language used within
the four corners of the document. DuTrac Cmty. Credit Union v. Radiology Grp. 5
Real Est., L.C., 891 N.W.2d 210, 216 (Iowa 2017). “In the construction of written
contracts, the cardinal principle is that the intent of the parties must control, and
except in cases of ambiguity, this is determined by what the contract itself says.”
Id. (citation omitted). When the parties’ intent “is clear and unambiguous from the
words of the contract itself, we will enforce the contract as written.” Id. “If the
language of the contract is ambiguous, then we engage in interpretation in order
to determine ‘the meanings attached by each party at the time the contract was
made.’” Id. (citation omitted).
A. Mickle’s Appeal
1. Breach of contract
Mickle contends that the district court erred in concluding it breached the
contract for three reasons: (1) Spring Crest never sent written notice of
commencement, so the twenty-one-day clock never began; (2) it was impossible
Free access — add to your briefcase to read the full text and ask questions with AI
IN THE COURT OF APPEALS OF IOWA
No. 23-0647 Filed July 3, 2024
SPRING CREST TOWNHOMES WDM, LLC, Plaintiff-Appellee/Cross-Appellant,
vs.
MICKLE ELECTRIC & HEATING CO., INC. d/b/a MICKLE ELECTRIC & HEATING, LLC, Defendant-Appellant/Cross-Appellee. ________________________________________________________________
Appeal from the Iowa District Court for Dallas County, Charles C. Sinnard,
Judge.
A subcontractor appeals a ruling determining that it breached a construction
contract. The developer cross-appeals the ruling awarding the subcontractor an
offset for unbilled labor. AFFIRMED ON APPEAL AND CROSS-APPEAL.
Billy J. Mallory and Trevor A. Jordison of Mallory Law, West Des Moines,
for appellant/cross-appellee.
John F. Fatino and Parker Howe of Whitfield & Eddy, P.L.C., Des Moines,
for appellee/cross-appellant.
Heard by Ahlers, P.J., and Chicchelly and Buller, JJ. 2
AHLERS, Presiding Judge.
After a developer terminated a contract with a subcontractor, the two parties
disagree over who breached the contract and is responsible for the additional cost
incurred by the developer to hire a new subcontractor to finish the job.
I. Background Facts and Prior Proceedings
Spring Crest Townhomes WDM, LLC (Spring Crest) contracted with Mickle
Electric & Heating, LLC (Mickle) to complete electrical work on three buildings
within its townhome development. The contract provided that Mickle had twenty-
one days from “the date of commencement” to complete all work. The contract
defined the date of commencement as “the date that the Construction Manager
notifies the Subcontractor in writing or email when the work is to commence.”
As to the start date, Mickle’s written bid, which was incorporated into the
terms of the written contract between the parties, included a note stating, “if you
choose to go with us, please let me know as soon as possible. We would like to
get material ordered.” Shortly after the contract was signed, representatives from
the two companies had a phone conversation wherein Mickle shared it wanted to
get to work right away because it had workers waiting for work. Ultimately, Mickle
began work within a day or two after the contract was finalized despite not receiving
notification in “writing or email” stating that work was to begin. As the contract was
signed by Mickle on April 19, 2021, and by Spring Crest on April 20, and Mickle
started work on the project within a day or two, the electrical work would have
needed to be completed by around May 14 if the twenty-one-day period had begun
to run. 3
The electrical work was not completed by that time. Spring Crest provided
Mickle with extensions to complete the work. But on August 3, Spring Crest’s
construction manager confronted Mickle in a text message noting no one from
Mickle was doing any electrical work on the project. A Mickle employee responded
by email, noting that Mickle was behind schedule because the townhomes were
not ready for the trim work when its employees went to install it. She then provided
Spring Crest with a “loose schedule” for the remaining electrical work. Under that
schedule, work on one townhome would be completed on August 12 with the rest
of the work on the other townhomes completed by August 31.
But by August 12, work on the first townhome was not completed as
provided for in the schedule provided by Mickle’s employee. That was the final
straw for Spring Crest. Its attorney sent a letter to Mickle on August 13, informing
Mickle that it had until 4:00 p.m. on August 15 to complete all outstanding work.
Mickle did not complete the work by August 15. On August 16, Spring Crest sent
notice to Mickle that it was terminating their contract for cause. Spring Crest
contracted with two other electricians to complete the remaining electrical work on
the townhomes.
Spring Crest then brought this action against Mickle to recover the
difference between its contracted cost with Mickle and the amount it spent to have
the townhomes finished by the different electricians. Mickle responded with a bill
to Spring Crest for work it had completed before termination of the contract but
had yet to bill. It brought a counterclaim against Spring Crest for payment for those
amounts. 4
The case proceeded to a bench trial. The district court determined that
Mickle breached the contract and awarded Spring Crest damages. However, the
court offset that award by the amount Mickle was due for work completed prior to
Mickle’s termination. The court determined that, under the contract, Spring Crest
was the prevailing party entitled to attorney fees.
Mickle appeals, arguing it did not breach the contract and that Spring Crest
is not the sole prevailing party entitled to attorney fees. Spring Crest cross-
appeals, arguing that the court erred by awarding Mickle an offset for unbilled work.
II. Standard of Review
“[O]ur review of the district court’s contract interpretation and construction
is at law.” Homeland Energy Sols., LLC v. Retterath, 938 N.W.2d 664, 683 (Iowa
2020). “The district court’s factual findings have the effect of a special verdict and
are binding on us if supported by substantial evidence.” Metro. Prop. & Cas. Ins.
Co. v. Auto-Owners Mut. Ins. Co., 924 N.W.2d 833, 839 (Iowa 2019). “We view
the evidence in the light most favorable to the judgment when a party argues the
trial court’s ruling is not supported by substantial evidence.” Meincke v. Nw. Bank
& Tr. Co., 756 N.W.2d 223, 227 (Iowa 2008). “Evidence is substantial when
reasonable minds accept the evidence as adequate to reach a conclusion.” Id.
“Evidence is not insubstantial merely because we may draw different conclusions
from it; the ultimate question is whether it supports the finding actually made, not
whether the evidence would support a different finding.” Id. (citation omitted).
III. Discussion
Generally, when interpreting a contract, we look to the language used within
the four corners of the document. DuTrac Cmty. Credit Union v. Radiology Grp. 5
Real Est., L.C., 891 N.W.2d 210, 216 (Iowa 2017). “In the construction of written
contracts, the cardinal principle is that the intent of the parties must control, and
except in cases of ambiguity, this is determined by what the contract itself says.”
Id. (citation omitted). When the parties’ intent “is clear and unambiguous from the
words of the contract itself, we will enforce the contract as written.” Id. “If the
language of the contract is ambiguous, then we engage in interpretation in order
to determine ‘the meanings attached by each party at the time the contract was
made.’” Id. (citation omitted).
A. Mickle’s Appeal
1. Breach of contract
Mickle contends that the district court erred in concluding it breached the
contract for three reasons: (1) Spring Crest never sent written notice of
commencement, so the twenty-one-day clock never began; (2) it was impossible
for Mickle to perform within twenty-one days; and (3) Spring Crest actually
breached when it terminated the contract.
We find it unnecessary to resolve Mickle’s claim that the twenty-one-day
clock never began to run. This is because the district court appropriately found an
independent basis for Spring Crest to terminate the contract. Under section 6.3 of
the contract, Spring Crest had the right to terminate the contract if Mickle “at any
time and for any reason” failed to perform its work under the contract “in a diligent,
efficient, timely, workmanlike, safe and careful manner.”
There is no dispute Mickle began working on the project within a day or two
after both parties signed the contract in April, yet Mickle had not completed its part
of the project by early August. While Spring Crest may have been dissatisfied with 6
the timeliness of Mickle’s work even earlier, there is no question Spring Crest
notified Mickle of its dissatisfaction no later than August 2 when it notified Mickle
of upcoming deadlines it had to meet and it would accept “NO EXCUSES” for
Mickle not getting its work done. There is also no question that Mickle then
provided Spring Crest with a schedule Mickle created to complete the project by
August 31. Despite providing this new schedule over three months after starting
the project and the new schedule contemplated a period to complete the project
that exceeded the twenty-one days for project completion called for by the contract,
Mickle missed the very first deadline provided for in its new schedule. This was
the final straw that caused Spring Crest to deem Mickle in default and exercise its
right under section 6.3 to give Mickle a forty-eight-hour notice to cure the default.
Mickle did not cure the default after receiving the notice, entitling Spring Crest to
terminate the contract. The district court’s finding that Mickle breached the contract
is supported by substantial evidence, so we are bound by it. See Iowa R. App.
P. 6.904(3)(a).
We turn next to Mickle’s contention that it was impossible to complete the
work in a timely manner and therefore its failure to do so does not constitute a
breach of the contract entitling Spring Crest to terminate it. “In order to excuse
nonperformance, the term must be objectively impossible to perform. The
impossibility of performance cannot be due to the fault of the nonperforming party.”
DuTrac, 891 N.W.2d at 217 (internal citation omitted).
Mickle did not persuade the district court that it was prevented from
performing, and the district court’s finding is supported by substantial evidence.
Section 2.2.3 of the contract required Mickle to “immediately notify the 7
Construction Manager of any . . . problems that would cause a delay . . . under [its]
phase of work.” So under the terms of the contract, Mickle was required to inform
Spring Crest of any issues that would delay its work. But nothing in the record
establishes Mickle informed Spring Crest it could not complete the electrical work
due to delays caused by others.
The only evidence in the record that Mickle informed Spring Crest that it
could not complete its work due to lack of progress by others is an email from the
Mickle office manager sent on August 3 in response to Spring Crest demanding
completion with “NO EXCUSES.” In that email, Mickle’s representative claimed
Mickle went to complete trim work during “the weeks of 7/19, 7/26 & 8/2 but the
units weren’t ready.” This falls short of establishing that it was impossible for
Mickle to complete the work within the allotted time, particularly because the
contract required Mickle to inform Spring Crest of any delays, which would have
allowed Spring Crest to intervene with the other trades to help keep the project on
schedule. Furthermore, the email raising claimed delays for the first time also
included a new schedule created by Mickle for completing the project, but, as
previously noted, Mickle failed to follow that schedule too with no claim that its
failure was caused by others.
Finally, the replacement electrical contractor who finished the work after
Spring Crest terminated the contract with Mickle testified that it was able to
complete its work immediately after taking over the project. This evidence further
refutes Mickle’s claim that it was hampered by others in fulfilling its contractual
obligations. The district court’s finding that it was not impossible for Mickle to fulfill 8
its contractual obligation is supported by substantial evidence, and we are bound
by it. See Iowa R. App. 6.904(3)(a).
For the same reasons we find Mickle breached the contract and Spring
Crest properly terminated it, we reject Mickle’s contention that Spring Crest
breached the contract. Accordingly, we affirm the district court’s ruling determining
that Mickle breached the contract and awarding damages to Spring Crest.
2. Attorney Fees
Next, Mickle challenges the district court’s determination that Spring Crest
is the sole prevailing party and entitled to attorney fees under the contract. It
reasons that because the district court also determined that Mickle is entitled to an
offset to cover work it had completed but not billed prior to termination of the
contract, both parties prevailed and it should not be responsible for Spring Crest’s
attorney fees.
Section 11.2 of the contract provides, “The prevailing party in any legal
proceeding related to this Agreement, shall be entitled to payment of reasonable
attorney’s fees, costs, and interest at the legal rate.” Our supreme court
considered similar language in NCJC, Inc. v. WMG, L.C., 960 N.W.2d 58 (Iowa
2021). The contract in that case stated, “If either party files suit to enforce any of
the terms of this Lease, the prevailing party shall be entitled to recover court costs
and reasonable attorney’s fees.” NCJC, Inc., 960 N.W.2d at 62. Our supreme
court emphasized the use of “the prevailing party” makes clear only a singular party
can be the prevailing party rather than multiple parties. See id. That same singular
language is used here, meaning either Spring Crest or Mickle can be the prevailing
party, not both as Mickle contends. While the district court did award Mickle an 9
offset, ultimately Spring Crest prevailed as a whole after establishing Mickle
breached the contract. Accordingly, we agree with the district court that Spring
Crest was the prevailing party for purposes of awarding attorney fees under the
contract.
We affirm the district court.
B. Cross-Appeal
We turn our attention to Spring Crest’s cross-appeal. It argues “[t]he district
court erred in offsetting the amount due [to] Spring Crest based upon Mickle’s
unbilled invoices.” Mickle provided the court with a list of hours Mickle employees
worked on the project between the time Spring Crest had paid its prior invoice and
termination of the contract. Its representative testified that the unbilled labor
amounted to 171 hours of work at a rate of $80 per hour. And section 6.3.1 of the
contract provided that should the contract be terminated then Mickle would be
entitled to an offset for work that it had completed prior to termination for which it
had not yet been paid.
But Spring Crest contends that “the work was never billed because it was
worthless and [Mickle’s representative] knew it.” It highlights testimony from one
of the electricians who finished up the electrical work after Spring Crest terminated
the contract with Mickle. That individual testified that he had to redo some of the
work that was done by Mickle because it was not done correctly. Yet nothing in
the record establishes that the unbilled work was the work that had to be redone.
Regardless, we are bound to affirm the district court if its findings are supported by
substantial evidence. See Metro. Prop. & Cas. Ins. Co., 924 N.W.2d at 839. We
agree with the district court that the terms of the contract dictate that Mickle is 10
entitled to an offset for its labor completed after the work itemized on the last
invoice and prior to termination of the contract. While reasonable minds could
differ on the value of that labor, we conclude the district court’s valuation of the
offset is supported by substantial evidence, so we affirm on the cross-appeal.
AFFIRMED ON APPEAL AND CROSS-APPEAL.