Spring Crest Townhomes WDM v. Mickle Electric & Heating Co.

Court of Appeals of Iowa·Decided July 3, 2024·No. 23-0647·Published

Opinion

IN THE COURT OF APPEALS OF IOWA

No. 23-0647

Filed July 3, 2024

SPRING CREST TOWNHOMES WDM, LLC, Plaintiff-Appellee/Cross-Appellant,

vs.

MICKLE ELECTRIC & HEATING CO., INC. d/b/a MICKLE ELECTRIC & HEATING, LLC, Defendant-Appellant/Cross-Appellee.

Appeal from the Iowa District Court for Dallas County, Charles C. Sinnard, Judge.

A subcontractor appeals a ruling determining that it breached a construction contract. The developer cross-appeals the ruling awarding the subcontractor an offset for unbilled labor. AFFIRMED ON APPEAL AND CROSS-APPEAL.

Billy J. Mallory and Trevor A. Jordison of Mallory Law, West Des Moines, for appellant/cross-appellee.

John F. Fatino and Parker Howe of Whitfield & Eddy, P.L.C., Des Moines, for appellee/cross-appellant.

Heard by Ahlers, P.J., and Chicchelly and Buller, JJ.

AHLERS, Presiding Judge.

After a developer terminated a contract with a subcontractor, the two parties disagree over who breached the contract and is responsible for the additional cost incurred by the developer to hire a new subcontractor to finish the job. I. Background Facts and Prior Proceedings Spring Crest Townhomes WDM, LLC (Spring Crest) contracted with Mickle Electric & Heating, LLC (Mickle) to complete electrical work on three buildings within its townhome development. The contract provided that Mickle had twenty- one days from “the date of commencement” to complete all work. The contract defined the date of commencement as “the date that the Construction Manager notifies the Subcontractor in writing or email when the work is to commence.”

As to the start date, Mickle’s written bid, which was incorporated into the terms of the written contract between the parties, included a note stating, “if you choose to go with us, please let me know as soon as possible. We would like to get material ordered.” Shortly after the contract was signed, representatives from the two companies had a phone conversation wherein Mickle shared it wanted to get to work right away because it had workers waiting for work. Ultimately, Mickle began work within a day or two after the contract was finalized despite not receiving notification in “writing or email” stating that work was to begin. As the contract was signed by Mickle on April 19, 2021, and by Spring Crest on April 20, and Mickle started work on the project within a day or two, the electrical work would have needed to be completed by around May 14 if the twenty-one-day period had begun to run.

The electrical work was not completed by that time. Spring Crest provided Mickle with extensions to complete the work. But on August 3, Spring Crest’s construction manager confronted Mickle in a text message noting no one from Mickle was doing any electrical work on the project. A Mickle employee responded by email, noting that Mickle was behind schedule because the townhomes were not ready for the trim work when its employees went to install it. She then provided Spring Crest with a “loose schedule” for the remaining electrical work. Under that schedule, work on one townhome would be completed on August 12 with the rest of the work on the other townhomes completed by August 31.

But by August 12, work on the first townhome was not completed as provided for in the schedule provided by Mickle’s employee. That was the final straw for Spring Crest. Its attorney sent a letter to Mickle on August 13, informing Mickle that it had until 4:00 p.m. on August 15 to complete all outstanding work. Mickle did not complete the work by August 15. On August 16, Spring Crest sent notice to Mickle that it was terminating their contract for cause. Spring Crest contracted with two other electricians to complete the remaining electrical work on the townhomes.

Spring Crest then brought this action against Mickle to recover the difference between its contracted cost with Mickle and the amount it spent to have the townhomes finished by the different electricians. Mickle responded with a bill to Spring Crest for work it had completed before termination of the contract but had yet to bill. It brought a counterclaim against Spring Crest for payment for those amounts.

The case proceeded to a bench trial. The district court determined that Mickle breached the contract and awarded Spring Crest damages. However, the court offset that award by the amount Mickle was due for work completed prior to Mickle’s termination. The court determined that, under the contract, Spring Crest was the prevailing party entitled to attorney fees.

Mickle appeals, arguing it did not breach the contract and that Spring Crest is not the sole prevailing party entitled to attorney fees. Spring Crest cross- appeals, arguing that the court erred by awarding Mickle an offset for unbilled work. II. Standard of Review “[O]ur review of the district court’s contract interpretation and construction is at law.” Homeland Energy Sols., LLC v. Retterath, 938 N.W.2d 664, 683 (Iowa 2020). “The district court’s factual findings have the effect of a special verdict and are binding on us if supported by substantial evidence.” Metro. Prop. & Cas. Ins. Co. v. Auto-Owners Mut. Ins. Co., 924 N.W.2d 833, 839 (Iowa 2019). “We view the evidence in the light most favorable to the judgment when a party argues the trial court’s ruling is not supported by substantial evidence.” Meincke v. Nw. Bank & Tr. Co., 756 N.W.2d 223, 227 (Iowa 2008). “Evidence is substantial when reasonable minds accept the evidence as adequate to reach a conclusion.” Id. “Evidence is not insubstantial merely because we may draw different conclusions from it; the ultimate question is whether it supports the finding actually made, not whether the evidence would support a different finding.” Id. (citation omitted). III. Discussion Generally, when interpreting a contract, we look to the language used within the four corners of the document. DuTrac Cmty. Credit Union v. Radiology Grp.

Real Est., L.C., 891 N.W.2d 210, 216 (Iowa 2017). “In the construction of written contracts, the cardinal principle is that the intent of the parties must control, and except in cases of ambiguity, this is determined by what the contract itself says.” Id. (citation omitted). When the parties’ intent “is clear and unambiguous from the words of the contract itself, we will enforce the contract as written.” Id. “If the language of the contract is ambiguous, then we engage in interpretation in order to determine ‘the meanings attached by each party at the time the contract was made.’” Id. (citation omitted).

A. Mickle’s Appeal 1. Breach of contract Mickle contends that the district court erred in concluding it breached the contract for three reasons: (1) Spring Crest never sent written notice of commencement, so the twenty-one-day clock never began; (2) it was impossible for Mickle to perform within twenty-one days; and (3) Spring Crest actually breached when it terminated the contract.

We find it unnecessary to resolve Mickle’s claim that the twenty-one-day clock never began to run. This is because the district court appropriately found an independent basis for Spring Crest to terminate the contract. Under section 6.3 of the contract, Spring Crest had the right to terminate the contract if Mickle “at any time and for any reason” failed to perform its work under the contract “in a diligent, efficient, timely, workmanlike, safe and careful manner.”

Free access — add to your briefcase to read the full text and ask questions with AI

Spring Crest Townhomes WDM v. Mickle Electric & Heating Co., (iowactapp 2024).

Spring Crest Townhomes WDM v. Mickle Electric & Heating Co. (Spring Crest Townhomes WDM v. Mickle Electric & Heating Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related