Spring Crest Townhomes WDM v. Mickle Electric & Heating Co.

CourtCourt of Appeals of Iowa
DecidedJuly 3, 2024
Docket23-0647
StatusPublished

This text of Spring Crest Townhomes WDM v. Mickle Electric & Heating Co. (Spring Crest Townhomes WDM v. Mickle Electric & Heating Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Spring Crest Townhomes WDM v. Mickle Electric & Heating Co., (iowactapp 2024).

Opinion

IN THE COURT OF APPEALS OF IOWA

No. 23-0647 Filed July 3, 2024

SPRING CREST TOWNHOMES WDM, LLC, Plaintiff-Appellee/Cross-Appellant,

vs.

MICKLE ELECTRIC & HEATING CO., INC. d/b/a MICKLE ELECTRIC & HEATING, LLC, Defendant-Appellant/Cross-Appellee. ________________________________________________________________

Appeal from the Iowa District Court for Dallas County, Charles C. Sinnard,

Judge.

A subcontractor appeals a ruling determining that it breached a construction

contract. The developer cross-appeals the ruling awarding the subcontractor an

offset for unbilled labor. AFFIRMED ON APPEAL AND CROSS-APPEAL.

Billy J. Mallory and Trevor A. Jordison of Mallory Law, West Des Moines,

for appellant/cross-appellee.

John F. Fatino and Parker Howe of Whitfield & Eddy, P.L.C., Des Moines,

for appellee/cross-appellant.

Heard by Ahlers, P.J., and Chicchelly and Buller, JJ. 2

AHLERS, Presiding Judge.

After a developer terminated a contract with a subcontractor, the two parties

disagree over who breached the contract and is responsible for the additional cost

incurred by the developer to hire a new subcontractor to finish the job.

I. Background Facts and Prior Proceedings

Spring Crest Townhomes WDM, LLC (Spring Crest) contracted with Mickle

Electric & Heating, LLC (Mickle) to complete electrical work on three buildings

within its townhome development. The contract provided that Mickle had twenty-

one days from “the date of commencement” to complete all work. The contract

defined the date of commencement as “the date that the Construction Manager

notifies the Subcontractor in writing or email when the work is to commence.”

As to the start date, Mickle’s written bid, which was incorporated into the

terms of the written contract between the parties, included a note stating, “if you

choose to go with us, please let me know as soon as possible. We would like to

get material ordered.” Shortly after the contract was signed, representatives from

the two companies had a phone conversation wherein Mickle shared it wanted to

get to work right away because it had workers waiting for work. Ultimately, Mickle

began work within a day or two after the contract was finalized despite not receiving

notification in “writing or email” stating that work was to begin. As the contract was

signed by Mickle on April 19, 2021, and by Spring Crest on April 20, and Mickle

started work on the project within a day or two, the electrical work would have

needed to be completed by around May 14 if the twenty-one-day period had begun

to run. 3

The electrical work was not completed by that time. Spring Crest provided

Mickle with extensions to complete the work. But on August 3, Spring Crest’s

construction manager confronted Mickle in a text message noting no one from

Mickle was doing any electrical work on the project. A Mickle employee responded

by email, noting that Mickle was behind schedule because the townhomes were

not ready for the trim work when its employees went to install it. She then provided

Spring Crest with a “loose schedule” for the remaining electrical work. Under that

schedule, work on one townhome would be completed on August 12 with the rest

of the work on the other townhomes completed by August 31.

But by August 12, work on the first townhome was not completed as

provided for in the schedule provided by Mickle’s employee. That was the final

straw for Spring Crest. Its attorney sent a letter to Mickle on August 13, informing

Mickle that it had until 4:00 p.m. on August 15 to complete all outstanding work.

Mickle did not complete the work by August 15. On August 16, Spring Crest sent

notice to Mickle that it was terminating their contract for cause. Spring Crest

contracted with two other electricians to complete the remaining electrical work on

the townhomes.

Spring Crest then brought this action against Mickle to recover the

difference between its contracted cost with Mickle and the amount it spent to have

the townhomes finished by the different electricians. Mickle responded with a bill

to Spring Crest for work it had completed before termination of the contract but

had yet to bill. It brought a counterclaim against Spring Crest for payment for those

amounts. 4

The case proceeded to a bench trial. The district court determined that

Mickle breached the contract and awarded Spring Crest damages. However, the

court offset that award by the amount Mickle was due for work completed prior to

Mickle’s termination. The court determined that, under the contract, Spring Crest

was the prevailing party entitled to attorney fees.

Mickle appeals, arguing it did not breach the contract and that Spring Crest

is not the sole prevailing party entitled to attorney fees. Spring Crest cross-

appeals, arguing that the court erred by awarding Mickle an offset for unbilled work.

II. Standard of Review

“[O]ur review of the district court’s contract interpretation and construction

is at law.” Homeland Energy Sols., LLC v. Retterath, 938 N.W.2d 664, 683 (Iowa

2020). “The district court’s factual findings have the effect of a special verdict and

are binding on us if supported by substantial evidence.” Metro. Prop. & Cas. Ins.

Co. v. Auto-Owners Mut. Ins. Co., 924 N.W.2d 833, 839 (Iowa 2019). “We view

the evidence in the light most favorable to the judgment when a party argues the

trial court’s ruling is not supported by substantial evidence.” Meincke v. Nw. Bank

& Tr. Co., 756 N.W.2d 223, 227 (Iowa 2008). “Evidence is substantial when

reasonable minds accept the evidence as adequate to reach a conclusion.” Id.

“Evidence is not insubstantial merely because we may draw different conclusions

from it; the ultimate question is whether it supports the finding actually made, not

whether the evidence would support a different finding.” Id. (citation omitted).

III. Discussion

Generally, when interpreting a contract, we look to the language used within

the four corners of the document. DuTrac Cmty. Credit Union v. Radiology Grp. 5

Real Est., L.C., 891 N.W.2d 210, 216 (Iowa 2017). “In the construction of written

contracts, the cardinal principle is that the intent of the parties must control, and

except in cases of ambiguity, this is determined by what the contract itself says.”

Id. (citation omitted). When the parties’ intent “is clear and unambiguous from the

words of the contract itself, we will enforce the contract as written.” Id. “If the

language of the contract is ambiguous, then we engage in interpretation in order

to determine ‘the meanings attached by each party at the time the contract was

made.’” Id. (citation omitted).

A. Mickle’s Appeal

1. Breach of contract

Mickle contends that the district court erred in concluding it breached the

contract for three reasons: (1) Spring Crest never sent written notice of

commencement, so the twenty-one-day clock never began; (2) it was impossible

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Spring Crest Townhomes WDM v. Mickle Electric & Heating Co., Counsel Stack Legal Research, https://law.counselstack.com/opinion/spring-crest-townhomes-wdm-v-mickle-electric-heating-co-iowactapp-2024.