Spring Coal Co. v. Quemahoning Coal Co.

115 A. 635, 97 Conn. 116
Supreme Court of Connecticut·Decided December 5, 1921·Published

Opinion

Wheeler, C. J.

The contract whose breach is the subject of the appeal, covered the delivery by defendant between April 1st, 1916, and April 1st, 1917, of a minimum of 30,000 gross tons, in approximately equal monthly proportions, of “C Prime” coal from the Ralphton mines, to the plaintiff at either Port Reading, N. J., St. George, S. I., or Port Richmond, Pa., at a price of $1.65 per ton f. o. b. mine, or $2.90 per ton f. o. b. at these points of destination. The defendant delivered under the contract 17,583 tons, and the plaintiff sues to recover its damages for the failure to deliver the balance contracted for.

The court, found that the defendant had failed to deliver coal as contracted for during the months of September, October, November, January and February, and ascertained the difference between the contract *118 price and the market price under our rule of damages (Sales Act, General Statutes, § 4733), and rendered judgment for $6,615.72.

The trial court refused to include in its judgment damages for the failure to make delivery for the month of March, 1917. Under the contract the defendant was obligated to deliver approximately 2,500 gross tons in March, 1917. The trial court places its refusal to award damages for this breach, upon two grounds: (1) That the contract was abrogated by the parties prior to March 1st. (2) That the plaintiff’s failure to pay for the February shipment gave the defendant the right to refuse to ship coal for March until this payment was made. The first ground is determined by the facts found, unless the motion to correct paragraphs 18, 19 and 20 of the finding should have been granted. The second ground is determined by the construction given to the contract. We will dispose of this ground first.

The plaintiff was obligated to pay for the February shipment on the 20th of the following month of March. When the plaintiff failed to make such payment the defendant had two courses open to it. It might, at its option, have canceled the contract, or, if it was of the opinion that the credit of the plaintiff had become impaired, it had the right to require payments to be made in advance before making further deliveries. This latter provision did not give defendant the right to require all payments past due to be made before it should make further deliveries. It merely gave the defendant the right to refuse to make future deliveries when it should determine, and this meant fairly determine, that plaintiff’s credit had become impaired, until plaintiff should make payment for the same before delivery. Defendant understood this feature of the contract, for it pleaded in its answer that it had availed *119 itself of the right given by the contract and had required payments in advance before making further deliveries, since in its judgment the credit of the plaintiff had become impaired.

The finding does not support in any degree the claim that deliveries in March were not made because defendant had determined that the credit of the plaintiff had become impaired, and had required advance payments before making further deliveries.

In the absence of special provisions of the contract giving defendant the right to refuse future deliveries until past due payments had been made, it had no such right under the law.

The Sales Act is the same in all States whose law might be held to govern this contract. Whether defendant had the right to refuse to proceed further and sue for breach of the entire contract, or, if the breach is severable, for compensation for that but not to treat the whole contract as broken, is made to depend by the terms of the Sales Act (General Statutes, § 4711) “on the terms of the contract and the circumstances of the case. ” Payment for deliveries under the contract were not to be made at the time of delivery, but on the 20th of the succeeding month. The coal was sold on credit, and payment was not made a condition precedent to delivery. In fulfillment of its contract the defendant had no right to wait until the previous months’ deliveries were paid for, before making further delivery. Delivery of the coal and payment were not by the contract made concurrent conditions. This section of the Sales Act conformed to the rule of the existing common law. Mersey Steel & Iron Co. v. Naylor, Benzon & Co., L. R. 9 App. Cas. 434; Welsh v. Michigan Maple Co., 161 Mich. 16, 125 N. W. 692; Campbell & Cameron Co. v. Weisse, 121 Wis. 491, 99 N. W. 340. Under the *120 terms of the contract, defendant could not withhold deliveries in March until deliveries for February had been paid for; and this we hold irrespective of the fact that defendant had been for a long time largely in default on its deliveries. The terms of the contract and the default in deliveries by the defendant, justified the plaintiff in withholding the payment due March 20th in the manner in which it did.

Free access — add to your briefcase to read the full text and ask questions with AI

Spring Coal Co. v. Quemahoning Coal Co., 115 A. 635, 97 Conn. 116 (Colo. 1921).

115 A. 635 (Spring Coal Co. v. Quemahoning Coal Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Welsh v. Michigan Maple Co.
125 N.W. 692 (Michigan Supreme Court, 1910)
Campbell & Cameron Co. v. Weisse
99 N.W. 340 (Wisconsin Supreme Court, 1904)