2024 IL App (1st) 231140-U FOURTH DIVISION Order filed March 14, 2024
No. 1-23-1140 NOTICE: This order was filed under Supreme Court Rule 23 and is not precedent except in the limited circumstances allowed under Rule 23(e)(1). ______________________________________________________________________________ IN THE APPELLATE COURT OF ILLINOIS FIRST DISTRICT ______________________________________________________________________________
MARK SPORCICH, ) Appeal from the ) Circuit Court of Cook Plaintiff-Appellant, ) County. ) v. ) No. 22 CH 3335 ) VILLAGE OF ARLINGTON HEIGHTS, VILLAGE OF ) ARLINGTON HEIGHTS ADMINISTRATIVE ) ADJUDICATION, VILLAGE OF ARLINGTON HEIGHTS ) DEPARTMENT OF BUILDING AND LIFE SAFETY, and ) DANIEL HANLON, ) Honorable ) Clare J. Quish, Defendants-Appellees. ) Judge, presiding.
JUSTICE HOFFMAN delivered the judgment of the court. Justices Martin and Ocasio concurred in the judgment.
ORDER
¶ 1 Held: We affirmed the decision of the circuit court which affirmed a decision of an administrative hearing officer finding a building code violation and imposing a fine where the plaintiff failed to demonstrate that the decision was against the manifest weight of the evidence or that the hearing officer violated his due process rights in the conduct of the hearing. No. 1-23-1140
¶2 The plaintiff, Mark Sporich, acting pro se, appeals from the order of the circuit court
affirming an administrative adjudication of the Village of Arlington Heights (Village) which found
that he violated the Village’s maintenance code by failing to protect the soffits and install gutters on
a house he owned in the Village and assessing a $500 fine. The complaint for administrative
adjudication was filed by the Village’s Department of Building and Life Safety. On appeal, the
plaintiff raises five issues:
“I. Whether the circuit court erred in its order entered on June 26, 2023, by failing to find
that the adjudication hearing officer initially erred in his ruling due to Sporcich's properly
completed permit extension.
II. Whether the circuit court erred in its order entered on June 26, 2023, by failing to find
that the adjudication hearing officer initially erred in his ruling despite Sporcich's continued
compliance with additional requests and burdens imposed by the Village of Arlington
Heights between October 12th, 2021, and March 8th, 2022, despite the existence of a valid
permit and extension.
III. Whether the circuit court erred in its order entered on June 26, 2023, by basing its analysis
and conclusion on errors in the background statements that contradict testimony and
evidence in the record.
IV. Whether the circuit court erred in its order entered on June 26, 2023, by denying Marc
Sporcich's due process rights and right to a fair hearing due to the administrative review
officer's refusal to accept additional evidence and testimony from Sporcich during the
October 12th, 2021 and March 8th, 2022 hearings.
-2- No. 1-23-1140
V. Whether the circuit court erred in its order entered on June 26, 2023, by failing to consider
the allegations of misconduct by village employees involved in the administrative
proceedings, including the Village of Arlington Heights' Department of Building and Life
Safety and the adjudication hearing officer, Daniel Hanlon. The alleged misconduct, such as
bias, procedural improprieties, and failure to adhere to legal standards, directly impacted the
fairness and integrity of the administrative process.”
¶3 Although the Plaintiff addresses his arguments to the decision of the circuit court, when
reviewing an order of the circuit court on administrative review, we review the decision of the
administrative agency not the circuit court. Provena Covenant Medical Center v. Department of
Revenue, 236 Ill. 2d 368, 386 (2010). As a consequence, the plaintiff’s arguments can be
summarized as two basic contentions: (1) the findings of the hearing officer were against the
manifest weight of the evidence and (2) the hearing officer violated the plaintiff's due process rights
by limiting his arguments and failing to consider relevant evidence. For the reasons that follow, we
affirm the decision of the circuit court.
¶4 On September 8, 2021, a building inspector for the Village sent a letter to the plaintiff stating
that the house he owned on Haddow Avenue was in violation of the Village’s maintenance
ordinances sections 26-101 (304.2) and 26-101 (304.7). See Village of Arlington Heights Municipal
Code (Code) § 26-101 (revised March 1, 2020) (adopting the 2018 Edition of the International
Property Maintenance Code); see also 2018 International Property Maintenance Code §§ 304.2
(protective treatment), 304.7 (roofs and drainage). According to the letter, the plaintiff’s house was
inspected and found to be lacking protective covering for the fascia and soffits and missing gutters
and downspouts. The letter continued stating:
-3- No. 1-23-1140
“Please be aware that failure to comply by September 20, 2021 will result in the Village
pursuing a legal remedy. Please be advised that permit # 19-65 has expired. No
correspondence has been received regarding the permit extension since May 2021. As a
result, permit # 19-65 will be closed.”
On September 22, 2021, the Village filed a complaint against the plaintiff alleging the same
violations.
¶5 On October 12, 2021, an administrative hearing officer conducted a hearing on the Village’s
complaint. The transcript of the initial portion of that hearing is missing from the record. The
plaintiff submitted a supplement to the record, acknowledging that a portion of the record was
missing and supplementing the record with a bystander’s report for the missing portion. The circuit
court granted the plaintiff’s motion to supplement the record with the agreement of the parties.
¶6 According to the supplemental record, the plaintiff’s original architect and general contractor
stopped work on a remodeling project at the subject building. It took several months to terminate
the construction contract. The plaintiff admitted that “there are numerous potential violations if one
does not take into account that [sic] the obvious fact that the property is a construction site.” The
plaintiff testified that he had been told multiple times that the building permit for the site was active.
¶7 According to the transcript, the plaintiff stated that he had some email communications from
the Village. The hearing officer asked “Does one of them say you have a permit extension?” The
plaintiff responded “I don’t believe it’s that cut and clear.” The plaintiff testified that he was told
that the Village was waiting for revised plans. However, when asked if he provided the plans, the
plaintiff responded, “They didn’t give me a deadline on the revised plans.” The plaintiff further
added that the remodeling project began in May 2019, but was never completed and that he was
-4- No. 1-23-1140
suing the original contractor. The hearing officer noted that photographs provided by the Village
showed a house wrapped in Tyvek with exposed fascia and soffits. The plaintiff agreed that the
fascia was exposed but added that it needed to be removed because the builder did not apply it
properly.
¶8 Michael Boyle, the Village’s permits supervisor, stated that he received the plaintiff’s permit
extension request on May 14, 2021. Boyle did not process the permit extension because he was
Free access — add to your briefcase to read the full text and ask questions with AI
2024 IL App (1st) 231140-U FOURTH DIVISION Order filed March 14, 2024
No. 1-23-1140 NOTICE: This order was filed under Supreme Court Rule 23 and is not precedent except in the limited circumstances allowed under Rule 23(e)(1). ______________________________________________________________________________ IN THE APPELLATE COURT OF ILLINOIS FIRST DISTRICT ______________________________________________________________________________
MARK SPORCICH, ) Appeal from the ) Circuit Court of Cook Plaintiff-Appellant, ) County. ) v. ) No. 22 CH 3335 ) VILLAGE OF ARLINGTON HEIGHTS, VILLAGE OF ) ARLINGTON HEIGHTS ADMINISTRATIVE ) ADJUDICATION, VILLAGE OF ARLINGTON HEIGHTS ) DEPARTMENT OF BUILDING AND LIFE SAFETY, and ) DANIEL HANLON, ) Honorable ) Clare J. Quish, Defendants-Appellees. ) Judge, presiding.
JUSTICE HOFFMAN delivered the judgment of the court. Justices Martin and Ocasio concurred in the judgment.
ORDER
¶ 1 Held: We affirmed the decision of the circuit court which affirmed a decision of an administrative hearing officer finding a building code violation and imposing a fine where the plaintiff failed to demonstrate that the decision was against the manifest weight of the evidence or that the hearing officer violated his due process rights in the conduct of the hearing. No. 1-23-1140
¶2 The plaintiff, Mark Sporich, acting pro se, appeals from the order of the circuit court
affirming an administrative adjudication of the Village of Arlington Heights (Village) which found
that he violated the Village’s maintenance code by failing to protect the soffits and install gutters on
a house he owned in the Village and assessing a $500 fine. The complaint for administrative
adjudication was filed by the Village’s Department of Building and Life Safety. On appeal, the
plaintiff raises five issues:
“I. Whether the circuit court erred in its order entered on June 26, 2023, by failing to find
that the adjudication hearing officer initially erred in his ruling due to Sporcich's properly
completed permit extension.
II. Whether the circuit court erred in its order entered on June 26, 2023, by failing to find
that the adjudication hearing officer initially erred in his ruling despite Sporcich's continued
compliance with additional requests and burdens imposed by the Village of Arlington
Heights between October 12th, 2021, and March 8th, 2022, despite the existence of a valid
permit and extension.
III. Whether the circuit court erred in its order entered on June 26, 2023, by basing its analysis
and conclusion on errors in the background statements that contradict testimony and
evidence in the record.
IV. Whether the circuit court erred in its order entered on June 26, 2023, by denying Marc
Sporcich's due process rights and right to a fair hearing due to the administrative review
officer's refusal to accept additional evidence and testimony from Sporcich during the
October 12th, 2021 and March 8th, 2022 hearings.
-2- No. 1-23-1140
V. Whether the circuit court erred in its order entered on June 26, 2023, by failing to consider
the allegations of misconduct by village employees involved in the administrative
proceedings, including the Village of Arlington Heights' Department of Building and Life
Safety and the adjudication hearing officer, Daniel Hanlon. The alleged misconduct, such as
bias, procedural improprieties, and failure to adhere to legal standards, directly impacted the
fairness and integrity of the administrative process.”
¶3 Although the Plaintiff addresses his arguments to the decision of the circuit court, when
reviewing an order of the circuit court on administrative review, we review the decision of the
administrative agency not the circuit court. Provena Covenant Medical Center v. Department of
Revenue, 236 Ill. 2d 368, 386 (2010). As a consequence, the plaintiff’s arguments can be
summarized as two basic contentions: (1) the findings of the hearing officer were against the
manifest weight of the evidence and (2) the hearing officer violated the plaintiff's due process rights
by limiting his arguments and failing to consider relevant evidence. For the reasons that follow, we
affirm the decision of the circuit court.
¶4 On September 8, 2021, a building inspector for the Village sent a letter to the plaintiff stating
that the house he owned on Haddow Avenue was in violation of the Village’s maintenance
ordinances sections 26-101 (304.2) and 26-101 (304.7). See Village of Arlington Heights Municipal
Code (Code) § 26-101 (revised March 1, 2020) (adopting the 2018 Edition of the International
Property Maintenance Code); see also 2018 International Property Maintenance Code §§ 304.2
(protective treatment), 304.7 (roofs and drainage). According to the letter, the plaintiff’s house was
inspected and found to be lacking protective covering for the fascia and soffits and missing gutters
and downspouts. The letter continued stating:
-3- No. 1-23-1140
“Please be aware that failure to comply by September 20, 2021 will result in the Village
pursuing a legal remedy. Please be advised that permit # 19-65 has expired. No
correspondence has been received regarding the permit extension since May 2021. As a
result, permit # 19-65 will be closed.”
On September 22, 2021, the Village filed a complaint against the plaintiff alleging the same
violations.
¶5 On October 12, 2021, an administrative hearing officer conducted a hearing on the Village’s
complaint. The transcript of the initial portion of that hearing is missing from the record. The
plaintiff submitted a supplement to the record, acknowledging that a portion of the record was
missing and supplementing the record with a bystander’s report for the missing portion. The circuit
court granted the plaintiff’s motion to supplement the record with the agreement of the parties.
¶6 According to the supplemental record, the plaintiff’s original architect and general contractor
stopped work on a remodeling project at the subject building. It took several months to terminate
the construction contract. The plaintiff admitted that “there are numerous potential violations if one
does not take into account that [sic] the obvious fact that the property is a construction site.” The
plaintiff testified that he had been told multiple times that the building permit for the site was active.
¶7 According to the transcript, the plaintiff stated that he had some email communications from
the Village. The hearing officer asked “Does one of them say you have a permit extension?” The
plaintiff responded “I don’t believe it’s that cut and clear.” The plaintiff testified that he was told
that the Village was waiting for revised plans. However, when asked if he provided the plans, the
plaintiff responded, “They didn’t give me a deadline on the revised plans.” The plaintiff further
added that the remodeling project began in May 2019, but was never completed and that he was
-4- No. 1-23-1140
suing the original contractor. The hearing officer noted that photographs provided by the Village
showed a house wrapped in Tyvek with exposed fascia and soffits. The plaintiff agreed that the
fascia was exposed but added that it needed to be removed because the builder did not apply it
properly.
¶8 Michael Boyle, the Village’s permits supervisor, stated that he received the plaintiff’s permit
extension request on May 14, 2021. Boyle did not process the permit extension because he was
anticipating updated plans. Boyle added that he spoke to the plaintiff on the phone and told him that
he was going to hold processing of the extension request until the Village received the plaintiff's
plans.
¶9 The plaintiff argued that he was making progress on completing the construction and stated
that he had his plans revised and they were “ready to be submitted.” The hearing officer clarified
asking, “But you haven’t submitted those yet”; and the plaintiff responded, “No. I could do that if
necessary.”
¶ 10 When called to testify, Jorge Torres, the Village’s building inspector, stated:
“They would recommend – I would recommend – if we give them a one-month
extension for full submittal of the building plans, approves submittal of the building plans,
drawings. We’ve been waiting since May of this year. If them – if they submit plans and –
and they’re approved by the building department, then we could – we could remove the fine
that we – I’d recommend imposing today.”
¶ 11 Following the hearing, the hearing officer entered an order assessing a $750 fine against the
plaintiff and continuing the matter until November 9, 2021, for submission of approved plans and a
motion to vacate the fine, stating:
-5- No. 1-23-1140
“Well, I’m gonna enter a finding·of liable today.·I am gonna take the Village’s suggestion
though to make that plan subject to a·motion to vacate.·So basically, as long as you and the
Village aren’t proceeding forward to an end and the Village says yes, they’ve done what·we
need them to do, I will come to you in the next month in November assuming those -- the
plans have been submitted, approved, we will talk about whether I vacate the fine.”
¶ 12 On November 9, 2021, an unidentified Village employee testified that the plaintiff’s plans
had been submitted but not approved, and he requested additional time for Village review. The
hearing officer continued the matter until January 11, 2022.
¶ 13 On January 11, 2022, Torres testified that the plaintiff’s plans had not been approved. The
plaintiff stated that he was waiting for a response from the Village. The case was passed so that
Torres and the plaintiff could discuss the matter. When the case was recalled, Torres stated that there
were some plan revisions being requested, and the hearing officer continued the case to March 8,
2022.
¶ 14 On March 8, 2022, Torres testified that the plaintiff’s property was “not in compliance yet.”
The plaintiff responded that the revised plans were with his architect and that he should have plans
drawn up “by next week probably.” After further discussion, the plaintiff stated that he had received
some comments from the plan reviewer and sent them to his architect. The plaintiff added “I can
show you the emails I have.” The hearing officer responded “No, I trust what you say.” The plaintiff
argued that the delay in the construction project was attributable to the Village’s refusal to perform
a framing inspection. Torres responded that the Village enforcement officers were not home
inspectors and would not inspect the framing until mechanical and plumbing had been installed.
¶ 15 Near the end of the hearing the following colloquy occurred:
-6- No. 1-23-1140
“THE COURT: We’ve argued this
MARK SPORCICH: -- they haven’t
THE COURT: We’ve argued this back -- you’ve argued this back and forth multiple times
and you’re gonna keep repeating yourself and everybody in this room is gonna have to sit
there and listen to you repeat yourself to me. I understand your argument.·I do I get it.
Go·ahead.
MARK SPORCICH: Yeah. I -- I called yesterday and talked to George and asked him if we
could defer this one month because it had plans, and for some reason he wanted to drag me
in here again It feels like harassment.
THE COURT: I’m granting motion to vacate in part and denying in part.”
¶ 16 Ultimately, the hearing officer granted the motion to vacate in part, treating it as a motion to
reduce the fine. The hearing officer imposed a $500 fine for the failure to provide gutters and soffit
protection.
¶ 17 On April 12, 2022, the plaintiff filed a complaint in the circuit court for administrative review
of the hearing officer’s decision. After considering the parties’ briefs and arguments, the circuit court
affirmed the decision of the hearing officer finding the plaintiff liable for two building code
violations and imposing a $500 fine. This appeal followed.
¶ 18 We first address the question of whether the administrative adjudication and resulting fine
are against the manifest weight of the evidence. The hearing officer did not make written findings
of fact, but implicit in his order are two factual findings: (1) the building did not have gutters or
soffit protection at the time of the inspection, and (2) the plaintiff did not have a valid extension of
his building permit.
-7- No. 1-23-1140
¶ 19 The plaintiff’s challenge to the sufficiency of the evidence supporting the administrative
adjudication appears to be based on the argument that he had a valid extension of his permit and that
Boyle’s testimony to the contrary was inconsistent. We find no merit to the argument.
¶ 20 Division 31.1 of article 11 of the Illinois Municipal Code (65 ILCS 5/art. 11 div. 31.1 (West
2022)) provides a mechanism for enforcement of building code violations. Section 11-31.1-11 of
the Code adopts the Administrative Review Law (735 ILCS 5/3-101 et seq. (West 2022)) as the
method of review for decisions by a hearing officer in building code enforcement proceedings.
¶ 21 Section 3-110 of the Administrative Review Law provides that: “The findings and
conclusions of the administrative agency on questions of fact shall be held to be prima facie true and
correct.” 735 ILCS 5/3-110 (West 2022). On administrative review, courts will not reweigh the
evidence or substitute their judgment for that of the agency. Miller v. Board of Trustees of Oak Lawn
Police Pension Fund, 2019 IL App (1st) 172967, ¶ 52. Findings of fact will be reversed only if they
are against the manifest weight of the evidence. Beggs v. Board of Education of Murphysboro
Community Unit School District No. 186, 2016 IL 120236, ¶ 50
¶ 22 We turn first to the question of whether the plaintiff’s building had gutters and soffit
protection as required by the Village’s Code. Photographic evidence contained in the record clearly
shows that the plaintiff’s building lacked gutters and had unfinished fascia and soffits. Further the
Village’s building inspector testified that the building lacked gutters and soffits and was not in
compliance. Torres testified that, as of March 8, 2022, the property was still not in compliance. The
plaintiff does not argue that there were gutters or protected soffits in place on the date of the alleged
violation. Therefore, we cannot conclude that the hearing officer’s implicit findings that the building
lacked gutters and that the soffits were unprotected were against the manifest weight of the evidence.
-8- No. 1-23-1140
¶ 23 As to the issue of whether the plaintiff had a building permit in effect at the time of the
alleged violation, the hearing officer heard testimony that the plaintiff had only submitted a request
for a permit extension prior to the violation. The hearing officer also heard evidence that the permit
extension was on hold while the Village waited for revised plans. The plaintiff points to an email
which stated that Michael Boyle, the Village’s permit supervisor, would “process” the extension
application. However, the plaintiff has identified nothing in the record which would indicate that the
application was ever approved, or the extension granted. Further, at the hearing on October 12, 2021,
the plaintiff admitted he had not yet submitted the revised plans necessary for an extension. At the
March 8, 2022, hearing, the plaintiff admitted that the latest revised plans had not been submitted
but were still with his architect. The record in this case is clear that at no time relevant did the
plaintiff have a valid permit.
¶ 24 Furthermore, as defendants argue, the Village’s ordinances contain no exception to the
maintenance requirements for a building which is the subject of a valid building permit. We have
reviewed the Village’s ordinances and find no such exception, nor has the plaintiff cited any
authority for the proposition that his compliance with the maintenance ordinances would be excused
if his building permit was valid.
¶ 25 Based on the record before us, we cannot conclude that the hearing officer’s implicit finding
that the plaintiff’s building was in violation of section 26-101 of the Village Code was against the
manifest weight of the evidence.
¶ 26 The plaintiff also contends that the hearing officer violated his due process rights in the
manner in which he conducted the hearings. The plaintiff argues generally that there was misconduct
and bias demonstrated by the hearing officer and Village employees. However, the plaintiff only
-9- No. 1-23-1140
identifies two specific instances where the hearing officer is alleged to have violated his due process
rights
¶ 27 First, the plaintiff argues that the hearing officer deprived him of the right to present evidence
by stating “I trust what you say” when the plaintiff offered to present emails from his architect. The
plaintiff argues that “the emails that [he] was not permitted to produce would have provided material
proof to both courts to question the credibility of witnesses and change the outcome.” We find no
support for this contention in the record. The hearing officer’s comment only related to the limited
question of whether the plaintiff had contacted his architect, and the hearing officer simply stated
that he would accept the plaintiff’s assertion without documentary evidence.
¶ 28 Due process is a flexible concept and the procedures employed by an administrative agency
need only include such procedural protections as fundamental principles of justice and the particular
situation demands. M.F. Booker v. Board of Education of City of Chicago, 2016 IL App (1st)
151151, ¶ 57 (citing Abrahamson v. Illinois Department of Professional Regulation, 153 Ill. 2d 76,
92 (1992)). The procedures employed need not mimic a judicial proceeding, but on administrative
review a reviewing court has a duty to ensure that a fair and impartial procedure was used. Id.
Nothing the plaintiff said suggested that he intended to introduce additional emails or that those
emails would be somehow relevant to the core issues in this case, i.e., whether there were gutters
and soffits on the house and whether the plaintiff had made sufficient progress toward rectifying the
violation to excuse the imposition of a fine. Therefore, we cannot conclude that the hearing officer’s
comment deprived the plaintiff of due process.
¶ 29 The plaintiff also argues that the hearing officer violated his due process rights during the
hearing on his motion to vacate the fine when this exchange occurred:
- 10 - No. 1-23-1140
THE COURT: We’ve argued this back -- you’ve argued this back and forth multiple times
and you’re gonna keep repeating yourself and everybody in this room is gonna have to sit
there and listen to you repeat yourself to me. I understand your argument.· I do I get it.
Go·ahead.”
¶ 30 After reviewing the record as a whole, we find no due process violation in the hearing
officer’s remarks. The plaintiff was indeed repeating arguments he had made earlier. The hearing
officer was under no obligation to allow him to continue. The plaintiff has cited no authority for the
proposition that litigants have an unfettered right to present repetitive arguments. Due process
demands only a meaningful opportunity to be heard, not the right to be heard in whatever manner a
litigant wishes. See Trettenero v. Police Pension Fund of City of Aurora, 333 Ill. App. 3d 792, 799
(2002). Nor do we find any generalized due process violation after examining the record as a whole.
Accordingly, we reject the plaintiff’s due process arguments.
¶ 31 Based on the foregoing analysis, we conclude that the hearing officer’s finding that the
plaintiff’s building lacked gutters and soffit protection was not against the manifest weight of the
evidence. We further conclude that the hearing officer did not violate the plaintiff's due process
rights by limiting his ability to argue his case. We, therefore, affirm the order of the circuit court
which affirmed the administrative adjudication of the Village’s finding that the plaintiff violated the
Village’s Code by failing to protect the soffits and install gutters on a house he owned and assessing
a $500 fine.
¶ 32 Affirmed.
- 11 -