Spooner Construction & Tree Service, Inc. v. Maner

2003 MT 43, 66 P.3d 263, 314 Mont. 268, 2003 Mont. LEXIS 41
CourtMontana Supreme Court
DecidedMarch 11, 2003
Docket01-574
StatusPublished
Cited by4 cases

This text of 2003 MT 43 (Spooner Construction & Tree Service, Inc. v. Maner) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Spooner Construction & Tree Service, Inc. v. Maner, 2003 MT 43, 66 P.3d 263, 314 Mont. 268, 2003 Mont. LEXIS 41 (Mo. 2003).

Opinion

JUSTICE TRIEWEILER

delivered the Opinion of the Court.

¶1 We previously reviewed this matter in Spooner Const. & Tree Service v. Maner, 2000 MT 161, 300 Mont. 268, 3 P.3d 641 (Spooner 1). In Spooner I, we concluded that the District Court for the Fourth Judicial District in Missoula County erred when it granted the Respondent, Ernie Maner, summary judgment and awarded damages for supervisory work and wrongful attachment. The judgment of the District Court was affirmed in part, reversed in part, and the matter was remanded for further proceedings. A hearing was conducted to resolve the issues remanded. The District Court concluded that the Appellant, Spooner Construction & Tree Service, Inc., wrongfully attached Maner’s property and awarded attorney’s fees and consequential damages, and concluded there was insufficient evidence to prove damages for supervisory work. Spooner appeals the District Court’s award of damages for wrongful attachment. We affirm the judgment of the District Court.

¶2 We restate the issues as follows:

¶3 1. Did the District Court err when it denied Spooner’s motion to dismiss?

¶4 2. Was the District Court clearly erroneous when it found that Spooner wrongfully and maliciously attached Maner’s skidder?

¶5 3. Does a supersedeas bond remain in effect when the case is remanded to the district court following a successful appeal?

FACTUAL AND PROCEDURAL BACKGROUND

¶6 The following facts are taken, in part, from our prior decision in Spooner I and, in part, from the hearings conducted by the District Court following our remand for further proceedings.

¶7 In the fall of 1995, Spooner Construction & Tree Service, Inc., through its president James Spooner, entered into an oral agreement with Ernie Maner to harvest timber pursuant to Maner’s Big Cat timber contract with Plum Creek. Spooner and Maner both agreed to provide fifty percent of the labor and equipment for the harvest in exchange for an equal share of the profits.

¶8 During the timber harvest, Maner’s skidder broke down and it was taken to Spooner’s shop for repairs. Maner continued to harvest timber using Spooner’s 1450B Case Crawler. Meanwhile, the necessary *271 parts were ordered and the skidder was repaired. However, by the time the repairs were complete, winter had arrived and Maner was forced to cease work until spring. Spooner contends that its mechanic repaired the skidder while Maner maintains he made the repairs himself.

¶9 Maner made payments to Spooner for hauling timber harvested pursuant to the Plum Creek agreement in October and December of 1995. On February 6, 1996, Spooner filed a mechanic’s lien against Maner’s skidder, trailer, and bus for repair work allegedly performed on the skidder and for shop rental. Spooner claimed Maner could not be located for personal service and, therefore, notice of the lien and sheriffs sale was published in the newspaper. Spooner intended to purchase the skidder at the sale.

¶10 Robert Skiles, one of Maner’s business associates, brought the lien and sheriffs sale to Maner’s attention after seeing the notice in the paper. On March 15,1996, Maner filed a complaint injustice court to stop the sheriffs sale, to regain possession of his personal property, and to obtain payment for work he had performed for Spooner based on a separate agreement (the September contract).

¶11 On the same date, Spooner filed a complaint in district court in which it alleged that it was entitled to compensation for work performed pursuant to the Plum Creek agreement, for the use of the Crawler, and for repairs performed on Maner’s skidder. Ancillary to the complaint, Spooner requested a writ of prejudgment attachment of Maner’s skidder, trailer, and bus which were at Spooner’s shop. The writ was issued by the District Court that day.

¶12 On May 7, 1996, Maner filed an answer and counterclaim to Spooner’s complaint. He alleged that Spooner breached the Plum Creek agreement, failed to pay him for skidding and supervisory work done pursuant to the September contract, and wrongfully attached his personal property.

¶13 On May 13, 1996, Spooner agreed to dismiss the prejudgment attachment issued by the District Court. Spooner recognized that Maner would be damaged if deprived of the use of his equipment, however, it admitted no wrongdoing. The District Court discharged the writ of prejudgment attachment two days later.

¶14 Maner served Spooner with interrogatories, requests for admission, and requests for the production of documents on December 16,1996. Spooner was requested to admit that: (1) Maner was entitled to damages for skidding pursuant to the September contract; (2) Spooner was entitled to damages for the supervisory work he *272 performed pursuant to the September contract; (3) Maner obtained a writ of prejudgment attachment maliciously and without probable cause; (4) Spooner had received all of the money he was entitled to pursuant to the Plum Creek agreement; and (5) Spooner was not entitled to any money from Maner for the use of its Crawler. Spooner did not respond and the requests were deemed admitted.

¶15 Maner moved for partial summary judgment on Spooner’s claim for damages arising from the Plum Creek agreement, Maner’s use of the Crawler, and punitive damages. Maner also sought partial summary judgment on his claim that he was entitled to money for skidding and sawing timber, and for the supervisory work he performed pursuant to the September agreement. A hearing was held on May 28,1997, at which time Spooner filed a motion for leave to file discovery responses. Spooner’s motion was denied and partial summary judgment was awarded to Maner. As the basis for its judgment, the District Court amended admission number two, sua sponte, to state that Maner rather than “Spooner” was entitled to damages for supervisory work.

¶16 On March 31,1998, Maner filed for partial summary judgment on his claim of wrongful attachment, his claim for breach of the Plum Creek agreement, and Spooner’s claim for damages related to repair work performed on the skidder. The District Court held a hearing on May 29,1998, after which it awarded Maner summary judgment on all issues. As the basis for that award, the District Court amended admission number three, sua sponte, to state that Spooner rather than “Maner” maliciously attached Maner’s skidder.

¶17 On February 16, 1999, the District Court conducted a non-jury trial on the issue of damages. The District Court entered its Findings of Fact, Conclusions of Law, and Judgment and Order on April 2,1999, which awarded Maner $82,600 for consequential damages plus attorney’s fees and costs for the wrongful attachment claim.

¶18 Spooner posted a supersedeas bond and appealed the judgment of the District Court. We concluded that the District Court abused its discretion when it denied Spooner the opportunity to respond to the amended requests for admission. It was further held that the District Court erred when it awarded summary judgment in favor of Maner based on the facts deemed admitted in response to requests two and three.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Board of Education v. Beka Industries, Inc.
989 A.2d 1181 (Court of Special Appeals of Maryland, 2010)
State v. Jones
2006 MT 209 (Montana Supreme Court, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
2003 MT 43, 66 P.3d 263, 314 Mont. 268, 2003 Mont. LEXIS 41, Counsel Stack Legal Research, https://law.counselstack.com/opinion/spooner-construction-tree-service-inc-v-maner-mont-2003.