Spire STL Pipeline LLC v. 3.31 Acres of Land, More or Less, Situated in St. Charles County, State of Missouri

District Court, E.D. Missouri·Decided November 23, 2021·No. 4:18-cv-01327·Unknown

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF MISSOURI EASTERN DIVISION

SPIRE STL PIPELINE LLC, ) ) Plaintiff, ) ) v. ) Consolidated Action ) No. 4:18 CV 1327 DDN 3.31 ACRES OF LAND, et al., ) ) Defendants. ) )

MEMORANDUM AND ORDER This matter is before the Court on several motions: (a) defendant landowners’ second motion to dismiss case for lack of jurisdiction (Doc. 679) and motion for ruling on second motion to dismiss (Doc. 685); (b) plaintiff Spire STL Pipeline LLC’s motions for entry of final order and judgment (Docs. 676, 680, 681); (c) defendants Virginia Schaeffer and the Schaeffer Trust’s motion to alter judgment (Doc. 683); and (d) plaintiff’s motion to clarify order for alternative dispute resolution (Doc. 693).

MOTION TO DISMISS Defendants renew their motion to dismiss the condemnation action and dissolve the injunction based on the United States Court of Appeals for the D.C. Circuit’s issuance of its mandate on October 8, 2021. (Doc. 679.) They argue that the vacatur of the original Federal Energy Regulatory Commission (FERC) certificate deprives the Court of subject matter jurisdiction over plaintiff’s condemnation complaint. On September 14, 2021, before the D.C. Circuit issued its mandate, FERC issued a “temporary certificate of public convenience and necessity” pursuant to 15 U.S.C. § 717(c)(1)(B). (Doc. 667-1.) The temporary certificate allows plaintiff to continue to operate the facilities “currently in service, under the terms, conditions, and authorizations previously issued.” (Doc. 667-1 at 5.) The Natural Gas Act provides: When any holder of a certificate of public convenience and necessity cannot acquire by contract, or is unable to agree with the owner of property to the compensation to be paid for, the necessary right-of-way to construct, operate, and maintain a pipe line or pipe lines for the transportation of natural gas, and the necessary land or other property, in addition to right-of- way, for the location of compressor stations, pressure apparatus, or other stations or equipment necessary to the proper operation of such pipe line or pipe lines, it may acquire the same by the exercise of the right of eminent domain in the district court of the United States for the district in which such property may be located, or in the State courts.

15 U.S.C. § 717f(h). Through its original certificate issued by FERC in 2018 and its current temporary certificate, plaintiff has continuously held a certificate of public convenience and necessity. The Natural Gas Act permits any holder of such a certificate to exercise the right of eminent domain. Therefore, the Court denies defendants’ motion to dismiss.

MOTION TO ALTER JUDGMENT Defendants Virginia Schaeffer and the Schaeffer Trust move under Federal Rule of Civil Procedure 59(e) to amend or alter the Court’s order regarding their objections to the Commission’s Report. (Doc. 666.) They renew their arguments that the signatures of all five commissioners is clear error; that the Court erred in excluding evidence; and that the Court should have put the hearing on hold. (Id.) “Motions under Rule 59(e) serve the limited function of correcting manifest errors of law or fact or to present newly discovered evidence.” Continental Indemnity Co. v. IPFS of New York, LLC, 7 F.4th 713, 717 (8th Cir. 2021) (quoting Ryan v. Ryan, 889 F.3d 499, 507-08 (8th Cir. 2018)). “District courts have broad discretion in determining whether to alter or amend judgment.” Id. Defendants object to the signatures of all five Commissioners on the report. As the Court discussed in its memorandum and order adopting the Commissioner’s Report, the decision of the Commissioners was unanimous, and there is no indication that the alternate Commissioners influenced the Commissioners’ findings. (Doc. 666 at 3.) The signatures of the two alternate Commissioners on the report do not constitute manifest error. Defendants argue that the Court erred in excluding Mr. Berning’s compaction tests and the topsoil report. “If a party fails to provide information or identify a witness as required by Rule 26(a) or (e), the party is not allowed to use that information or witness to supply evidence on a motion, at a hearing, or at a trial, unless the failure was substantially justified or harmless.” Fed. R. Civ. P. 37(c)(1). Defendants did not produce Mr. Berning’s compaction testing until six weeks before the evidentiary hearing; the Court finds it unlikely that wet conditions precluded Mr. Berning from conducting the tests until May 2021. Additionally, requiring plaintiff to conduct its own compaction testing so close to the hearing would not have been harmless. The Court excluded the compaction tests because defendants failed to offer a justification for the late disclosure of Mr. Berning’s compaction testing, and the timing was not harmless to defendants. The exclusion of the compaction tests is not manifest error. The exclusion of evidence is within the discretion of the court. Walker v. Kane, 885 F.3d 535, 538 (8th Cir. 2018). The Court found that the components of the topsoil report, Exhibit D-14, were not verifiable. Additionally, defendants’ expert, Mr. Berning, calculated a different volume of topsoil than was indicated in Exhibit D-14. (Doc. 655 at 77-78.) Defendants failed to bear their burden of proving the admissibility of the topsoil report. The exclusion of the topsoil report is not manifest error. Lastly, defendants argue that the Court erred in permitting the hearing to go forward after the D.C. Circuit’s opinion vacating the FERC certificate, as well as in not informing the Commissioners that the certificate was vacated. “Until the mandate issues, an appellate judgment is not final; the decision reached in the opinion may be revised by the panel, or reconsidered by the en banc court, or certiorari may be granted by the Supreme Court.” Flagship Marine Servs., Inc. v. Belcher Towing Co., 23 F.3d 341, 342 (11th Cir. 1994). The D.C. Circuit’s decision vacating the original certificate was not final until the court issued its mandate on October 8, 2021. Additionally, informing the Commissioners of the D.C. Circuit’s decision had the potential to confuse the issues at the hearing. The purpose of the hearing was to present evidence to the Commissioners to assist them in determining just compensation for the property taken by plaintiff, not to determine the validity of the certificate. The decision to move forward with the evidentiary hearing and not to inform the Commissioners regarding the D.C. Circuit’s decision is not manifest error. Because the Court finds no manifest error of law or fact in its decision, and defendants do not present any newly discovered evidence, the Court will not alter or amend its order overruling defendants’ objections and adopting the Commissioners’ Report with respect to the Schaeffer tract.

Free access — add to your briefcase to read the full text and ask questions with AI

Spire STL Pipeline LLC v. 3.31 Acres of Land, More or Less, Situated in St. Charles County, State of Missouri, (E.D. Mo. 2021).

Spire STL Pipeline LLC v. 3.31 Acres of Land, More or Less, Situated in St. Charles County, State of Missouri (Spire STL Pipeline LLC v. 3.31 Acres of Land, More or Less, Situated in St. Charles County, State of Missouri) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Maurice Walker v. Dale White
885 F.3d 535 (Eighth Circuit, 2018)
Stacy Ryan v. Constance Ryan
889 F.3d 499 (Eighth Circuit, 2018)
Continental Indemnity Company v. IPFS of New York
7 F.4th 713 (Eighth Circuit, 2021)