Sperow v. Carter

8 Pa. D. & C.2d 635, 1956 Pa. Dist. & Cnty. Dec. LEXIS 381
CourtPennsylvania Court of Common Pleas, Cumberland County
DecidedAugust 30, 1956
Docketno. 40
StatusPublished

This text of 8 Pa. D. & C.2d 635 (Sperow v. Carter) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Cumberland County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sperow v. Carter, 8 Pa. D. & C.2d 635, 1956 Pa. Dist. & Cnty. Dec. LEXIS 381 (Pa. Super. Ct. 1956).

Opinion

Jacobs, J.,

The above case was tried before a jury and the writer of this opinion during the week of common pleas trials beginning February 13, 1956. The trial resulted in a verdict for defendant. A motion for a new trial was filed by plaintiff and the motion was argued before this court en banc on June 19, 1956.

In plaintiff’s motion for a new trial she assigns six reasons why the new trial should be granted. The first four reasons are the catch-all reasons usually given in asking for a new trial, namely: That the verdict was against the law, against the evidence, against the weight of the evidence and against the charge of the court. In her argument, plaintiff mentions only one of these objections, namely: That the verdict was against the weight of the evidence, and does not offer any argument in support of the other three reasons heretofore listed. The court will, therefore, treat this as the only problem raised by plaintiff in her first four listed reasons. The fifth reason assigned by plaintiff is that the trial judge erred in refusing to permit Ralph R. Baughman to testify as an expert witness. As her sixth reason plaintiff claims that the trial judge erred in refusing to permit J. E. Sacriste to testify as an expert witness and give his opinion as to the cause of the fire involved in the matter on trial.

Plaintiff owned a house at 100 South Second Street, Wormleysburg, Cumberland County, on November 16, [637]*6371954. A fire occurred on that date causing $3,541.49 damage to plaintiff's house. On the date of the fire the house was rented to Thomas H. Mumma. At about 7 p.m. on November 16, 1954, it became evident that the house was on fire. Plaintiff noticed sparks coming out of the side of the chimney near a wooden sill resting on top of the stone cellar wall. Mumma had not been living in the house up until that time but had been in the process of making repairs for a period of several months.

Mumma had a furnace installed in the house with plaintiff's consent. In order to install the furnace he had the chimney extended downward from the middle of the first floor. Defendant, a general contractor with 11 years’ experience, made the installation of the chimney. The chimney was constructed of building blocks with a clay flue liner. In order to install the chimney defendant cut out the stone wall for a distance of approximately two feet from its top downward. On top of the stone wall was a large wooden sill on which the house rested. In order to pass this wooden sill with the extension of the chimney downward it was necessary to offset the cinder blocks surrounding the flue liner. A portion of one of the cinder blocks rested on the wooden sill. The tenant, who was papering and painting the house, had built a number of wood fires in the furnace prior to the time he had coal put in. Several days before the fire occurred he had started a coal fire in the furnace.

On the day of the fire, the furnace was banked off and there was no draft turned on. The tenant was the first person to enter the cellar from the outside. The inside of the sill and the ends of four rafters near the base of the chimney were on fire. The fire had also burned up to the second floor between the weatherboarding and the studding and then proceeded across the second floor under the floors of two bedrooms and [638]*638actually burned the whole way across the second floor. The firemen, who had come very promptly, removed the smokepipe from the furnace to the chimney. This was done by the fire chief, Ralph R. Baughman.

When the pipe was removed it was noticed that there were openings on each side between the flue liner and the cinder block of the chimney. The openings were several inches long and a fraction of an inch wide. No repairs had ever been made to the old portion of the chimney nor had the same been cleaned since 1913. The wiring in the house had been installed in 1915. The firemen arrived shortly after the fire started and found that the fire had broken through about halfway up between the basement and the second story. Defendant and his witnesses testified that all of the cinder blocks were mortared together. Defendant himself observed the crevices between the cinder block and the flue liner about 9 on the evening of the fire, but he and the man who had actually repaired the chimney testified that these crevices were filled with mortar when the chimney was finished. The man who built the chimney testified that he offset the fourth cinder block one half or three fourths of an inch in order to get past the wooden sill. He testified that that was the maximum setoff possible because of the limited play of the flue liner inside the blocks.

The work on the chimney was completed before the furnace was installed. The man who installed the furnace testified that he examined the base of the chimney and found no crevices at the time that he installed the furnace pipe. Defendant’s witnesses testified that the cellar, at the time they installed the furnace, was cluttered with old lumber, bottles and cans and that the wiring above the furnace and at the foot of the basement steps was frayed. Aside from the fact that the crevices were mortared at the time the chimney was installed, defendant stated that the fire could not have [639]*639gone up between the flue and the cinder blocks because the mortar placed between each cinder block was squeezed out and filled up the space between the flue and the blocks.

The questions presented for the court’s consideration by the motion for a new trial are as follows:

1. Was the verdict against the weight of the evidence?

2. Did the court err in refusing to permit Fire Chief Ralph R. Baughman to testify as an expert witness?

3. Did the court err in refusing to permit J. E. Sacriste to give his opinion as to the cause of the particular fire in issue?

Plaintiff has phrased her statement of the third question involved as being the refusal of the court to permit J. E. Sacriste to testify as an expert witness. Such a statement of the third question is incorrect. Mr. Sacriste was admitted by defendant to be an expert in the investigation of fires. He was permitted to testify as an expert and gave his opinion as to the possible effect of the unsealed crevices which he discovered on the day he made his examination. All that the trial judge did on his ruling was to hold that the witness could not give his opinion as to the cause of “this specific fire”.

It is true that a new trial will be granted where the verdict is clearly against the weight of the evidence. However, in order to warrant the granting of a new trial on the ground that the verdict is against the weight of the evidence, the preponderance of evidence must be clear and decisive: Standard Pennsylvania Practice, vol. 6, p. 319. Inasmuch as the jury has found in favor of defendant, their findings of facts have been in his favor and the court must, therefore, view the testimony in the light most favorable to defendant, and defendant must be given the benefit of [640]*640every inference and deduction reasonably to be made therefrom: Rubin Brothers Waste Co. v Standard Equipment Co., 368 Pa. 61.

Defendant has testified that he was a building contractor with 11 years’ experience. He and his witnesses testified that the chimney when it was installed was properly sealed at the bottom. Defendant explains the absence of sealer after the fire by suggesting that it must have fallen out when the pipe was removed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stevenson v. East Deer Township
108 A.2d 815 (Supreme Court of Pennsylvania, 1954)
Commonwealth v. Nasuti
123 A.2d 435 (Supreme Court of Pennsylvania, 1956)
Decker v. Kulesza
85 A.2d 413 (Supreme Court of Pennsylvania, 1952)
Burton v. Horn & Hardart Baking Co.
88 A.2d 873 (Supreme Court of Pennsylvania, 1952)
Sinkovich v. Bell Tel. Co. of Pa.
133 A. 629 (Supreme Court of Pennsylvania, 1926)
Reithof v. Pittsburgh Railways Co.
65 A.2d 346 (Supreme Court of Pennsylvania, 1949)
Sweeney v. Blue Anchor Beverage Co.
189 A. 331 (Supreme Court of Pennsylvania, 1936)
Commonwealth v. Greenberg
17 A.2d 698 (Superior Court of Pennsylvania, 1940)
Graham v. Pennsylvania Co.
21 A. 151 (Supreme Court of Pennsylvania, 1891)
Struthers v. Philadelphia & Delaware County Railroad
34 A. 443 (Supreme Court of Pennsylvania, 1896)
Groff v. Groff
59 A. 65 (Supreme Court of Pennsylvania, 1904)
Wissinger v. Valley Smokeless Coal Co.
115 A. 880 (Supreme Court of Pennsylvania, 1922)
Rubin Bros. Waste Co. v. Standard Equipment Co.
81 A.2d 876 (Supreme Court of Pennsylvania, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
8 Pa. D. & C.2d 635, 1956 Pa. Dist. & Cnty. Dec. LEXIS 381, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sperow-v-carter-pactcomplcumber-1956.