Spencer v. Stowell

2017 Ohio 7353
CourtOhio Court of Appeals
DecidedAugust 25, 2017
DocketWD-16-044
StatusPublished
Cited by1 cases

This text of 2017 Ohio 7353 (Spencer v. Stowell) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Spencer v. Stowell, 2017 Ohio 7353 (Ohio Ct. App. 2017).

Opinion

[Cite as Spencer v. Stowell, 2017-Ohio-7353.]

IN THE COURT OF APPEALS OF OHIO SIXTH APPELLATE DISTRICT WOOD COUNTY

Cara Spencer Court of Appeals No. WD-16-044

Appellee Trial Court No. 2014 CV 0633

v.

Matthew Stowell, et al. DECISION AND JUDGMENT

Appellant Decided: August 25, 2017

*****

Gregory L. Arnold, for appellee.

Ann M. Baronas, for appellant.

JENSEN, J.

{¶ 1} Appellant, Matthew Stowell, appeals the May 25, 2016 judgment of the

Wood County Court of Common Pleas granting summary judgment to appellee, Cara

Spencer. For the following reasons, we affirm. I. Background

{¶ 2} This case arose from a dispute over a construction contract between Ms.

Spencer and Maumee River Remodeling (“Maumee River”). On July 31, 2014, Ms.

Spencer signed a contract for the construction of an addition to her home. The contract

indicates that the contracting parties are Ms. Spencer and Maumee River. Though the

name Maumee River Remodeling appears on the contract, the contract does not indicate

what type of entity Maumee River is. The contract contains Ms. Spencer’s signature and

an illegible signature above the line labeled “Sales Representative.” Ms. Spencer

indicated in her affidavit in support of her motion for summary judgment that Mr.

Stowell signed the contract. The contract contains an area for approval of the contract by

an officer of Maumee River; it is unsigned.

{¶ 3} In her affidavit, Ms. Spencer averred that she signed the contract with

Maumee River on July 31, 2014, and tendered a check for $17,000 made out to “Maumee

River Remodeling” as a down payment. She claimed that she was told that the project

would take approximately eight weeks from the contract date to complete. Mr. Stowell

and Maumee River began work on September 9, 2014. Though they did some

excavating, they did not complete any other work on the project. Ms. Spencer said she

tried to call Mr. Stowell and Maumee River several times, but no one returned her calls.

She discovered on October 29, 2014, that neither Mr. Stowell nor Maumee River had

obtained the building permits required for the project. According to Ms. Spencer, Mr.

Stowell came to her home on October 31, 2014, to tell her she “should contact a stranger

2. to perform the job * * *.” He also refused her request to refund her $17,000 down

payment. Ms. Spencer eventually hired another contractor to complete the job at an

additional expense of approximately $35,000.

{¶ 4} Ms. Spencer filed suit on December 17, 2014, against Matthew Stowell;

Matthew Stowell, dba Maumee River Remodeling; Matthew Stowell, dba Maumee River

Remodeling, LLC; and Maumee River Remodeling, LLC for breach of contract,

constructive trust, unjust enrichment, conversion, accounting, punitive damages and

attorney fees. Ms. Spencer eventually dismissed all claims except the two breach of

contract claims.

{¶ 5} Neither Mr. Stowell nor Maumee River initially responded to Ms. Spencer’s

complaint. After Ms. Spencer filed a motion for default judgment, Mr. Stowell sent a

letter to the trial court on August 14, 2015, that essentially contested his liability. The

court treated the correspondence as an answer for all of the defendants. In its entry

adopting the letter as an answer, the court required Mr. Stowell to file either a notice of

appearance by an attorney or a notice that he was proceeding pro se within 14 days. Mr.

Stowell opted to proceed pro se.

{¶ 6} On February 9, 2016, after an unsuccessful mediation attempt, Ms. Spencer

served Mr. Stowell with interrogatories, requests for production, and requests for

admission. Ms. Spencer requested responses within 28 days, but Mr. Stowell did not

respond. On March 23, 2016, Ms. Spencer filed a motion for summary judgment against

Mr. Stowell individually based on her affidavit and Mr. Stowell’s failure to respond to

3. the requests for admission. She argued that under Civ.R. 36 Mr. Stowell’s silence

conclusively established that: (1) Mr. Stowell failed to obtain a building permit for Ms.

Spencer’s project; (2) Mr. Stowell failed to submit building plans for Ms. Spencer’s

project to the Wood County Building Inspection Office; and (3) Ms. Spencer suffered

damages in the amount of $52,365 as a result of Mr. Stowell’s breach of contract. On

April 4, 2016, Ms. Spencer also filed a motion for default judgment against Maumee

River.

{¶ 7} Mr. Stowell responded to the motion for summary judgment on April 19,

2016, by sending another letter to the court. In it he claimed that Ms. Spencer’s contract

was with Maumee River, a limited liability company—not with Mr. Stowell personally—

and outlined the evidence he intended to provide to Ms. Spencer by the court’s discovery

deadline. He asked the court to deny Ms. Spencer’s motions for summary judgment and

default judgment. Mr. Stowell did not include any documents, affidavits, or other

evidentiary material with his response.

{¶ 8} The trial court issued its decision on May 25, 2016. It found, as to Ms.

Spencer’s breach of contract claims only, that Ms. Spencer’s affidavit and the facts in the

unanswered requests for admission entitled Ms. Spencer to summary judgment against

Mr. Stowell personally. The court also clarified that Mr. Stowell’s August 14

correspondence constituted his personal answer to Ms. Spencer’s complaint and found

that Maumee River was in default. The court awarded Ms. Spencer a judgment of

$52,365 plus statutory interest against Maumee River and Mr. Stowell jointly and

4. severally. Ms. Spencer dismissed all remaining counts in her complaint after the trial

court issued its decision.

{¶ 9} Mr. Stowell appeals the trial court’s decision, setting forth two assignments

of error:

APPELLANTS’S [sic] ASSIGNMENT OF ERROR NUMBER

ONE: THE TRIAL COURT ERRED IN GRANTING SUMMARY

JUDGMENT AGAINST MATTHEW STOWELL, PERSONALLY,

WHEN CONTRACT FOR SERVICES WAS WITH MAUMEE RIVER

REMODEDLING, [sic] L.L.C., NOT MATTEW [sic] STOWELL,

PERSONALLY[.]

APPELLANT’S ASSIGNMENT OF ERROR NUMBER TWO:

THE TRIAL COURT ERRED IN GRANTING SUMMARY JUDGMENT

WHEN GENUINE ISSUES OF MATERIAL FACT EXISTED.

II. Law and Analysis

{¶ 10} An appellate court reviews summary judgment de novo, employing the

same standard as the trial court. Grafton v. Ohio Edison Co., 77 Ohio St.3d 102, 105,

671 N.E.2d 241 (1996); Lorain Natl. Bank v. Saratoga Apts., 61 Ohio App.3d 127, 129,

572 N.E.2d 198 (9th Dist.1989). The court can grant a motion for summary judgment

only when the moving party demonstrates:

(1) that there is no genuine issue as to any material fact; (2) that the moving

party is entitled to judgment as a matter of law; and that (3) that reasonable

5. minds can come to but one conclusion, and that conclusion is adverse to the

party against whom the motion for summary judgment is made, who is

entitled to have the evidence construed most strongly in his favor. Harless

v. Willis Day Warehousing Co., 54 Ohio St.2d 64, 66, 375 N.E.2d 46

(1978); Civ.R. 56(C).

{¶ 11} The party seeking summary judgment must specifically delineate the basis

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Riesterer v. Porter
2022 Ohio 1698 (Ohio Court of Appeals, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
2017 Ohio 7353, Counsel Stack Legal Research, https://law.counselstack.com/opinion/spencer-v-stowell-ohioctapp-2017.