Spencer v. Stowell

2017 Ohio 7353
Ohio Court of Appeals·Decided August 25, 2017·No. WD-16-044·Published·Cited by 1 cases

Opinion

IN THE COURT OF APPEALS OF OHIO SIXTH APPELLATE DISTRICT

WOOD COUNTY

Cara Spencer Court of Appeals No. WD-16-044 Appellee Trial Court No. 2014 CV 0633 v. Matthew Stowell, et al. DECISION AND JUDGMENT Appellant Decided: August 25, 2017

*****

Gregory L. Arnold, for appellee.

Ann M. Baronas, for appellant.

*****

JENSEN, J.

{¶ 1} Appellant, Matthew Stowell, appeals the May 25, 2016 judgment of the Wood County Court of Common Pleas granting summary judgment to appellee, Cara Spencer. For the following reasons, we affirm.

I. Background

{¶ 2} This case arose from a dispute over a construction contract between Ms.

Spencer and Maumee River Remodeling (“Maumee River”). On July 31, 2014, Ms. Spencer signed a contract for the construction of an addition to her home. The contract indicates that the contracting parties are Ms. Spencer and Maumee River. Though the name Maumee River Remodeling appears on the contract, the contract does not indicate what type of entity Maumee River is. The contract contains Ms. Spencer’s signature and an illegible signature above the line labeled “Sales Representative.” Ms. Spencer indicated in her affidavit in support of her motion for summary judgment that Mr. Stowell signed the contract. The contract contains an area for approval of the contract by an officer of Maumee River; it is unsigned.

{¶ 3} In her affidavit, Ms. Spencer averred that she signed the contract with Maumee River on July 31, 2014, and tendered a check for $17,000 made out to “Maumee River Remodeling” as a down payment. She claimed that she was told that the project would take approximately eight weeks from the contract date to complete. Mr. Stowell and Maumee River began work on September 9, 2014. Though they did some excavating, they did not complete any other work on the project. Ms. Spencer said she tried to call Mr. Stowell and Maumee River several times, but no one returned her calls. She discovered on October 29, 2014, that neither Mr. Stowell nor Maumee River had obtained the building permits required for the project. According to Ms. Spencer, Mr. Stowell came to her home on October 31, 2014, to tell her she “should contact a stranger to perform the job * * *.” He also refused her request to refund her $17,000 down payment. Ms. Spencer eventually hired another contractor to complete the job at an additional expense of approximately $35,000.

{¶ 4} Ms. Spencer filed suit on December 17, 2014, against Matthew Stowell;

Matthew Stowell, dba Maumee River Remodeling; Matthew Stowell, dba Maumee River Remodeling, LLC; and Maumee River Remodeling, LLC for breach of contract, constructive trust, unjust enrichment, conversion, accounting, punitive damages and attorney fees. Ms. Spencer eventually dismissed all claims except the two breach of contract claims.

{¶ 5} Neither Mr. Stowell nor Maumee River initially responded to Ms. Spencer’s complaint. After Ms. Spencer filed a motion for default judgment, Mr. Stowell sent a letter to the trial court on August 14, 2015, that essentially contested his liability. The court treated the correspondence as an answer for all of the defendants. In its entry adopting the letter as an answer, the court required Mr. Stowell to file either a notice of appearance by an attorney or a notice that he was proceeding pro se within 14 days. Mr. Stowell opted to proceed pro se.

{¶ 6} On February 9, 2016, after an unsuccessful mediation attempt, Ms. Spencer served Mr. Stowell with interrogatories, requests for production, and requests for admission. Ms. Spencer requested responses within 28 days, but Mr. Stowell did not respond. On March 23, 2016, Ms. Spencer filed a motion for summary judgment against Mr. Stowell individually based on her affidavit and Mr. Stowell’s failure to respond to the requests for admission. She argued that under Civ.R. 36 Mr. Stowell’s silence conclusively established that: (1) Mr. Stowell failed to obtain a building permit for Ms. Spencer’s project; (2) Mr. Stowell failed to submit building plans for Ms. Spencer’s project to the Wood County Building Inspection Office; and (3) Ms. Spencer suffered damages in the amount of $52,365 as a result of Mr. Stowell’s breach of contract. On April 4, 2016, Ms. Spencer also filed a motion for default judgment against Maumee River.

{¶ 7} Mr. Stowell responded to the motion for summary judgment on April 19, 2016, by sending another letter to the court. In it he claimed that Ms. Spencer’s contract was with Maumee River, a limited liability company—not with Mr. Stowell personally— and outlined the evidence he intended to provide to Ms. Spencer by the court’s discovery deadline. He asked the court to deny Ms. Spencer’s motions for summary judgment and default judgment. Mr. Stowell did not include any documents, affidavits, or other evidentiary material with his response.

{¶ 8} The trial court issued its decision on May 25, 2016. It found, as to Ms.

Spencer’s breach of contract claims only, that Ms. Spencer’s affidavit and the facts in the unanswered requests for admission entitled Ms. Spencer to summary judgment against Mr. Stowell personally. The court also clarified that Mr. Stowell’s August 14 correspondence constituted his personal answer to Ms. Spencer’s complaint and found that Maumee River was in default. The court awarded Ms. Spencer a judgment of $52,365 plus statutory interest against Maumee River and Mr. Stowell jointly and severally. Ms. Spencer dismissed all remaining counts in her complaint after the trial court issued its decision.

{¶ 9} Mr. Stowell appeals the trial court’s decision, setting forth two assignments of error:

APPELLANTS’S [sic] ASSIGNMENT OF ERROR NUMBER ONE: THE TRIAL COURT ERRED IN GRANTING SUMMARY JUDGMENT AGAINST MATTHEW STOWELL, PERSONALLY, WHEN CONTRACT FOR SERVICES WAS WITH MAUMEE RIVER REMODEDLING, [sic] L.L.C., NOT MATTEW [sic] STOWELL, PERSONALLY[.]

APPELLANT’S ASSIGNMENT OF ERROR NUMBER TWO:

THE TRIAL COURT ERRED IN GRANTING SUMMARY JUDGMENT WHEN GENUINE ISSUES OF MATERIAL FACT EXISTED.

II. Law and Analysis

{¶ 10} An appellate court reviews summary judgment de novo, employing the same standard as the trial court. Grafton v. Ohio Edison Co., 77 Ohio St.3d 102, 105, 671 N.E.2d 241 (1996); Lorain Natl. Bank v. Saratoga Apts., 61 Ohio App.3d 127, 129, 572 N.E.2d 198 (9th Dist.1989). The court can grant a motion for summary judgment only when the moving party demonstrates:

(1) that there is no genuine issue as to any material fact; (2) that the moving party is entitled to judgment as a matter of law; and that (3) that reasonable minds can come to but one conclusion, and that conclusion is adverse to the party against whom the motion for summary judgment is made, who is entitled to have the evidence construed most strongly in his favor. Harless v. Willis Day Warehousing Co., 54 Ohio St.2d 64, 66, 375 N.E.2d 46 (1978); Civ.R. 56(C).

Free access — add to your briefcase to read the full text and ask questions with AI

Spencer v. Stowell, 2017 Ohio 7353 (Ohio Ct. App. 2017).

2017 Ohio 7353 (Spencer v. Stowell) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Riesterer v. Porter
2022 Ohio 1698 (Ohio Court of Appeals, 2022)