Spencer v. Allpress Logging, Inc.

11 P.3d 475, 134 Idaho 856, 2000 Ida. LEXIS 104
CourtIdaho Supreme Court
DecidedSeptember 12, 2000
Docket24951
StatusPublished
Cited by17 cases

This text of 11 P.3d 475 (Spencer v. Allpress Logging, Inc.) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Spencer v. Allpress Logging, Inc., 11 P.3d 475, 134 Idaho 856, 2000 Ida. LEXIS 104 (Idaho 2000).

Opinion

KIDWELL, Justice.

This ease arises from an injury received during a logging operation. The claimant contends that the lumber mill, which purchased the logs, was the statutory employer of the claimant and is thus liable for the claimant’s worker’s compensation benefits. We agree.

I.

FACTS AND PROCEDURAL BACKGROUND

Steve Schilling acquired over 1200 acres of land in North Idaho between 1991 and 1994 valued between $500,000 and $600,000. Schilling purchased these properties by entering into timber sales contracts with different timber mills. One of these properties, known as the Greer Grade property, involved the sale of timber to two separate mills.

Schilling purchased the Greer Grade property for $200,000 in August of 1992. Prior to closing escrow on the Greer Grade property, Schilling contacted several mills to arrange for the best price for the timber on the property. The two mills Schilling ultimately contracted with were the Triple R (a former wholly owned subsidiary of Weyerhaeuser) and Columbia Vista. Columbia agreed to purchase the Douglas fir and Weyerhaeuser agreed to purchase the Ponderosa pine. Both of these mills agreed to advance Schilling $100,000 (secured by the timber on the land) which he used to purchase the property.

Under each of the separate contracts with Weyerhaeuser and Columbia, Schilling was required to harvest the timber and deliver it to their respective mills. The contract between Schilling and Weyerhaeuser provided that Weyerhaeuser would advance Schilling $100,000 and in return Weyerhaeuser would have the right to cut and remove Ponderosa pine from Greer Grade. Additionally, the contract provided that when Schilling delivered timber to Weyerhaeuser, a portion of the contract price would be used to reduce the advance and a portion would be allocated to cover the cost of harvesting the timber. The contract had an ending date of April 1, 1993. If during that time Schilling delivered more than the $100,000 advance, Weyerhaeuser would pay Schilling at the contract rate. If, on the other hand, Schilling did not completely pay off the advance by that date, Weyerhaeuser would have the right to reimbursement of the unpaid balance. At that time the rights to the remaining timber would revert back to Schilling. The contract also provided that Weyerhaeuser would assume the risk of loss during the contract period, and that in addition to the right of ingress and egress, Weyerhaeuser would have the right to build and maintain roads on the property as needed to remove timber.

Schilling’s agreement with Columbia was similar to the one with Weyerhaeuser. Schilling was to pay off the $100,000 advance by Columbia by delivering Douglas fir from the Greer Grade property. Columbia had the same rights of ingress and egress, and to build roads as needed. Like the Weyerhaeuser contract, a portion of each delivery to Columbia would be used to pay off the advance, and a portion would be used to pay Schilling for the cost of harvesting the tim *858 ber. Unlike the Weyerhaeuser contract, however, the Columbia contract did not have a specific ending date. Rather it provided that the contract would end when full delivery had been made.

Schilling contracted with James AUpress of AUpress Logging to cut and deliver the timber to both Weyerhaeuser and Columbia. During the logging, AUpress exclusively used his own equipment, with the exception of Schüling’s CaterpiUar tractor which was used as a “deadman.” AUpress hired, instructed and paid his own employees without any involvement from SchiUing, Weyerhaeuser or Columbia. On all but two occasions, checks were issued from Weyerhaeuser and Columbia directly to SchUling who deposited them into his personal account. SchiUing would then pay AUpress out of this account. Twice, Weyerhaeuser made a draw (an advanced payment) for harvesting costs. For these two draws, Weyerhaeuser issued the checks to both SchiUing and AUpress. SchUling endorsed the cheeks, and AUpress cashed them.

The logging operation began in October or November of 1992 and continued until shortly after the accident on September 9, 1993. On that date, one of AUpress’s employees, claimant Justin Spencer, was severely injured when the line machine he was operating tipped over on top of him. At the time of the accident neither AUpress nor SchUling had worker’s compensation insurance coverage for Spencer.

AUpress testified in his deposition that the logs which were being puUed up the lull at the time of the accident were consistent with those going to Weyerhaeuser. Although the matter was never conclusively decided by the Industrial Commission, there was no evidence presented to indicate that the logs were going to Columbia Vista.

Because SchUling was unsatisfied with the progress of the logging, he directed AUpress off the property prior to the completion of either timber contract. SchiUing and his father then worked from the fall of 1993 through the spring of 1994 to complete the contracts.

Because of delays in the logging process, Weyerhaeuser extended the contract deadline twice. Both of the extensions were granted during the time that AUpress was logging on the property. On March 26,1993, the deadline was extended to around June 1, 1993, then on July 14, 1993, the contract was extended to August 1,1993.

SchUling, however, did not complete delivery prior to August 1, 1993. He and his father continued to make deliveries and Weyerhaeuser continued to accept dehveries under the terms of the original contract through the spring of 1994. When the original contract was completed, SchiUing and Weyerhaeuser entered into another timber sale agreement. SchUling used part of these proceeds to pay off the outstanding balance owed to Columbia. AH timber harvesting concluded by June or July of 1994.

During the logging process, representatives from Weyerhaeuser made several visits to the Greer Grade property. Most of these visits were to cheek the progress of the logging and to check for weathering conditions on the feUed logs. Columbia also made simüar visits to the property. During each of the visits by representatives of either Weyerhaeuser or Columbia, the representative would contact only SchUling, and did not provide any logging instruction to either SchUling or AUpress.

Spencer filed a worker’s compensation complaint on December 6,1993. On November 29, 1995, the Industrial Commission held a hearing. On December 13, 1996, the Industrial Commission announced a two to one decision 1 that (1) AUpress was personally liable for Spencer’s worker’s compensation benefits, (2) SchUling was Spencer’s statutory employer and thus personaUy liable for Spencer’s worker’s compensation benefits, and (3) Weyerhaeuser was also a statutory *859 employer of Spencer’s and was also liable for his worker’s compensation benefits. Commissioner Gilbert dissented on the basis that the Idaho Code should not be interpreted as being so broad as to include Weyerhaeuser simply because it purchased raw materials from Schilling.

Spencer moved for reconsideration. On July 21, 1998, the Industrial Commission entered an order on reconsideration which reversed and vacated its prior order.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith v. Excel Fabrication, LLC
535 P.3d 1098 (Idaho Supreme Court, 2023)
Alcala v. Verbruggen Palletizing Solutions, Inc.
531 P.3d 1085 (Idaho Supreme Court, 2023)
Fulfer v. Sorrento Lactalis, Inc.
520 P.3d 708 (Idaho Supreme Court, 2022)
Kelly v. TRC Fabrication LLC
487 P.3d 723 (Idaho Supreme Court, 2021)
Geff Stringer v. William Robinson
314 P.3d 609 (Idaho Supreme Court, 2013)
Seven Resorts, Inc. v. United States
112 Fed. Cl. 745 (Federal Claims, 2013)
Pierce v. School District 21
164 P.3d 817 (Idaho Supreme Court, 2007)
Dilulo v. Anderson & Wood Co.
153 P.3d 1175 (Idaho Supreme Court, 2007)
Kolar v. Cassia County Idaho
127 P.3d 962 (Idaho Supreme Court, 2005)
Gonzalez v. Lamb Weston, Inc.
124 P.3d 996 (Idaho Supreme Court, 2005)
Venters v. Sorrento Delaware, Inc.
108 P.3d 392 (Idaho Supreme Court, 2005)
Robison v. Bateman-Hall, Inc.
76 P.3d 951 (Idaho Supreme Court, 2003)
Lopez v. State
30 P.3d 952 (Idaho Supreme Court, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
11 P.3d 475, 134 Idaho 856, 2000 Ida. LEXIS 104, Counsel Stack Legal Research, https://law.counselstack.com/opinion/spencer-v-allpress-logging-inc-idaho-2000.