Speier v. Locust Laundry

63 Pa. Super. 99, 1916 Pa. Super. LEXIS 111
CourtSuperior Court of Pennsylvania
DecidedMay 8, 1916
DocketAppeal, No. 265
StatusPublished
Cited by4 cases

This text of 63 Pa. Super. 99 (Speier v. Locust Laundry) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Speier v. Locust Laundry, 63 Pa. Super. 99, 1916 Pa. Super. LEXIS 111 (Pa. Ct. App. 1916).

Opinion

Opinion by

Rice, P. J.,

The judgment of this court on the former appeal .(56 Pa. Superior Ct. 323) did not abate the action. The plaintiff still had two actions pending, the present one and the prior action in C. P. No. 3;' both claims arose directly out of the same contract, which was conceded by the pleadings to be an entire contract; both claims were due at the inception of the first suit; both were money demands; and both involved, if they did not entirely depend upon, the same" breach of contract, namely the wrongful discharge of the plaintiff. As was further pointed out in the opinion rendered on the former appeal there is no conceivable reason why both claims could not be joined in one action, and there are many good reasons why they should be. It follows that the defendant’s objection against being compelled to defend both actions was good and still remained notwithstanding the judgment entered by this court on the former appeal. But this objection did not go to the merits of either action, and .could be removed. This being the situation,. the plaintiff obtained orders, (1) consolidating the two actions; (2) permitting him to amend his statement so as to join both claims, and subsequently amended his statement accordingly. If the purpose and effect of the first of these orders had been simply to transfer the' case pending in C. P. No. 3 from that court to C. P. No. 1 for trial in connection with the case pending in the latter [103]*103court, there would be merit in the appellant’s contention that the order was not authorized by Rule 5 of the Common Pleas, entitled, “Transfer of Cases.” But as shown by the petition such was not the purpose for which the order was applied, and when the order is considered in connection with the order permitting the plaintiff’s statement to be.amended, it is very clear that such was not the effect. The object was to correct the mistake the plaintiff had made in splitting up his demands, and it ■is needless to say that he had not irretrievably lost his right to recover either of them by that initial mistake. By obtaining the first order and then amending his statement pursuant to leave of court granted by the second order the plaintiff, as effectually precluded himself from further prosecuting the action in C. P. No. 3, as if he had discontinued it, (which unquestionably he might have done) and at the same time put himself in position to recover his entire demand, if the facts warranted such recovery. ■ Thereby the technical objection, originally pleadable in abatement, was removed and the substantive rights of both parties were preserved. The action of the court, viewed as a connected whole in the light of the special facts of the case, was outside of and not supported by Rule 5 of the Common Pleas, it is true, but it was not in violation of it and was eminently fair and just, as well as legal.

The amended statement of claim embraced the two demands which had been embraced in the two actions thus consolidated. They were, first, for the salary accruing between March 23,1912, and November 28,1912, the end of the contract period, second, for the money due under the clause of the contract relating to the wagon, harness, route, etc. It is alleged in the statement of the claim and admitted in the affidavit of defense that the plaintiff, upon being discharged from employment on March 9,1912, brought three separate actions for $25.00 each, being the salary due for the weeks ending March 9, March 16, March 23,1912, which actions, having been [104]*104brought into the Common Pleas by appeal, were put at issue, tried together, and resulted in verdicts in plaintiff’s favor for the sums claimed, with interest, and which the defendant satisfied by payment. Both parties concur in claiming that these former recoveries have a conclusive effect in the present issue, but they differ as to what that effect is. The plaintiff’s contention is that they are conclusive upon the question of the wrongfulness of his discharge, which the defendant by its affidavit of defense attempts to raise; while the defendant contends that they are a complete bar to the present action.

We fail to see how they can be held to be a bar to the action so far as it relates to the clause of the contract whereby, at the expiration of eighteen months from the date of the contract and upon payment by the defendant to the plaintiff of f350.00, the title to the property should vest in, the defendant. Evidently the parties intended that vesting of the title and payment of the price should occur at the same time. There is nothing in the contract, and no principle of law, that put it in the power of the defendant, at its own ex-parte election, to advance the time when the title would vest; and if it could not do that directly, it could not do it indirectly by wrongfully discharging the plaintiff and thus breaking the contract. The plaintiff was not bound to take back the property when he was wrongfully discharged, even though it was tendered, but had a right to wait until the expiration of the eighteen months before asserting his claim under this clause of the contract. It follows that he was not barred from recovering it by not including it in the actions for salary brought by him long before the expiration of that period.

So far as the demand for balance of salary not sued for and recovered in the first three actions is concerned, the decision of the main question is ruled by Allen v. International Text Book Company, 201 Pa. 579, and Stradley v. Bath Portland Cement Co., 228 Pa. 108. In the first of these cases it was held that where a person [105]*105is employed for a definite period at a fixed salary payable in weekly installments, and is discharged during the period, and two weeks afterwards sues for two installments of his salary and recovers a judgment which is paid, such a judgment conclusively establishes the wrongfulness of the discharge, and in an action brought after the period of employment had expired to recover salary for the balance of the year, the question of the wrongfulness of the plaintiff’s discharge cannot again be inquired into, and the defendant is confined to proof of payment, or release, or of facts in mitigation of damages. The same principle was recognized and applied in the Stradley case where it was further held, that where an employee under such a contract has been wrongfully discharged, he can, if he sees fit bring a separate action as each installment of salary falls due; yet if no action is brought until more than one is due, all installments that are then due must be included in the one action; and if an action is brought when more than one is due, a recovery in such action will be an effectual bar to a second suit brought to recover installments which were due at the time of the inception of the first action; and this on the theory that a judgment settles everything involved in the right to recover, not only matters that were raised, but those which might have been raised. It is argued by appellant’s counsel’ that at the time of obtaining judgment in the first of the three actions above referred to “at least four weeks’ salary was due, and in taking judgment for only one week the three weeks omitted must at least be deducted from the present claim under the reasoning in Stradley v. Bath Portland Cement Company.” This contention cannot be sustained.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Savitz v. GALLACCIO
118 A.2d 282 (Superior Court of Pennsylvania, 1955)
Weidner v. Augustine Construction Co.
57 Pa. D. & C. 3 (Philadelphia County Court of Common Pleas, 1946)
Russell v. Barnes Foundation
52 F. Supp. 827 (E.D. Pennsylvania, 1943)
Gordon v. Tomei
19 A.2d 588 (Superior Court of Pennsylvania, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
63 Pa. Super. 99, 1916 Pa. Super. LEXIS 111, Counsel Stack Legal Research, https://law.counselstack.com/opinion/speier-v-locust-laundry-pasuperct-1916.