Speegle Construction, Inc.

CourtArmed Services Board of Contract Appeals
DecidedMay 10, 2016
DocketASBCA No. 60089
StatusPublished

This text of Speegle Construction, Inc. (Speegle Construction, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Speegle Construction, Inc., (asbca 2016).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of-- ) ) Speegle Construction, Inc. ) ASBCA No. 60089 ) Under Contract No. W91278-07-D-0038 )

APPEARANCE FOR THE APPELLANT: Jesse W. Rigby, Esq. Clark, Partington, Hart, Larry, Bond & Stackhouse Pensacola, FL

APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq. Engineer Chief Trial Attorney David C. Brasfield, Jr., Esq. Andrea M. Dowdy, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Mobile

OPINION BY ADMINISTRATIVE JUDGE THRASHER ON THE GOVERNMENT'S MOTION FOR SUMMARY JUDGMENT

The United States Army Corps of Engineers (Corps or government) moves for summary judgment, arguing that Speegle Construction Inc. (Speegle or appellant) executed a bilateral modification that constituted both a release and an accord and satisfaction barring appellant's claim as a matter of law. 1 Appellant opposes the motion. 2 We deny the motion for the reasons set forth below.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. In 2006, Speegle was awarded an indefinite-delivery/indefinite-quantity (ID/IQ) contract (Contract No. W91278-07-D-0038) (Contract), for military construction support to the Corps' South Atlantic Division (R4, tab 4 at 1, 11). On 1 July 2010, Speegle was awarded Task Order (TO) No. 0004 for Design-Build Repair Hurricane Damage Phase I, Mississippi Army Ammunition Plant (MSAAP), Stennis Space Center,

1 The government's motion included an attached exhibit (ex. G-1), a Price Negotiation Memorandum (PNM), dated 26 November 2012. 2 Appellant's response to the government's motion for summary judgment included an attached affidavit of Jeffrey S. Page, President of Speegle Construction, Inc., dated 24 November 2015 (ex. A-1). Mississippi (R4, tab 5 at 2). The stated purpose of the TO was to repair damage to the existing facilities resulting from Hurricane Katrina in September 2006 and to harden MSAAP infrastructure against future hurricanes. Phase I of the work included installation of underground communication system duct banks and the construction of a new alternate communications Point of Presence (POP) facility. (R4, tab 5 at 100)

2. On 16 November 2012, the parties executed bilateral Modification No. 000404/SC003 (Mod. 000404/SC003) modifying TO 0004 to incorporate changes to the scope of the work on the POP facility (R4, tab 6 at 13). Shortly thereafter it was discovered changes were required to the fire suppression system added by Mod. 000404/SC003 due to inadequate design data and update to new equipment parameters (ex. G-1). On 26 November 2012, the parties entered into negotiations to implement the changes to the POP facility fire suppression system. The parties reached agreement on all terms except the 122% field overhead rate Speegle proposed on behalf of one of its subcontractors, L. Pugh & Associates, Inc. (L. Pugh). (Id.) The parties were unable to reach agreement on this issue and, on 7 December 2012, the Corps issued unilateral Modification No. 00041H (Mod. 00041H) applying a 10% field overhead rate for L. Pugh. The modification did not provide a time extension and specifically reserved each party's rights to pursue claims under the Disputes clause. (R4, tab 6 at 15-16)

3. By Serial Letter H-0064, dated 19 August 2013, Speegle requested that the Corps obtain a DCAA audit ofL. Pugh's overhead rate (R4, tab 7). That same day, Speegle sent Serial Letter H-0066 requesting a 21-day time extension, stating:

On December 7, 2012 the Government issued unilateral modification SC01 l/00041H (attached) for Fire Suppression Changes for the subject contract. This unilateral was issued in the amount of $292,320.37 for added scope to the life safety systems for the subject contract. Please note this modification was not mutually agreed/accepted by SCI. The amount of the modification remains in dispute with regard to the subcontractor's overhead rate. SCI has submitted via a separate transmittal (reference serial letter H-0064) a request on behalf of L. Pugh and Associates for a DCAA audit. In addition, SCI was not granted additional contract performance time for this specific modification. Reference paragraph (D) of the subject modification wherein it states: The contract completion date shall remain unchanged by this modification. SCI does acknowledge additional contract time was added to modification 000404/SC003 - Misc. Scope changes to

2 POP Facility; however that modification was dated/executed on November 11, 2012, (21) days prior to issuing the unilateral modification for the Fire Suppression System.

The subject modification (SC01 l/00041H) significantly increased the scope of the Fire Suppression System .... This additional work added hundreds of man-hours as a result of this additional scope. SCI respectfully requests that a minimum of 21 calendar days be added to the contract performance. Though it could be argued that additional days can be substantiated, SCI is only seeking (at this time), uncompensated days that represent the 21 day difference in issue/execution dates for modification SCOO 1/0004 lH and modification 000404/SC003. This delay and inaction on the part of the Government delayed our ability to process a change order to the subcontractor, which subsequently delayed shop drawings, fabrication of materials and installation of the subject FE-25 system. As of this date, SCI still is waiting on the remaining required materials to be delivered for the FE-25 System. In summary, SCI is seeking 21 additional days to this contract.

(R4, tab 9 at 2)

4. The contracting officer's representative responded to Serial Letter H-0066 by email on 4 September 2013, stating that the Corps was considering the time extension if Speegle would confirm that there was no other cost involved with the time extension (R4, tab 10). Speegle responded that same day stating there were costs involved, but that it was waiving its rights "for extended overhead or other costs for this associated time request" (R4, tab 11 ).

5. The parties' entered into negotiations on 4 September 2013, in response to Speegle's 19 August 2013 proposal (R4, tab 12). The Corps' PNM associated with the negotiation, under ''DESCRIPTION OF CHANGE" states, "Request for adjustment for mod 00041H" and, "The purpose of this modification is to provide a complete equitable adjustment for any and all impacts, delays and costs associated with modification 00041H issued unilaterally on 7 December 2012" (id. ii 1). Under "NECESSITY FOR CHANGE" the PNM merely repeated the statement regarding purpose in paragraph 1 (id. ii 2). Paragraph 6, "TIME DISCUSSION," stated:

3 The Contractor sought an adjustment as a result of modification 00041H for the Fire Suppression System in serial letter H-0066, dated 19 August 2013, requesting 21 days additional contract time.

The Contractor's request for time adjustment in serial letter H-0066 and request for audit in serial letter H-0064 were not provided within the time limit prescribed in the Changes Clause; therefore, no time extension is warranted. However, there is mutual benefit in providing a 21-day time extension at no additional cost in order to reach a complete equitable adjustment for any and all impacts, delays, and costs associated with modification 00041H issued unilaterally on 7 December 2012. This time extension does not represent any additional cost but has the potential to reduce the extended field overhead costs associated with outstanding change order requests SCO 17 for Feeders and SC020 for Additional Duct Bank.

(Id. ~ 6) In conclusion the PNM summed up the negotiation by stating:

At the conclusion of negotiations, the contractor and government were in agreement on the time extension. The contractor stated that Speegle Construction, Inc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Bell Bci Co. v. United States
570 F.3d 1337 (Federal Circuit, 2009)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Ed. Zueblin, A.G. v. United States
44 Fed. Cl. 228 (Federal Claims, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
Speegle Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/speegle-construction-inc-asbca-2016.