Specialty Products, Inc. v. Demolition Services, Inc.

87 Va. Cir. 325, 2013 Va. Cir. LEXIS 93
CourtNorfolk County Circuit Court
DecidedDecember 12, 2013
DocketCase No. (Civil) CL 12-8830
StatusPublished

This text of 87 Va. Cir. 325 (Specialty Products, Inc. v. Demolition Services, Inc.) is published on Counsel Stack Legal Research, covering Norfolk County Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Specialty Products, Inc. v. Demolition Services, Inc., 87 Va. Cir. 325, 2013 Va. Cir. LEXIS 93 (Va. Super. Ct. 2013).

Opinion

By Judge Charles E. Poston

This action is before the Court upon the objection to venue and motion to transfer of the Defendant Demolition Services, Inc. Having considered the written submissions of counsel, the papers filed in this action, and the argument of counsel, the court finds that venue is permissible in the City of Norfolk and that the Defendant’s objection should be overruled and its motion denied.

Factual Background

The Defendant, Demolition Services, Inc. (“DSI”), is a sub-contractor for a Department of Defense construction project at Building 2803, Camp Peary, Virginia. Its scope of work there included the removal of an epoxy layer from the building’s existing concrete floor. In late October 2012, it telephoned the Plaintiff, Specialty Products, Inc. (“SPI”), to solicit a bid for that work. In the course of the ensuing negotiations, DSI allegedly represented to SPI that it had tested the surface and [326]*326determined that the epoxy coating was relatively thin and could be removed without difficulty by diamond grinding. In reliance on that representation, SPI offered to remove the epoxy layer for $30,000. DSI accepted this offer. DSI then forwarded a $15,000 mobilization payment to SPI.

SPI alleges that, when it started work it discovered that the epoxy coating was thicker than DSI originally led it to believe, that the epoxy coating was reinforced with a fiber mesh that DSI did not disclose, and that complete removal would require nearly three times as much edging work as DSI represented. SPI informed DSI that, due to these differing circumstances, its work would be more difficult and costly. Accordingly, SPI requested that DSI submit a change order through the prime contractor for commensurate additional compensation on its behalf. SPI claims that DSI agreed to do so and, in reliance on its expectation that DSI would secure the change order, it continued work for another month, removing 95% of the epoxy layer. On December 3, 2012, SPI again requested that DSI secure a change order to compensate it for its additional costs, but this time DSI refused. Considering this refusal a material breach of their contract, SPI left the work site with 5% of the epoxy layer still in place.

Procedural History

SPI brought the instant action in December 2012, alleging three counts: first, that DSI breached the parties’ contract by failing to submit change orders to the prime contractor on SPI’s behalf; second, that DSI was unjustly enriched by SPI’s substantial performance without payment; and, third, that DSI fraudulently induced SPI to enter the contract on adverse terms and to continue working under the mistaken belief that change orders would be forthcoming. In February 2013, DSI filed a motion styled “Defendant’s Demurrer and Objection to Venue,” in which it demurs to the unjust enrichment and fraud counts, and moves to transfer the action to Manassas, Virginia. The Court heard the parties’ arguments on the objection to venue and motion to transfer in a hearing on October 1, 2013. The Defendant’s demurrer will be addressed after a separate hearing.

Discussion

When a defendant objects to the plaintiff’s chosen venue, it bears the burden of proving that venue is improper. Hawthorne v. VanMarter, 279 Va. 566, 580, 692 S.E.2d 226, 235 (2010). In ruling on an objection to venue, the Court examines the record up to the time of filing to determine whether the case falls within either of the Commonwealth’s venue statutes. Id. The instant case includes both contract and tort claims, both of which fall under Virginia Code § 8.01-262’s procedures for determining “permissible venue” for “Category B” cases. The parties agree that, because no other provision of § 8.01-262 is sufficient to establish permissible [327]*327venue in the City of Norfolk, Paragraph Four of that section controls the question of whether venue is proper here. Paragraph Four provides that venue is proper “[wjhere the cause of action, or any part thereof, arose. “§ 8.01-262(4). Where a plaintiff alleges multiple causes of action, the Court may, in its discretion, retain the entire case if venue is proper for at least one claim. E.g., Wasson v. Engineering & Econ. Research, Inc., 20 Va. Cir. 133 (1990) (retaining a case in which venue was proper for two tort claims,butnotforthethreecontractclaims).Therefore,toprevailinitsobjection, DSI must show that no part of any of SPI’s causes of action arose in the City of Norfolk.

Because SPI stipulated to DSI’s argument that no part of its cause of action for unjust enrichment arose in the City of Norfolk, venue is improper here with respect to that claim. Because SPPs breach of contract claim arose either in Manassas or at Camp Peary, Norfolk is also an improper venue with respect to that claim. However, because the Court finds that a part of SPPs fraud cause of action arose in the City of Norfolk, DSPs objection to venue will be overruled.

A. Breach of Contract

Venue is not proper with respect to SPI’s breach of contract claim because no part of its cause of action for that count arose in the City of Norfolk. A cause of action for breach of contract arises both where the contract is formed and where it is breached. Big Seam Coal Corp. v. Atlantic Coast Line RR., 196 Va. 590, 593, 85 S.E.2d 239, 241 (1955). A contract is formed where the last act of its formation occurs, and, when oral negotiations are reduced to writing, this is where the writing is fully executed. Id. at 594, 85 S.E.2d at 242. A breach occurs where “that is not done which ought to have been done, or that is done which ought not to have been done.” Norfolk & W. Ry. v. Crull, 112 Va. 151, 70 S.E. 521, 522 (1911) (quoting Bank v. Lacombe, 84 N.Y. 367, 384, 38 Am. Rep. 518). Under the “to pay” doctrine, a party’s breach of its contractual obligation to pay the other occurs at the obligee’s principal place of business if the parties have not agreed upon another delivery location. Dean Steel Erectors v. Virginia Steel Erectors, 35 Va. Cir. 346 (1995); Village Auto Ctr. v. Apple Auto Glass & Mirror, Inc., 51 Va. Cir. 471 (2000).

In Big Seam Coal, the Virginia Supreme Court concluded that a contract, negotiated in the forum county but reduced to writing and executed elsewhere, was formed upon execution and so was not formed in the forum county. 196 Va. at 594, 85 S.E.2d at 242. Similarly, in Wasson, the court concluded that the parties’ contract was formed in Fairfax County because that is where the defendant accepted the plaintiff’s offer. 20 Va. Cir. at 133.

In Dean Steel, the plaintiff brought suit in its home county when the defendant allegedly failed to pay a sum of money pursuant to the parties’ oral agreement. 35 Va. Cir. at 346. The defendant objected to the plaintiff’s [328]*328choice of venue, arguing that the contract had been formed in another county and, if breached, had been breached there as well because the parties did not agree on a specific location for the defendant to deliver the money. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Abi-Najm v. Concord Condominium, LLC
699 S.E.2d 483 (Supreme Court of Virginia, 2010)
Hawthorne v. VanMarter
692 S.E.2d 226 (Supreme Court of Virginia, 2010)
DUNN CONST. CO. v. Cloney
682 S.E.2d 943 (Supreme Court of Virginia, 2009)
Richmond Metropolitan Authority v. McDevitt Street Bovis, Inc.
507 S.E.2d 344 (Supreme Court of Virginia, 1998)
Spiker v. Commonwealth
711 S.E.2d 228 (Court of Appeals of Virginia, 2011)
Faison v. Hudson
417 S.E.2d 302 (Supreme Court of Virginia, 1992)
Big Seam Coal Corp. v. Atlantic Coast Line Railroad
85 S.E.2d 239 (Supreme Court of Virginia, 1955)
Sensenbrenner v. Rust, Orling & Neale, Architects, Inc.
374 S.E.2d 55 (Supreme Court of Virginia, 1988)
Hibernia National Bank v. . Lacombe
84 N.Y. 367 (New York Court of Appeals, 1881)
Norfolk & Western Railway Co. v. Crull
70 S.E. 521 (Supreme Court of Virginia, 1911)
Deady Advertising, Inc. v. Foam Industries, Inc.
4 Va. Cir. 435 (Richmond County Circuit Court, 1977)
Wasson v. Engineering & Economics Research, Inc.
20 Va. Cir. 133 (Westmoreland County Circuit Court, 1990)
Dean Steel Erectors v. Virginia Steel Erectors
35 Va. Cir. 346 (Rockingham County Circuit Court, 1995)
Village Auto Center v. Apple Auto Glass & Mirror, Inc.
51 Va. Cir. 471 (Rockingham County Circuit Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
87 Va. Cir. 325, 2013 Va. Cir. LEXIS 93, Counsel Stack Legal Research, https://law.counselstack.com/opinion/specialty-products-inc-v-demolition-services-inc-vaccnorfolk-2013.