Specialty Minerals, Inc. v. Dunbar Mechanical, Inc.

164 F. App'x 539
CourtCourt of Appeals for the Sixth Circuit
DecidedDecember 6, 2005
Docket04-4376, 04-4377
StatusUnpublished
Cited by2 cases

This text of 164 F. App'x 539 (Specialty Minerals, Inc. v. Dunbar Mechanical, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Specialty Minerals, Inc. v. Dunbar Mechanical, Inc., 164 F. App'x 539 (6th Cir. 2005).

Opinion

OPINION

R. GUY COLE, Jr., Circuit Judge.

Defendant-Appellant and Cross-Appellee Dunbar Mechanical, Inc. (“Dunbar”) appeals the district court’s decision declaring invalid two affidavits Dunbar filed in support of mechanic’s liens, the court’s dismissal of Dunbar’s counterclaim for judgment on bonds substituted for the liens per Ohio law, and the court’s denial of Dunbar’s motion to bifurcate the proceedings. Plaintiff-Appellee and Cross-Appellant Specialty Minerals, Inc. (“SMI”) appeals the district court’s dismissal of its claim for slander of title against Dunbar. For the reasons that follow, we AFFIRM the decisions of the district court.

I.

This case arises from the implementation of a two-stage process to manufacture polymers, developed by SMI, whereby material is pelletized and heated.

SMI contracted with Triad Construction Services, Inc. (“Triad”) to install a pelletizing system in its Ohio plant (“contract 1”). Triad subcontracted with Dunbar (“subcontract 1A”) to perform this service. SMI entered into a second contract with LB & W Engineering, Inc. (“LB & W”) to install a kiln system (“contract 2”). LB & W subcontracted with Triad (“subcontract 2A”) who subcontracted again with Dunbar (“subcontract 2B”).

On December 14, 2000, SMI tested the pelletizing and kiln systems. Because of flaws in the SMI design, both systems had to be modified. SMI and LB & W bypassed a financially imperiled Triad and contracted directly with Dunbar to modify the two systems (“contracts 3 and 4”). SMI and LB & W paid Triad for the work on contracts 1 and 2. SMI and LB & W also substantially paid Dunbar for the work on contracts 3 and 4. Triad filed for bankruptcy, however, and failed to pay Dunbar a collective $240,904 on subcontracts 1A and 2B.

On March 22, 2001, Dunbar filed a pair of affidavits, thereby establishing two mechanic’s liens against SMI’s Ohio plant. SMI posted monetary bonds to remove the liens, pursuant to Ohio law. See O.R.C. § 1311.11(C). SMI brought this action requesting a declaratory judgment that Dunbar’s affidavits were not filed within 75 days of the last day of work performed on the site, as required by O.R.C. § 1311.06(B)(3). Moreover, SMI brought a claim for slander of title to property. Dunbar moved to bifurcate the proceed *541 ings and filed a counterclaim requesting summary judgment on the bonds posted by SMI in lieu of the liens. Following a bench trial, the district court held on summary judgment that the affidavits were untimely; the court held against the moving party on each other claim. This appeal and cross-appeal followed.

SMI is a Delaware corporation that conducts business principally in New York. LB & W is a Pennsylvania corporation that conducts business principally in that state. Dunbar is an Ohio corporation that conducts business exclusively in Ohio; its owner is an Ohio resident. Thus, the district court had jurisdiction in this diversity case pursuant to 28 U.S.C. § 1332. 28 U.S.C. § 1291 in turn grants us jurisdiction to hear this timely set of appeals.

II.

A. Dunbar’s Motion to Bifurcate the Proceedings

Federal Rule of Civil Procedure 42(b) states: “The court, in furtherance of expedition and economy, may order a separate trial of any claim.” In addition to speed and economy, the convenience of the parties and the avoidance of prejudice are important factors. See In re Beverly Hills Fire Litig., 695 F.2d 207, 216 (6th Cir. 1982). We review the denial of a motion to bifurcate for abuse of discretion, Yung v. Raymark Industries, Inc., 789 F.2d 397, 400 (6th Cir.1986), which exists only upon a “definite and firm conviction that the court below committed a clear error of judgment in the conclusion it reached upon a weighing of the relevant factors.” Taylor v. U.S. Parole Comm’n, 734 F.2d 1152, 1155 (6th Cir.1984).

The district court did not abuse its discretion. Contracts 1 and 2 involve the same parties and arise out of the same project. The two mechanic’s liens at issue attach to the same property. The court found that bifurcating the proceedings would not serve judicial economy, would have little effect on the convenience of the parties in such a short trial, and was unnecessary to avoid prejudice because there was no jury to confuse. In short, the court reasonably weighed the relevant factors. Accordingly, we affirm the district court’s denial of Dunbar’s motion to bifurcate.

B. The Timeliness of Dunbar’s Affidavits

Upon appeal from a bench trial, we review the district court’s findings of fact for clear error and its findings of law de novo. Pressman v. Franklin Nat’l Bank, 384 F.3d 182, 185 (6th Cir.2004). Athough we give substantial deference to the district court’s assessments of witness credibility, Fed. R. Crv. P. 52(a), we review a district court’s application of state law — which governs this diversity ease — de novo. Leavitt v. Jane L., 518 U.S. 137, 116 S.Ct. 2068, 135 L.Ed.2d 443 (1996); International Ins. Co. v. Stonewall Ins. Co., 86 F.3d 601, 604 (6th Cir.1996).

Under Ohio law, a contractor must file mechanic’s lien affidavits within 75 days of the last day of work it performed on the contract at issue. O.R.C. § 1311.06(B)(3); King, Gilbert & Warner v. Ship-Bldg. Co., 50 Ohio St. 320, 34 N.E. 436, 439 (1893). The last day of performance cannot be extended by “tacking together” labor performed on subsequent contracts. King, 34 N.E. at 439; Talco Capital Corp. v. State Underground Parking Comm., 41 Ohio App.2d 171, 324 N.E.2d 762, 769 (1974). Furthermore, unnecessary and unsolicited tinkering and repair do not extend the last day of performance. Walter v. Brothers, 42 Ohio App. 15, 181 N.E. 554, 555 (1932); Bohunek v. Smith, 36 Ohio App. 146, 172 N.E. 852, 854 (1930).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bac Home Loans Servicing LP v. Fall Oaks Farm LLC
848 F. Supp. 2d 818 (S.D. Ohio, 2012)
Guernsey Bank v. Milano Sports Enterprises, L.L.C.
894 N.E.2d 715 (Ohio Court of Appeals, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
164 F. App'x 539, Counsel Stack Legal Research, https://law.counselstack.com/opinion/specialty-minerals-inc-v-dunbar-mechanical-inc-ca6-2005.