Spaulding Manufacturing Co. v. City of Grinnell

136 N.W. 649, 155 Iowa 500
CourtSupreme Court of Iowa
DecidedJune 6, 1912
StatusPublished
Cited by4 cases

This text of 136 N.W. 649 (Spaulding Manufacturing Co. v. City of Grinnell) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Spaulding Manufacturing Co. v. City of Grinnell, 136 N.W. 649, 155 Iowa 500 (iowa 1912).

Opinion

Deemer, J.

The defendant city owns and operates a' [502]*502municipal waterworks system, and plaintiff, a large manufacturing concern has been one of its- patrons for many years. In April of the year 1910, the meter was read, and plaintiff was presented with a bill for the preceding six months amounting to $142.90. This was much larger than any previous bill for many years at least, and a controversy arose over the bill. A rough test was made of the meter and the- conclusion 'anrive'd at that it was one-tenth fast, and the bill was discounted ten percent. Thereafter ■another preliminary reading was made on July 2d, and this showed a large increase in the consumption of water, and the meter was again read on October 10, 1910, to secure the data for the November bill. This reading showed the sum of $618.95 due for water for practically two-quarters, or six months. This was an increase over the previous bill, and - another controversy arose. A new meter was installed, and the old one was again tested, and the conclusion was that it was running ten percent fast. The $618.95 bill was then reduced ten percent, or to $557.05, and payment thereof demanded from plaintiff. Instead of complying with the request, plaintiff tendered the sum of $53.25 in full payment of the account, which amount the city refused to accept. Plaintiff having refused to pay the city more than the amount tendered, the city ordered the water cut off, and was in the act of doing so when this action in equity was commenced, to restrain the ■defendants, its officers and agents, from cutting off the water. A temporary writ was issued and thereafter the city moved to dissolve the same; but its motion was denied. The case came on in regular order for trial at the regular February term of court, resulting in a decree dissolving the temporary writ of injunction and dismissing the petition. The court also found that the amount due from the plaintiff to the city was $557.05, but no judgment was rendered for the amount so found due.

[503]*503nection: in-^ junction: evidence. „ water^supp^ íent-adiscon-y [502]*502The questions presented on this . appeal are largely [503]*503of fact, and have to do primarily with the amount of water which the city supplied to the plaintiff- during the periods in controversy. The water was metered to the plaintiff, and for any leaks after the water passed the meter plaintiff is responsible. It is quite clear from the testimony that there must have been some leaks in plaintiff’s- system for at least a part of the time in question. Many things confirm this conclusion, and we think there is practically no dispute over the proposition. To what extent these leaks contributed to plaintiff’s loss and augmented the bills presented by the city it is difficult to say with any degree of accuracy. One fact stands out very prominently in the case. It is conceded that the amount of water actually consumed by plaintiff for the years 1908, 1909, and 1910 was practically the same for each year or for each six months of these years. But on account of a slow 'or defective meter, the meter readings grew constantly less from May, 1908, down to November 1, 1909, when the meter “went dead,” and the amount consumed during the six months from May to November, 1909, was estimated. A new meter was installed shortly after the old one failed, and when it was read preparatory to making-out the bill for May, 1910, the amount consumed immediately jumped up to $14-2.90, and with the presentation of the ball fon May -the controversy began.

That this matter may be fully understood, we here reproduce in tabulated form the results of the different readings from May 1, 1908, -down to and including November 1, 1910: (See next page.)

A glance at this table will indicate our thought. Back -of -the year 1908 we have no data; but it is apparent from the concessions made by counsel that the meter which was in place from May, 1908, -down to some time in November, 1910, was a slow one, and that it finally went dead. So that we have no reliable data [504]*504whereby to discover the exact amount of water consumed or passing through a perfect meter prior to the year 1910. It was conceded on oral argument, however, that the meter installed some time before July 1, 1910, was correct in its measurement, and that the amount of water consumed by plaintiff from July 1, 1910, the date of the intermediate reading down -to Octber- 10th of the same year, according to the table heretofore set out, is approximately correct. This amounted to 25,650 cubic feet, or approximately 192,425 gallons in about three months, which would make the actual amount of consumption less than from April to October, 1910. These figures are the nearest approach we have to anything like accurate meter readings. If this be correct, then it is apparent that the meters were at fault from the time the new one was installed, immediately after the one failed, during the period from May to November 1, 1909, down to July 1, 1910, or that there were leaks in plaintiff’s system of piping at some place after the water passed the meter. A new meter was installed just after the one was found dead at the time of the reading for November, 1909,' and this was the [505]*505meter which was read April 18, 1910. When the controversy arose over the bill presented for May, the matter was allowed to run until the last of June, when the meter was given the rough test 'hitherto indicated, and an intermediate reading was then made on July 1 or 2, 1910, which showed a consumption of. 248,820 gallons after April 18th of the same yean This led to an immediate overhauling of the piping in the factory. After this wa3 done, plaintiff wrote the city clerk as follows:

[504]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schultz v. Town of Lakeport
54 P.2d 1110 (California Supreme Court, 1936)
Bailey v. Interstate Power Co.
228 N.W. 644 (Supreme Court of Iowa, 1930)
City of Atlanta v. McJenkin
135 S.E. 498 (Supreme Court of Georgia, 1926)
Dodd v. City of Atlanta
113 S.E. 166 (Supreme Court of Georgia, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
136 N.W. 649, 155 Iowa 500, Counsel Stack Legal Research, https://law.counselstack.com/opinion/spaulding-manufacturing-co-v-city-of-grinnell-iowa-1912.