Southwestern Underground Supply & Environmental Services, Inc. v. Amerivac, Inc.

894 S.W.2d 15, 1994 WL 745068
CourtCourt of Appeals of Texas
DecidedDecember 15, 1994
DocketB14-93-00515-CV
StatusPublished
Cited by11 cases

This text of 894 S.W.2d 15 (Southwestern Underground Supply & Environmental Services, Inc. v. Amerivac, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southwestern Underground Supply & Environmental Services, Inc. v. Amerivac, Inc., 894 S.W.2d 15, 1994 WL 745068 (Tex. Ct. App. 1994).

Opinion

OPINION ON MOTIONS FOR REHEARING

ROBERTSON, Justice.

Both parties have filed motions for rehearing. Appellant contends we erred in holding it had not preserved error on its claim that the trial court erroneously permitted appel-lee recovery in quantum meruit Although we remain skeptical as to whether appellant’s claim of error was properly preserved, we will, nevertheless, address the point on its merits.

Appellee claims in its motion for rehearing that we erred in not entering judgment against the surety on the supersedeas bond. In overruling appellee’s motion, we point out that the record on appeal does not contain a supersedeas bond, nor is there any indication that such a bond was entered into. Accordingly, we withdraw our original opinion and substitute the following.

This is a quantum meruit case. The Ap-pellee, Amerivae, Inc. (Amerivac), successfully sued Southwestern Underground Supply and Environmental Services, Inc. (Southwestern) to recover compensation for ser *17 vices rendered. Appellant, Southwestern, complains on appeal of an illegal contract, insufficient evidence, and the failure of the trial court to award attorney’s fees on a successful counterclaim. We affirm.

Statement of Facts

Southwestern is in the business of cleaning underground sewer lines. In 1989, they entered into a joint venture with another firm in order to secure work from the City of Houston. Contracts were subsequently awarded by the City and work was begun in November of the same year. In October of 1990, Southwestern entered into a written contract with Amerivac whereby Amerivac, as a subcontractor, would provide services to Southwestern for the City contract.

Under the terms of the City contract, Southwestern did not receive payment from the City until the work was approved; this process normally taking between sixty to seventy days. However, Southwestern agreed to pay Amerivac when Amerivac completed its work, less ten percent retainage to be paid to Amerivac when Southwestern was paid by the City. In effect, by “quick paying” Amerivac prior to Southwestern receiving its payment from the city, Southwestern served to finance Amerivac’s operations. As was understood by both parties, Amerivac could not have continued operations without such financing.

Under their agreement, Southwestern could stop “quick paying” Amerivac if the latter failed to provide Southwestern with all of its available output. After discovering that Amerivac had breached the agreement by working for other contractors, Southwestern ceased “quick paying” and reverted to regular payment terms; paying Amerivac only when it was paid by the City. At this point, Southwestern was holding $42,000 in retainage.

The first agreement expired, and Southwestern urged Amerivac to enter into a second contract; this one allowing Southwestern to hold a twenty-five percent retainage instead of the original ten percent. There was evidence that Southwestern led Amerivac to believe that it would have to enter into the second contract in order to receive the $42,-000 retainage from work performed under the first agreement. The second contract also provided that Southwestern would revert to regular payment terms if Amerivac did not work exclusively for Southwestern. Amerivac, in need of the retained funds from the first contract, signed the second agreement on April 30, 1991. Southwestern subsequently “quick paid” Amerivac the $42,000 due under the first agreement.

Southwestern claims that Amerivac began breaching the second contract almost immediately by offering services to other general contractors and, within a few weeks, completely ceased working for Southwestern. Southwestern further alleges that it suffered substantial damages when it was required to seek other subcontractors to finish the work left uncompleted by Amerivac. At this point, Amerivac also owed Southwestern $2,233 on an open account.

Amerivac brought suit against Southwestern alleging breach of contract, fraud, and unlawful restraint of trade. Amerivac sought the retainage it had agreed would go unpaid if it breached the second agreement. Southwestern counterclaimed for recovery of the $2,233 on the open account. At the beginning of trial, the parties stipulated that the contract was void. Therefore, with the agreement of both parties, the trial court dismissed all claims and counterclaims based on the contract. Amerivac then proceeded to argue for recovery based on (1) quantum meruit to recover the retainage for work performed, and (2) fraud in connection with Southwestern inducing Amerivac to enter into the second contract. With regard to the fraud claim, Amerivac maintained that Southwestern promised to keep Amerivac fully occupied with work when, in fact, Southwestern did not have enough work to split among its subcontractors.

A judgment awarded Amerivac $34,123.73 actual damages in quantum meruit, $35,000 attorney’s fees, $3,160.30 taxable court costs, plus pre-judgment and post-judgment interest. Additionally, the jury found in favor of Amerivac on its fraud claim, but the trial court apparently granted Southwestern’s Motion for Judgment Notwithstanding the Verdict (JNOV); possibly reversing the fraud award and allowing Southwestern an offset *18 for $2,233 on an open account. However, we cannot state with certainty the grounds for the reduction of the jury award, as the JNOV is not included in the record.

Discussion

In their first point of error, Southwestern contends that the trial court erred in entering judgment for Amerivac on the theory of quantum, meruit. The essence of their argument is that, as a matter of law, no recovery was available either in law or in equity for services rendered under a contract which was void for illegality. We agree that the contract was likely illegal under Texas law since it contained an impermissible non-competition clause. See Free Enterprise and Antitrust Act of 1983, Tex.Bus. & Com.Code Ann. § 15.01 et seq. (Vernon 1987 & Supp. 1994). Additionally, numerous cases provide support for the proposition that if Amerivac voluntarily entered into an illegal contract, there would be no recovery allowed in equity. E.g. Jones v. Hanna, 264 S.W.2d 133 ((Tex.App.—Waco 1954, no writ) (no quantum meruit substitute for enforcement of illegal contract; parties cannot contract away their individual rights to the public’s detriment); Montgomery Ward & Co. v. Lusk, 52 S.W.2d 1110 (Tex.App.—Waco 1932, writ ref'd) (law intended to prohibit an act also prohibits contracts to perform the act; therefore, no enforcement of illegal contracts). Thus, if Amerivac did voluntarily enter into an illegal contract, they could not then recover on the contract; nor would they likely be allowed any recovery in equity. However, this suit is distinguishable from the eases cited in appellant’s brief on several grounds.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
894 S.W.2d 15, 1994 WL 745068, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southwestern-underground-supply-environmental-services-inc-v-amerivac-texapp-1994.