Southwestern Sheet Metal Works, Inc. v. C. H. Leavell & Co.

414 S.W.2d 723, 1967 Tex. App. LEXIS 2696
CourtCourt of Appeals of Texas
DecidedApril 5, 1967
Docket5811
StatusPublished
Cited by3 cases

This text of 414 S.W.2d 723 (Southwestern Sheet Metal Works, Inc. v. C. H. Leavell & Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southwestern Sheet Metal Works, Inc. v. C. H. Leavell & Co., 414 S.W.2d 723, 1967 Tex. App. LEXIS 2696 (Tex. Ct. App. 1967).

Opinion

OPINION

CLAYTON, Justice.

On March 21, 1963, C. H. Leavell & Company of El Paso, Texas, (herein known as *724 “Leavell”) entered into a contract with the United States Government, through the Army Corps of Engineers, for the construction of certain radar facilities at White Sands Missile Range in New Mexico known ns the “ZMAR” Facility or project. Lea-vell subcontracted the mechanical portion of the work to Brown-Olds Corporation (known herein as “Brown-Olds”) including the furnishing and installation of wave guide filters, for radio wave shielding. .Brown-Olds, in turn, subcontracted a portion of its work to Southwestern Sheet Metal Works, Inc. (known herein as “Southwestern”) including the furnishing and installation of the wave guide filters. Southwestern executed a purchase order agreement with the Filtron Company, Inc. (known herein as “Filtron”) for the manufacture and delivery of the filters within the prime contract completion schedule and according to plans and specifications for such filters included in the prime contract.

When the wave guide filters were received by Southwestern from Filtron and installed, several of the filters were alleged not to meet the attenuation requirements of the specifications and these filters were rejected by the Government. Southwestern informed Filtron of the rejection and a dispute arose as to the cause of the failure, with Filtron maintaining that these filters were damaged in the installation by Southwestern. In an attempt to correct the alleged deficient filters and prevent delay of the whole project, both Southwestern and Leavell made certain expenditures of time and money. Finally Filtron delivered supplemental filters, but the project was delayed from the original completion date of November IS, 1963 for installation and testing of the filters until on or about May 4, 1964. The entire project was to have heen completed by December 22, 1963 with a provision that a penalty of $1,000.00 per day would be exacted by the Government for a delayed completion. However, this penalty was not withheld by the Government in its final payment to Leavell, and the latter makes no claim for such damages in this suit.

However, Leavell withheld from Southwestern the amount it had expended in attempting to correct the filters, and Southwestern withheld such amount as it had expended for such purpose from the purchase price owing to Filtron. Filtron then brought this suit against Southwestern and Leavell for recovery of the balance of the purchase price, and Southwestern and Lea-vell filed counter-claims for their damages for the failure of the filters to meet specifications. Leavell also filed against Brown-Olds, which became a third-party defendant, and which filed a cross-action against Southwestern and Filtron.

In the trial a total of thirteen special issues were submitted to the jury, which special issues will not be dwelt upon individually except as necessary under the various points of error. The trial court entered judgment in the following terms: The defendants Leavell and Southwestern, and cross-defendant Brown-Olds having stipulated that should cross-defendant Brown-Olds be found to have breached its contract with Leavell, then Southwestern would be deemed to have breached its contract with Brown-Olds in the same particulars and to the same extent; and the court having granted plaintiff Filtron’s motion for directed verdict on defendant Leavell’s counter-claim against Filtron at the close of all evidence, and also having granted at such time Leavell’s motion for directed verdict against Filtron on its suit against Leavell, and based on the jury’s findings, the court entered judgment in favor of Filtron in the amount of $8,488.61 against Southwestern; in favor of Leavell against Brown-Olds on the former’s cross-action in the amount of $2,574.25 plus $1.00 as nominal damages plus attorney’s fees in the amount of $1,250.00; in favor of Brown-Olds against Southwestern on the former’s cross-action in the amount of $3,825.25; and since Leavell had withheld from Brown-Olds the sum of $2,574.25, and Brown-Olds in turn *725 withheld the same sum from Southwestern, the last-named was given credit for said .amount as against Leavell and Brown-Olds, so that the judgment in favor of Brown-Olds against Southwestern was reduced by $2,574.25. Filtron took nothing against Leavell, and Leavell took nothing on its counter-claim against Filtron. Leavell took nothing on its cross-action against Southwestern, and Southwestern took nothing on its cross-action against Leavell and Brown-Olds. Southwestern’s motion to disregard certain jury findings and for judgment N.O.V., and for new trial, were overruled, as were all motions for judgment on the verdict, from which this appeal is taken by Southwestern, Brown-Olds and Leavell.

The First Point of Error by appellant Southwestern complained of the trial court’s overruling Southwestern’s motion for new trial because the evidence presented at the hearing on such motion proved that harmful jury misconduct occurred as a matter of law. The alleged misconduct occurred principally in the jury’s answers to Special Issues 3, 4, and 11. Special Issue 3 inquired as to whether Filtron fabricated and delivered to Southwestern all the filters (not including supplementary filters) in accordance with the plans and specifications. The jury answered “No”. Issue 4 inquired what sum of money was reasonably expended by Southwestern in connection with the failure of Filtron to furnish filters meeting the plans specifications, if the jury found they did so fail, to which the jury answered $.00 (zero). Special Issue 11 inquired whether Southwestern orally agreed with Filtron that if Filtron would furnish supplementary filters, Southwestern would pay Filtron the sum of $8,580.32 and would install these filters at no expense to Fil-tron and waive any claim to damages because of the failure of some of the original filters to pass the frequency range test. The jury answered “yes” to this issue. There were attached to the motion for new trial the affidavits of six jurors, and four jurors were called by Southwestern and testified at the hearing on the motion, as well as two jurors called by Filtron.. It seems advisable to quote parts of the jurors’ testimony here. One, Alice L. Gereche, testified in part as follows:

“Q Was there any discussion during that time about the possibility of a hung jury or not?
A Yes, sir, there was. On the third question, there was a discussion. One of the jurors said that if we didn’t agree with him that he was going to hang the jury.
Q Okay. Do you remember whether or not most of the questions were answered before the last day or on the last day?
A Most of them were on the last day.
Q Were on the last day ? I hand you a copy of the questions that you had in the juryroom and ask you if you can remember whether or not Questions No. 3, 4, and 11 were answered on the last day or before the last day.
A They were answered the last day, right together.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Strange v. Treasure City
608 S.W.2d 604 (Texas Supreme Court, 1980)
Roming v. McDonald
514 S.W.2d 129 (Court of Appeals of Texas, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
414 S.W.2d 723, 1967 Tex. App. LEXIS 2696, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southwestern-sheet-metal-works-inc-v-c-h-leavell-co-texapp-1967.