Southwestern Portland Cement v. Beavers

478 P.2d 546, 82 N.M. 218
CourtNew Mexico Supreme Court
DecidedDecember 28, 1970
Docket9071
StatusPublished
Cited by10 cases

This text of 478 P.2d 546 (Southwestern Portland Cement v. Beavers) is published on Counsel Stack Legal Research, covering New Mexico Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southwestern Portland Cement v. Beavers, 478 P.2d 546, 82 N.M. 218 (N.M. 1970).

Opinion

OPINION

McKENNA, Justice.

Appellee Southwestern Portland Cement brought this suit to collect payment on an account in the amount of $1,647.00, plus costs and attorney fees, against appellants Beavers and Glasgow, doing business as Plains Sand and Gravel, and defendant Adams. Judgment was entered against all three jointly and severally for the sum sued for, plus costs and attorney fees of $549.31. Only Beavers and Glasgow appealed.

■In February of 1968, the appellants formed a partnership known as Plains Sand and Gravel to provide concrete for a construction project at Cannon Air Force Base. The general contractor for the project was Wilkerson-Webb. Defendant Adams had no proprietary interest in the partnership. In March, 1968, the partnership entered into an oral agreement with Adams to use his ready-mix concrete batching plant and delivery trucks to mix and deliver concrete to the project. The partnership made arrangements with appellee Southwestern to furnish bulk cement to Adams at his plant. The method of payment for the delivered concrete was for Wilkerson-Webb to issue their check payable jointly to Plains Sand and Gravel and to Southwestern.

On March 20, 1968, and again on April 30, 1968, Southwestern delivered cement to Adams’ plant for the partnership account. Adams received these deliveries at his plant and signed truck tickets for the cement on behalf of Plains Sand and Gravel for the Cannon Air Force job. These two deliveries of cement were paid for by Wilkerson-Webb’s joint check in the amount of $1,052.70.

On July 10, 13 and 16, Adams ordered cement from Southwestern telling it that the order was for Plains Sand and Gravel. Similarly, Adams received the three deliveries at his plant, signed truck tickets for receipt of the cement on behalf of Plains Sand and Gravel for the Cannon Air Force job.

It was established during trial that prior to the last three deliveries by Southwestern, Adams’ equipment broke down and he was unable to deliver the concrete to the job site and Plains Sand and Gravel made other arrangements with another firm to deliver the concrete. However, the appellants did not inform Southwestern of this prior to the last three deliveries. After the last of the three deliveries, Southwestern contacted Wilkerson-Webb to “confirm” the amount of concrete usage on the job and to “reconfirm” the guarantee of payment. It was then informed that only a negligible amount of concrete was supplied by Plains Sand and Gravel for the job, and Wilkerson-Webb refused to issue a joint check for the delivered cement. Thereupon, Southwestern called one of the appellant partners who denied that Adams had authority to order the cement.

Southwestern then sued Beavers, Glasgow and Adams for the last three loads delivered.

The testimony was conflicting as to whether Adams or one of the appellants placed the first two orders. Adams said he did; Beavers said his partner did. The court found that Adams placed the first two orders as well as the last three. This finding is of no consequence, however, because there is no finding that the first two calls were relied upon by appellee in any way.

The findings of fact pertinent to this appeal are:

“8. In March, 1968, Plains Sand & Gravel entered into a sub-contract to supply concrete on a construction project at Cannon Air Force Base, New Mexico, and then made an oral contract with Adams whereby Adams was to use his ready-mix concrete batching plant and delivery trucks to mix and deliver concrete on said project, with Plains Sand & Gravel furnishing the cement and aggregate. Plains Sand & Gravel made arrangements with plaintiff to furnish bulk cement to Adams for use on said project, and deliveries were made by plaintiff to Adams under this arrangement in March and April, 1968, and paid for by the prime contractor on the project in behalf of Plains Sand & Gravel.”

This finding was uncontested; the court, however, proceeded further and found:

“9. Plains Sand & Gravel authorized Adams to order cement from plaintiff for use on said project, and Adams ordered the cement which was delivered to him by plaintiff in March and April, 1968. Adams’ authority to so order cement was not cancelled until after July, 1968. This course of dealing gave Adams apparent authority to place other orders for cement from plaintiff on behalf of Plains Sand & Gravel.
<< ^ sfc
“11. On July 10 and 13, 1968, Adams ordered additional loads of bulk cement from plaintiff on the Plains Sand & Gravel account, without specific authority from Plains Sand & Gravel. * * * ”

The court concluded:

“2. Plains Sand & Gravel as principal is estopped to deny the authority of Adams as its agent to order the cement involved in this action, having clothed Adams with apparent authority to order same, and plaintiff having acted on said apparent authority in good faith and to its detriment.”

For reversal, the appellants argue that there was no substantial evidence to support the finding that Adams had apparent authority from the course of dealing to order the last three loads of cement and Southwestern was negligent by not inquiring into the scope of Adams’ authority and this negligence precluded appellee from any recovery. Although the trial court may have- given some weight to finding 9, even though there is no finding of any reliance by appellant on any orders from Adams, we do not find this fatal to its judgment if uncontcsted finding 8 is alone sufficient to uphold the judgment. Board of Education, School District 16, etc. v. Standhardt, 80 N.M. 543, 458 P.2d 795 (1969).

Obviously, the course of dealing was not lengthy, and was limited, in terms, of time span and deliveries, but this must be viewed in light of the limited business, relationship which was involved — it was for only one project at Cannon Air Force Base. It is equally obvious that the component acts in the course of dealing were identical and reflected a common pattern. See Ulen v. Knecttle, 50 Wyo. 94, 58 P.2d 446, 111 A.L.R. 565 (1936). Each of the deliveries made to Adams by Wilkerson-Webb was for the account of Plains Sand and Gravel for use on the particular project in accordance with the pre-arranged procedure. Each delivery was made to the same location; each was receipted for by Adams for the partnership. If Southwestern had not been paid for the first two loads, it would have been warned or alerted — at least the law would so view it (Malia v. Giles, 100 Utah 562, 114 P.2d 208 [1941]) — but having been paid for the first two loads by the very procedure agreed upon, Southwestern could reasonably construe this as ratification of the previous, course of business. We cannot say that under these circumstances Southwestern acted in bad faith or without reasonable prudence in delivering the last three shipments.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sparks Bros. Drilling Co. v. Texas Moran Exploration Co.
1991 OK 129 (Supreme Court of Oklahoma, 1991)
Superior Concrete Pumping, Inc. v. David Montoya Construction, Inc.
773 P.2d 346 (New Mexico Supreme Court, 1989)
Bozza v. General Adjustment Bureau
704 P.2d 454 (New Mexico Court of Appeals, 1985)
Vickers v. North American Land Developments, Inc.
607 P.2d 603 (New Mexico Supreme Court, 1980)
Hagel v. Buckingham Wood Products, Inc.
261 N.W.2d 869 (North Dakota Supreme Court, 1977)
Otis Engineering Corporation v. Grace
527 P.2d 322 (New Mexico Supreme Court, 1974)
Echols v. NC Ribble Company
511 P.2d 566 (New Mexico Court of Appeals, 1973)
Pribble v. Aetna Life Insurance Company
501 P.2d 255 (New Mexico Supreme Court, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
478 P.2d 546, 82 N.M. 218, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southwestern-portland-cement-v-beavers-nm-1970.