Southwestern Bell Telephone Company v. Webb

393 S.W.2d 117, 1965 Mo. App. LEXIS 612
CourtMissouri Court of Appeals
DecidedJune 15, 1965
Docket31958
StatusPublished
Cited by10 cases

This text of 393 S.W.2d 117 (Southwestern Bell Telephone Company v. Webb) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southwestern Bell Telephone Company v. Webb, 393 S.W.2d 117, 1965 Mo. App. LEXIS 612 (Mo. Ct. App. 1965).

Opinion

L. F. COTTEY, Special Judge.

Respondents are the owners of a tract of land platted, but not otherwise developed, as a residential subdivision of eighty-eight lots in the rapidly expanding Maxville community in Jefferson County. Appellant has acquired by condemnation an easement over a 1-rod wide strip along the entire southern boundary of the tract for the purpose of constructing an underground communication system “consisting of underground cables, wires, conduits, surface testing terminals, markers and other necessary appurtenances,” and for the purpose of entering thereon whenever necessary “to construct, operate, maintain, inspect, replace and remove” the paraphernalia comprising the system, and to keep “the surface and sub-surface of said strip” free from all obstructions that might interfere with its use. Promptly upon acquiring the right-of-way appellant buried on it, to a depth of forty inches, a cable consisting of 600 separately insulated copper wires, of such complexity that two man-days are required to splice it at any given point.

The evidence on the issue of consequential damages was to this effect: At a point about midway on the southern boundary of the subdivision respondents’ plans called for the construction of a sewer lagoon having a surface area of 1.42 acres, the minimum required by law for the service of eighty-eight family dwellings. The topography of the land is such that this is the only feasible location for it. Even so, as originally planned, it would have been necessary to excavate as far as practicable into an adjacent hillside, and to use a portion of the bed of a nearby creek, in order to obtain an adequate floor for the basin. The backslope of the lagoon dam would then have rested on the southern boundary line of the property. In addition, since the creek provides the drainage for the area, use of its bed would have required the concurrent excavation of a diversion channel *119 to take its place. Only in that manner could a lagoon of the required capacity be constructed. The diversion channel must be excavated to a depth below the 40-inch level at which the cable lies buried. That project, as well as the construction of the dam, requires the use of heavy machinery which, from its own weight or from the inattention of the operator, is likely to cause the cable to be damaged, and for that reason it would be imprudent to operate it on the right-of-way strip; as one witness put it, “I wouldn’t dare.” Accordingly, it has become necessary for respondents to revise their original plans so as to relocate the dam one rod back from the south property line (and apparently enough more to allow for a new method of diverting the surface drainage) thereby narrowing the lagoon and reducing its surface area to 1.16 acres, sufficient only for the service of eighty-three family units. The remaining five lots will, therefore, have to be supplied with septic tanks at a cost of $700-$750 each. This, in addition to the fact that the fronts of nine lots abutting the south property line are traversed by the right-of-way. Estimates of the overall damage to respondents’ property resulting from appellant’s appropriation and use of the easement ranged from $500 to $20,000. The jury settled on a figure of $3,500.

Appellant complains of the admission of all the evidence relating to those consequential damages. Its objections are premised on the proposition that in its original petition (and in an amendment which the court allowed on the eve of trial) it had entirely extinguished the necessity for any revision of respondents’ plans for developing their subdivision, and virtually every other prospect of damage to it, by inserting a number of “reservations” to respondents, the effect of which the trial court misunderstood, the benefit of which respondents rejected, and the value of which the jury ignored; all to the end that the verdict was unconscionably excessive. The reservations giving rise to these reproaches are as follows:

(a) That respondents might “freely use and enjoy their interests” in the strip condemned — “insofar as the exercise thereof does not endanger or interfere with the construction, operation and maintenance of said communication system, or create a hazard thereto”;

(b) That respondents might “cultivate and grow crops” on the condemned strip;

(c) That respondents might erect buildings thereon — “with the written consent of plaintiff”; and,

(d) That respondents might use the easement area “for the backslope of the lagoon dam * * * and * * * for a drainage channel for surface waters.” This latter concession is accompanied by the promise that “the Telephone Company shall bear any expense of adjusting or lowering its communication system so as to permit the construction of the drainage channel.”

We pause to notice, and to emphasize, the fact that in this case the pleading of the reservations was allowed; respondents’ motion to strike them for indefiniteness was overruled. Moreover, appellant was permitted to hypothesize a most optimistic appraisal of their extent and utility in the examination and cross-examination of every witness who testified on the issue of consequential damages. The same interpretation of their scope and nature was submitted to the jury by appellant’s Instruction P-2 which listed the reservations and told the jury to bear them in mind in assessing the damages to be awarded. In all those respects appellant could not have been more generously treated. On the face of the record, therefore, it seems hardly appropriate for appellant to argue that all of its “claims of error turn upon the proposition as to whether or not plaintiff had the right * * * to restrict defendants’ damages” by setting up the reservations. That right was freely accorded and fully exercised.

What appellant is actually contending for is: That the pleaded reservations were so definite in terms and so generous in scope as to eliminate the neces *120 sity for any change in respondents’ plans for construction of the sewer lagoon and diversion channel, and hence to preclude the allowance of any damages claimed on that score and, indeed, to foreclose all inquiry into that subject, as a matter of law. We cannot agree. In the first place, appellant did not ask to have the issue of consequential damages (or the objectionable aspects thereof) withdrawn from the jury’s consideration in the trial court; on the contrary, by Instruction P-2 it submitted the reservations to the jury in terms, admonished the jury to hear them in mind on the question of damages generally, and thereby invited the jury to treat as an issue of fact the very proposition that is now urged upon us as a question of law. Appellant must be held on this appeal to the theory on which it submitted the case in the court below. Johnson v. Duensing, Mo., 332 S.W.2d 950, 957. In the second place, although it is a question of law as to whether the pleaded reservations constitute a limitation of the taking to some degree, and hence reduce to some degree the damages to which the condemnee is entitled, nevertheless, if after the pleading of them there remains a reasonable doubt as to their extent and effect, that question must he submitted to the jury as a question of fact

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Lakewood v. Plain Dealer Publishing Co.
486 U.S. 750 (Supreme Court, 1988)
City of Perryville v. Stark
715 S.W.2d 268 (Missouri Court of Appeals, 1986)
Loretto v. Teleprompter Manhattan CATV Corp.
458 U.S. 419 (Supreme Court, 1982)
Missouri Public Service Co. v. Allied Manufacturers, Inc.
574 S.W.2d 509 (Missouri Court of Appeals, 1978)
Southwestern Bell Telephone Co. v. Roussin
534 S.W.2d 273 (Missouri Court of Appeals, 1976)
Jenkins v. Andrews
526 S.W.2d 369 (Missouri Court of Appeals, 1975)
Shelton v. M & a Electric Power Cooperative
451 S.W.2d 375 (Missouri Court of Appeals, 1970)
Southwestern Bell Telephone Co. v. Kroupa
403 S.W.2d 931 (Missouri Court of Appeals, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
393 S.W.2d 117, 1965 Mo. App. LEXIS 612, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southwestern-bell-telephone-company-v-webb-moctapp-1965.