Southwestern Bell Telephone Co. v. City of Fayetteville

609 S.W.2d 914, 271 Ark. 630, 1980 Ark. LEXIS 1727
CourtSupreme Court of Arkansas
DecidedDecember 22, 1980
Docket80-176
StatusPublished
Cited by7 cases

This text of 609 S.W.2d 914 (Southwestern Bell Telephone Co. v. City of Fayetteville) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southwestern Bell Telephone Co. v. City of Fayetteville, 609 S.W.2d 914, 271 Ark. 630, 1980 Ark. LEXIS 1727 (Ark. 1980).

Opinions

Fi. William Allen, Special Chief Justice.

After several years of planning and effort, appellee City of Fayetteville (City) by agreement with the Arkansas State Highway Department acquired sufficient federal funds to proceed with a project to extend and widen North Street in order to straighten the nearby intersection of Arkansas Highways 112 and 16 West. The project required a number of telephone poles and gas meters of appellants Southwestern Bell Telephone Company (SWB) and Arkansas Western Gas Company (AWG) to be relocated from their positions in the existing North Street right-of-way. Some of SWB’s poles were relocated within the existing right-of-way and some within the new right-of-way acquired for the project. All of the affected AWG meters were moved to locations within the new right-of-way.

The City brought an action seeking a declaratory judgment that SWB and AWG were liable for the costs of relocating their facilities. To expedite construction SWB and AWG agreed to relocate the facilities, preserving for determination by the courts the issue of whether the City or they are liable for relocation costs. The parties stipulated the facts and filed cross-motions for summary judgment. On February 6, 1980 the Washington County Chancery Court entered a decree declaring SWB and AWG liable for their relocation costs. It is from this decree that SWB and AWG appeal.

All the parties and the chancellor cite and rely upon three previous decisions of the court. They are: Ark. Stat. Hy. Comsn. v. Ark. Pow. and Light Co., 231 Ark. 307, 330 S.W. 2d 77 (1960); Ark. State Hy. Cmsn. v. Ark. Pow. and Light Co., 235 Ark. 277, 359 S.W. 2d 441 (1962); and City of Little Rock v. Ark. La. Gas Co., 261 Ark. 347, 548 S.W. 2d 133 (1977). In each case the utility was awarded its relocation costs.

In the I960 AP&L case we held that when a State Highway Commission project required the removal of power company poles entirely from the right-of-way it occupied in the City of El Dorado, Arkansas, the utility had been ousted from its property right and was entitled to recover its relocation costs from the Commission. The opinion in this case contained the following dicta which is relied upon by appellee here:

“Hence, if the city or county should change the right-of-way of a public street or road, or widen it, or relocate it, the Company could be required to change its poles and wires without compensation so as not to ‘unnecessarily and unreasonably impair or obstruct’ the street. But here it is not a question of requiring the Power Company to relocate its poles so as not to unnecessarily or unreasonably impair or obstruct the traffic. The Commission has demanded that the Company remove its facilities entirely from the right-of-way.” 359 S.W. 2d 441 at 442.

In the 1962 AP&L case the power company’s poles were located on right-of-way easements of two streets within the city of North Little Rock, Arkansas. The Commission subsequently engaged in the construction of an interstate highway which crossed these two streets and required the relocation of the affected poles further back on the existing right-of-way easements but outside of the new right-of-way acquired by the project. Because the poles were merely moved from locations on the existing right-of-way to other locations on the same right-of-way the Commission argued that the quoted language from the I960 case applied and the utilities should bear the cost of removal. However, the Court held that the right-of-way referred to in the quoted portion of the I960 AP&L case was not the existing right-of-way but the new right-of-way. Because the project removed and excluded the poles from the new right-of-way, the court ruled an ouster had occurred and the Commission was-required to reimburse the utility’s cost.

At this stage of the development of the cases, it might well have been assumed that the quoted dicta in the 1960 case still had substantial viability and would apply in situations where removal of utility facilities was within a street project’s newly created right-of-way. However, in the 1977 case of City of Little Rock v. Ark. La. Gas, supra, the Court rejected, at least by implication, any prospect of affording a different treatment to relocations of utility facilities depending upon whether the facilities were moved to points inside or outside a new right-of-way. The Arkla case dealt with a street improvement project where only the existing right-of-way was involved. The gas company, in the face of certain federal highway commission requirements, chose to remove its gas line from under the pavement or the street and relocate it along the side of the street, still within the existing right-of-way. The federal requirements included a prohibition against cutting the pavement for installing service connections for a period of five years and a restriction on Aridas use of its manholes to the hours between 8 p.m. and 6 a.m. This court found that the relocation to the side of the street was compelled by the limiting conditions placed on Arkla and that the requirements amounted to an ouster requiring compensation to the utility.

After reviewing these three cases, the chancellor below justified the conclusion that the utilities must bear their own relocation costs on the basis that, unlike the previous cases, there was no showing here:

“. . . That SWB or AWG had been ousted from easement rights altogether nor have any limiting conditions been placed on either in respect of access to, maintenance of or delivery of service from, their respective lines as relocated.”

We do not believe the case here can be distinguished from the Arkla case on the basis that in the latter limiting conditions were imposed and that no such conditions were imposed here. In this case the utilities were instructed to move their facilities outright — an even more drastic action than indirectly requiring their removal by imposing restrictions on access. We cannot affirm the lower court without overruling the Arkla case which we decline to do. Even if we were inclined to overrule the Arkla case, we could not condone a holding that reimbursement of a utility depends on whether it is directed to remove its facilities inside or outside of a new right-of-way. It is undoubtedly removal itself which causes the utility its primary harm in most cases, rather than the position of the relocation (assuming that the new location is in the near vicinity of the old location). It would be unfair to have a rule which would allow a municipality to gerrymander a new right-of-way in such a manner as to avoid reimbursing a utility.

We recognize the evolution of our decisions has departed to a substantial extent from the dicta of the I960 AP&L case relied upon by appellee. We further recognize that this case and the Arkla case depart from the general common law rule that a utility bear its own relocation costs when the changes are required by public necessity. McQuillin on Municipal Corporations, Third Ed. (1970) (Rev. Vol.) Vol. 12, Sec. 34, 74a (p. 183). However, the treatise does recognize exceptions to the general rule and that it may be changed by contract or legislation.

It is admitted by appellee that this project was constructed under the federal-aid urban system program and that if reimbursement is permissible under state law, the federal government will pay 70% of the reimbursement costs in issue.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Qwest Corp. v. City of Chandler
217 P.3d 424 (Court of Appeals of Arizona, 2009)
Craighead Electric Cooperative Corp. v. Craighead County
98 S.W.3d 414 (Supreme Court of Arkansas, 2003)
Opinion No.
Arkansas Attorney General Reports, 1999
City of Little Rock v. AT&T COMMUNICATIONS OF SOUTHWEST, INC.
888 S.W.2d 290 (Supreme Court of Arkansas, 1994)
AT&T Communications of Southwest, Inc. v. City of Little Rock
866 S.W.2d 414 (Court of Appeals of Arkansas, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
609 S.W.2d 914, 271 Ark. 630, 1980 Ark. LEXIS 1727, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southwestern-bell-telephone-co-v-city-of-fayetteville-ark-1980.