Southwestern Bell Telephone Co. v. Ahrens Contracting, Inc.

366 S.W.3d 602, 2012 WL 1231791, 2012 Mo. App. LEXIS 480
CourtMissouri Court of Appeals
DecidedApril 10, 2012
DocketED 96415
StatusPublished
Cited by6 cases

This text of 366 S.W.3d 602 (Southwestern Bell Telephone Co. v. Ahrens Contracting, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southwestern Bell Telephone Co. v. Ahrens Contracting, Inc., 366 S.W.3d 602, 2012 WL 1231791, 2012 Mo. App. LEXIS 480 (Mo. Ct. App. 2012).

Opinion

PATRICIA L. COHEN, Judge.

Introduction

Ahrens Contracting, Inc. (Defendant) appeals the judgment of the Associate Division of the Circuit Court of the City of St. Louis in favor of Southwestern Bell Telephone Co., d/b/a AT & T Missouri (Plaintiff). Defendant claims that the trial court erred in overruling Defendant’s motion for a directed verdict because Plaintiff failed to prove a prima facie case of negligence under the Underground Facility Safety and Damage Prevention Act (the “Act”). We affirm.

Background

On June 22, 2005, Plaintiff suffered damage to its underground telephone cable located near the intersection of Hampton and Chippewa in the City of St. Louis. Plaintiff dispatched multiple service technicians to the site, where a Target store was under construction. Upon arriving at the scene, Ricky L. James, Jr., a customer service technician for Plaintiff, observed Plaintiffs damaged cable “sticking out of the ground.” James and other technicians photographed the damage site.

James’s supervisor, Pat Roberts, was also notified about the damage. Roberts contacted SM & P Utilities (SM & P) and requested that it send a Certified Damage Investigator to the scene to investigate and prepare a report about the damaged telephone cable. SM & P dispatched Bob Sehardin. Schardin took a series of eight photographs and wrote a “fact-based investigation report.” Schardin’s report stated that the general contractor for the Target store construction site was S.M. Wilson. The report concluded that the underground cable “may have been damaged by [Defendant] while grading.”

Plaintiff sued S.M. Wilson for the damage to Plaintiffs cable, but S.M. Wilson denied that it performed the type of work that could have caused the damage. S.M. Wilson provided Plaintiff with the daily time log for the work occurring at the construction site on June 22, 2005. This time log revealed that Defendant, a subcontractor, had performed work removing sidewalks near the “front lot” of the construction site on that date. Plaintiff dismissed its suit against S.M. Wilson and filed suit against Defendant for negligent damage to Plaintiffs property in violation of the Underground Facility Safety and Damage Prevention Act. 1 On January 13, *605 2011, the parties tried the case to the Associate Division of the Circuit Court of St. Louis County without a jury.

Plaintiffs first witness, James, testified that, when he arrived at the scene, he “saw [Plaintiffs] cable was damaged and [there was] some digging going on around it.” Plaintiffs counsel showed James a picture of the damaged cable, and James stated: “That’s our — that’s our pulp cable damaged.” He further explained: “[T]he copper is wrapped in plastic and then covered in a poly coating on the outside, with a turn plate, a metal turn plate on the inside to keep it from — protected.”

David Ross, an employee of SM & P Utilities, 2 also testified for Plaintiff. Ross stated that SM & P was the “underground locating company” for Plaintiff. As the underground locating company, SM & P “answer[ed] locate requests generated by Missouri One Call 3 to locate the approximate location of underground facilities for excavation purposes.” Ross testified that, at Plaintiffs request, he searched SM & P’s database to determine whether Defendant or S.M. Wilson had sought a “locate request” for the area of the damage. Ross clarified that SM & P’s database was linked to the Missouri One Call notification system. He confirmed that neither Defendant nor S.M. Wilson had sought a locate request for the area of the damage for sixty to ninety days prior to June 22, 2005.

Finally, Jon Becker, a Senior Risk Specialist for Plaintiff, testified as a corporate representative and non-retained expert. Becker testified that he worked for Plaintiff for over thirty-two years and that his “whole career [had] been in installation, repair, [and] maintenance” of Plaintiffs cable. Becker also testified that his job duties included determining fault for damage to underground cable. According to Becker, he reviewed the fact-based investigation report, the S.M. Wilson daily log, and the photographs taken by both Plaintiff and SM & P. Based on his review, Becker testified that the evidence indicated “somebody was digging at the front of ... Hampton and Chippewa, at the sidewalks.” Plaintiffs counsel showed Becker a photograph of the damaged cable, and Becker testified that: “[The photograph] depicts a lead sheath cable, 600 pair, and if you can see, the paper is like a pink, and that’s what the — our copper cable is wrapped in.” Becker further testified that a “heavy piece of equipment” had caused the damage while “ripping sidewalks out and grading.” Becker elaborated: “It had to be something large with a bucket that was pulling.”

At the close of Plaintiffs evidence, Defendant moved for a directed verdict. The trial court overruled Defendant’s motion.

Defendant’s sole witness was Richard Politte, its supervisor at the construction site during June 2005. Politte testified that Defendant was “removing sidewalks and grading” on June 22, 2005, but stated that it was not doing work in the area where the damage occurred. On cross-examination, Politte admitted that Defendant had been using a “high lift, two Bob *606 cats, and a backhoe with a breaker” while doing its work. Politte explained that a “high lift” was a machine with tank-style tracks and a scoop on the front. Politte acknowledged that the high lift Defendant used was capable of severing a telephone cable. On cross-examination, Plaintiffs counsel showed Politte a photograph of the damage site taken on June 22, 2005. Pol-itte admitted that a backhoe belonging to Defendant was positioned right next to the site of the damage in the photograph. Politte testified that Defendant used the backhoe on June 22, 2005 to “[c]arry[] material from the front of the building, across the sidewalk and down Chippewa,” but denied that it was used on that date to excavate in the area where the damage occurred.

The trial court took the matter under submission. On January 14, 2011, the trial court issued a judgment against the Defendant in the amount of $13,177.98. This appeal followed.

Standard of Review

Defendant contends that the trial court erred in overruling its motion for a directed verdict. However, because the parties tried this case to the court, and not to a jury, there was no verdict for the court to direct. Bogart v. Dir. of Revenue, 185 S.W.3d 286, 287 (Mo.App. W.D.2006). We consider a motion for a “directed verdict” in a court-tried case to be a motion for a judgment on the merits pursuant to Rule 73.01(b). 4 See id. We review the trial court’s determination of a Rule 73.01(b) motion under the standards set forth in Murphy v. Carron, 536 S.W.2d 30, 32 (Mo. banc 1976). Nautilus Ins. Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Richard D. Schaffer v. Mickey J. Howard
Missouri Court of Appeals, 2021
In re 8760 Serv. Grp., LLC
586 B.R. 44 (W.D. Missouri, 2018)
Union Electric Company D/B/A Ameren Missouri v. A.P. Read Homes, LLC
485 S.W.3d 773 (Missouri Court of Appeals, 2016)
Bank of America, N.A. v. Duff
422 S.W.3d 515 (Missouri Court of Appeals, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
366 S.W.3d 602, 2012 WL 1231791, 2012 Mo. App. LEXIS 480, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southwestern-bell-telephone-co-v-ahrens-contracting-inc-moctapp-2012.