Southside Utilities, Inc. v. Abante Corp.

54 Va. Cir. 288, 2000 Va. Cir. LEXIS 598
CourtNorfolk County Circuit Court
DecidedDecember 21, 2000
DocketCase No. (Law) L99-2869
StatusPublished

This text of 54 Va. Cir. 288 (Southside Utilities, Inc. v. Abante Corp.) is published on Counsel Stack Legal Research, covering Norfolk County Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southside Utilities, Inc. v. Abante Corp., 54 Va. Cir. 288, 2000 Va. Cir. LEXIS 598 (Va. Super. Ct. 2000).

Opinion

By Judge Marc Jacobson

In December 1996, Defendant Abante Corporation entered into a contract with the Commonwealth of Virginia to perform certain work at Norfolk State University in the City of Norfolk, Virginia (Project). Pursuant to Va. Code § 11-58, Abante was required to post a payment bond (Bond) in order to protect materialmen in the event of default on the Project. In December 1996, Abante did post the required Bond and on or about December 27, 1996, Abante entered into a subcontract with Plaintiff Southside Utilities, Inc., for certain work on the Project. Abante terminated its subcontract with Plaintiff in July 1997, and Plaintiff filed suit against Abante and Seaboard Surety Company, die maker and provider of the Bond, on or about May 15,1998, in die Circuit Court of the City of Norfolk, alleging tíiat Abante failed to pay for work performed. By Order entered by the Circuit Court of the City of Norfolk on December 9,1999, Plaintiff suffered a voluntary nonsuit Plaintiff filed the instant action on December 6,1999, approximately two and one half years after last performing work on the Project.

On September 14,2000, Abante and Seaboard (sometimes jointly referred to as Defendants) died a Motion to Dismiss Motion for Judgment of Southside Utilities, Inc. (Motion to Dismiss), alleging as follows:

[289]*2891. The payment bond (the “Bond”) upon which the Plaintiff bases its suit contains a provision that “[n]o suit or action shall be commenced hereunder by any claimant___[ujnless brought within one year after the day on which the person bringing such action last performed labor or last furnished or supplied materials.”
2. As a claimant (defined in the Bond as one having a direct contract with Abante) under the Bond, Southside is subject to this contractual one-year limitations period.
3. Southside initially filed suit against the defendants on May 15, 1998, in the Circuit Court for the City of Norfolk (the “Initial Action”).
4. The last work performed on or materials supplied to the project at Norfolk State University (the “Project”) by Southside occurred prior to the filing of the Initial Action.
5. Southside requested and was granted a nonsuit of the Initial Action on December 9,1999.
6. Southside filed the action presently before the Court on December 6, 1999, more than one year after the last labor was performed on or materials were supplied to the Project.
7. The filing by Southside of the Initial Action within the one-year limitations period did not toll the contractual limitations period. Massie v. Blue Cross and Blue Shield of Virginia, 256 Va. 161 (1998).

The issue before this Court is whether the filing of the initial Motion for Judgment by Plaintiff on May 15, 1998, in the Circuit Court of the City of Norfolk tolled the statute of limitations relative to Va. Code § 11-58 as to Paragraph 11 set forth in the Payment Bond1 and, whether the provisions of Va. Code § 8.01-229(EX3)2 permit or allow Plaintiff six months from [290]*290December 9,1999, the date of entry of the aforementioned Nonsuit Order to recommence its action.

Defendants contend that there was a contractual period of limitation contained in the surety bond between Abante and Seaboard (See Paragraph 11 of Va. Code § 11-58) and that Va Code § 8.01-229(EX3) does not operate to toll that contractual limitation. See Defendant’s Memorandum in Support of Motion to Dismiss (Defendant’s Memorandum) at 7. Because Plaintiff is suing to recover under the Payment Bond, Defendants contend that Plaintiff* s action is subject to the contractual limitation set forth in the Payment Bond because Plaintiff is a third party beneficiary thereof. See id.

In support of this position, Defendant relies heavily upon Massie v. Blue Cross and Blue Shield of Virginia, 256 Va. 161, 500 S.E.2d 509 (1998), for the proposition that parties are free to contract around statutoiy periods of limitation. In Massie, the Court concluded that a “contractual” period of limitations was not subject to the tolling statute found in Va. Code § 8.01-229(EX3). See id. at 165, 500 S.E.2d at 511. Using the plain language of the Code, the Court found that the tolling provision referred only to “statutes” of limitations, as opposed to “contractual” limitations. See id.

However, in the context of Va. Code § 11-60 the contractual period of limitation does not apply to the instant case and Plaintiff is not bound by it. Virginia Code § 11 -60(c)3 provides a one-year statute of limitations for a claim against a surety bond in the context of construction on public property. The Virginia Supreme Court has ruled that statutes of limitations in actions on public construction bonds are prohibitoiy and cannot be abrogated or changed by contract. In Joseph F. Hughes & Co. v. George H. Robinson Corp., 211 Va. 4, 175 S.E.2d 413 (1970), the bond in question provided a different period of limitations than did the applicable statute.4 See id. The Court held that the [291]*291contractual provision did not apply, because the language of the applicable code section, Va. Code § 11-23 (a precursor to Va. Code § 11-60), indicated that the provision was intended to be “prohibitory of any other limitation.” See id. at 6. The Court specifically held that “the statutory language controls the time for bringing an action on tire bond.” See id. Because of this mandate, and because “the bond contained a provision amending its own limitation to conform to the statutory minimum if its own limitation is prohibited,” the Court reasoned that the statutory limitation was incorporated into the bond itself. See id. Therefore, the statutory provision controlled, and the contractual provision was stricken. See id.

The case at bar is similar to the facts of Hughes. In Hughes, the Court noted that Va. Code § 11-23 stated “no action on any bond required herein shall be brought unless within one year....” See id. at 6. The current Va. Code § 11-60 provides that “Any action on a payment bond must be brought within one year....” See Va. Code § 11-60. In Hughes, the Court noted that the language “no action ... shall” indicated a prohibition, see Hughes at 6. The language in die current statute “Any action... must,” see Va Code §11-60, has not changed enough to warrant a different analysis from that used in Hughes. The bond in question here also contained an amendatory provision providing that “if any limitation embodied in this bond is prohibited by law controlling the construction hereof, the limitation embodied within this bond shall be deemed to be amended so as to be equal to the minimum period permitted by such law.” See Defendant’s Brief at 5. This is the same amendatory provision as in Hughes, wherein the court substituted the statutory provision for the contractual one within the bond. See Hughes at 6. Because Va.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Massie v. BLUE CROSS & BLUE SHIELD OF VA
500 S.E.2d 509 (Supreme Court of Virginia, 1998)
Dodson v. Potomac MacK Sales & Service, Inc.
400 S.E.2d 178 (Supreme Court of Virginia, 1991)
Joseph F. Hughes & Co. v. George H. Robinson Corp.
175 S.E.2d 413 (Supreme Court of Virginia, 1970)
Commercial Const. v. Acm Const.
405 S.E.2d 852 (Supreme Court of Virginia, 1991)
Virginia National Bank v. Harris
257 S.E.2d 867 (Supreme Court of Virginia, 1979)
Massie v. Blue Cross & Blue Shield
500 S.E.2d 509 (Supreme Court of Virginia, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
54 Va. Cir. 288, 2000 Va. Cir. LEXIS 598, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southside-utilities-inc-v-abante-corp-vaccnorfolk-2000.