Southern Transp. Co. v. Unkel

236 F. 779, 1916 U.S. Dist. LEXIS 1322
CourtDistrict Court, E.D. Pennsylvania
DecidedNovember 1, 1916
DocketNo. 26
StatusPublished
Cited by6 cases

This text of 236 F. 779 (Southern Transp. Co. v. Unkel) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Transp. Co. v. Unkel, 236 F. 779, 1916 U.S. Dist. LEXIS 1322 (E.D. Pa. 1916).

Opinion

DICKINSON, District Judge.

This controversy had its beginnings in two charter parties entered into, one on November 13, 1914, for the charter of the barge Pamunky; the other on December 12, 1914, for the charter of the barge Wicomico. The barges were to carry lumber from Acquia Creek, Va., to Philadelphia. The place of shipment in the first charter party is given as Quantico, and in the other as Cole Randing. The pertinent provisions of the contracts will be stated in connection with the points raised.

The claim of the libel is for demurrage, dead freight, and towage. The issues as raised by the pleadings, supported by the evidence and discussed by counsel, can be best presented by treating each barge as a claimant, and considering the claims of each separately. The-claim of the Pamunky, as set forth in the libel, is this:

The contract was that the respondent should “load and stow” the lumber on the barge. The “lay days,” or days allowed for loading, should “commence from the time the captain reports his barge ready to receive cargo.” Ten of such lay days were allowed the charterer, but .Sundays and legal holidays were to be excluded from the count, and also days on which the charterer was “prevented from working the major portion of the day by rain.” The vessel was to be paid $2.25 per M. for carrying the lumber and $15 per day “for each and every day’s detention by default” of the charterer. The claim is for $52.50 for such demurrage. The barge is averred to have been reported by her master ready to receive cargo at 12 o’clock noon November 18, 1914, and that her loading was not completed until 2:40 p. m. December 4, 1914, whereby a demurrage charge for 3% days had accrued to the vessel.

The answer sets up some defenses not necessary to consider. The sufficient one is the averment of the loading having-been completed on December 1, 1914, and within the 10 lay days allowed by the charter party. It will perhaps contribute to the clarity of the discussion if the position of the litigants is stated and then the facts found from the evidence. If the vessel was in fáct loaded by noon of December 1st, the days would, on the vessel’s own count, be just 10. The libel-ant claims, however, this half day and additional days for December 2d, 3d, and 4th, making the total count of 3% days. The merit of the claim turns upon when the loading of the boat was completed.

The real defense is that the loading was done by December 1st, so that the boat was free to sail within the 10 days allowed for loading. The fact would clearly seem to be, and is so found, so far as the charterer was concerned, that the loading was so completed. Mr. Wallace had some lumber of his own, not sold to the charterer, which he desired to ship to Philadelphia, on the venture that Mr. Unkel might be persuaded to buy it, and that, if he did not, some one else would. There was not much of it, either in quantity or value. The captain agreed that it might be put aboard and carried on the accotmt of Mr. Wallace, if put aboard before the vessel was ready to sail. There was [781]*781good judgment in his doing so, and therefore nothing improbable in the statement that he had so done. He could safely take it and thereby earn additional freight. The putting of it aboard involved no delay. The agent of the charterer could have no valid objections, if it was understood that it was not loaded on his account, nor' made the subject of a demurrage charge. At all events, under this view of the facts, there was “no detention” of the vessel due to the “default” of the charterer.

The testimony of the captain is not inconsistent with this version. He admits he had planned to take his boat away on December 1st. He admits he said he would sail as soon as the tug arrived, whether all of the lumber was then aboard or not. He does not deny that the quantity of lumber put aboard after December 1st was small and of little value. All that he denies is that he expressed any opinion as to when the lay days expired. In view of the attitude of his employers when his testimony was given, this is not surprising. Under the finding of fact made, the libel as to this item of claim should be dismissed. The question of when the lay days began to run is eliminated by the finding of facts.

Presenting, in like manner, the claim made on behalf of the Wicom-ico, we have first a similar claim for demurrage at Cole Landing, the port of loading. The provisions of the charter party are the same, except that the lay days are reduced to 7. The pertinent averments of the libel are these: The captain reported the vessel ready to receive cargo at 11:30 a. m. December 18, 1914. The loading was completed January 11, 1915. The elapsed time, excluding the excepted days, was 10 days. A demurrage claim of $45 for the 3 days’ excess is in consequence made.

The answer again sets up a defense not necessary to consider. It further claims that on the demurrage days the charterer was prevented from loading by unusual and exceptionally severe weather conditions, which should excuse him of default. The tabulations made by counsel of the days of loading relieve the case of all questions except the one of weather conditions, other than the one stipulated in the contract, excusing the detention of the vessel. The libel claims only 3 days’ delay. The days other than the first, and other than Sundays, holidays, and rainy days, exceed the demurrage demanded. If the excuse advanced is a valid one, the detention is brought easily within the number of lay days allowed. This, then, is the only question arising out of this branch of the case.

There is no dispute over the facts. The weather conditions were severe. They are found to he unusual in the sense in which we speak of unusually cold weather. They were not, however, unusual in the sense of being extraordinary, or beyond what they might be expected to be in that latitude. They did in fact practically interfere with and reasonably delay the loading. There was no actual prevention of the loading, hut the difficulties presented were such that the finding might well be made that the delay in proceeding with it was not due to lack of diligence, on the part of the charterer. In other words, if the de-murrage claim had as its basis damages due to the culpable negligence [782]*782of the charterer, the finding of negligence might be refused. This claim, on the contrary, however, has a contract basis. The charterer agreed to load in a given number of days. If this were done, the vessel would be earning freight. If it were not done, the vessel would be idle for the overtime, and for this the charterer agreed to pay a per diem allowance. On the face of the contract it might be argued that the contract was not to pay for all the delay, but only for such part as was due to the “default” of the charterer, and default suggests the idea of culpability.

[1,2] The real question is the interpretation of the clause “detention by default of the charterer,” and either party, according as that meaning is, may retort upon the other, “If you wished the contract to be different from what it is, you should-have so contracted.” Discussion of the question is uncalled for, because it has been expressly ruled. “Default” does not mean “fault,” but merely failure to comply with the agreement to complete the loading in the stipulated time. The only exception is vis major or its equivalent. If the case of Burrill v. Crossman (D. C.) 65 Fed. 104, had been consulted and its experience in the appellate courts as reported in 69 Fed. 747, 16 C. C. A. 381, and 179 U. S. 106, 21 Sup. Ct. 38, 45 L. Ed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Perkins v. Lawrence Sperry Aircraft Co.
57 F.2d 719 (E.D. New York, 1932)
Bruusgaard v. Acosta
292 F. 957 (Second Circuit, 1923)
Fido v. Brazileiro
267 F. 733 (S.D. New York, 1919)
Mikkelsen v. A Cargo of Sugar
248 F. 807 (E.D. Pennsylvania, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
236 F. 779, 1916 U.S. Dist. LEXIS 1322, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-transp-co-v-unkel-paed-1916.