Southern Telecom, Inc. v. Tw Telecom Inc. of Georgia, L. P. F/K/A Time Warner Telecom of Georgia, L. P.

Court of Appeals of Georgia·Decided March 29, 2013·No. A12A2381·Published

Opinion

SECOND DIVISION

BARNES, P. J.,

MCFADDEN and MCMILLIAN , JJ.

NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed.

(Court of Appeals Rule 4 (b) and Rule 37 (b), February 21, 2008)

http://www.gaappeals.us/rules/

March 29, 2013

In the Court of Appeals of Georgia A12A2381. SOUTHERN TELECOM INC. v. TW TELECOM INC. McF-111 OF GEORGIA L.P. et al.

MCFADDEN, Judge.

This dispute is about the interpretation of certain contracts for the creation of telecommunications networks in Atlanta and Birmingham, Alabama. Those contracts were entered in the 1990s between the parties’ predecessors in interest. Appellant Southern Telecom and its predecessors are affiliates of the Southern Company, whose subsidiaries own power lines, power poles, conduits, rights-of-way and related equipment. Appellees TW Telecom Inc. of Georgia LP and TW Telecom of Alabama LLC (together, “TW”), like their predecessors, are in the telecommunications business. TW’s predecessors contracted to run cable and fibers along power lines and rights-of-way and through conduits belonging to Southern Telecom’s affiliates in the

Atlanta and Birmingham areas. Under the terms of those contracts Southern Telecom is entitled to a share of the revenue generated over TW’s predecessors’ Atlanta and Birmingham telecommunications networks.

The parties now disagree about the scope of the telecommunication networks from which Southern Telecom’s fee is calculated. The subject networks are identified and their scope is defined in the subject contracts. Those definitions specify how the subject networks at issue are to be distinguished from other networks to which they are interconnected. The subject networks are defined broadly, and the definitions contemplate future growth through expansion.

But the parties did not bargain for growth through acquisition, which is what has occurred. When the TW entities acquired their predecessors in interest, they had preexisting networks of their own in Atlanta and Birmingham. Southern Telecom now claims a right to share in the revenues of those preexisting networks. We find no warrant for that claim in the contracts. The contractual definitions of the subject networks do not support that claim. We find instead that Southern Telecom’s claim to revenue from the preexisting networks is controlled – and defeated – by the general rule that assignees’ rights and obligations are no greater than their assignors’.

Ruling on cross motions for summary judgment, the trial court held that Southern Telecom’s right to a share of revenues, and consequently to information needed to calculate amounts owed, is limited to the networks as they existed at the time the contracts were first assigned. The trial court properly rejected Southern Telecom’s claim to revenue from TW’s preexisting networks and properly ruled that TW was not required to provide financial records related to its preexisting networks. We therefore affirm.

1. Facts.

Summary judgment is appropriate when the pleadings and evidence “show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” OCGA § 9-11-56 (c). “On appeal from the grant or denial of summary judgment, we conduct a de novo review, with all reasonable inferences construed in the light most favorable to the nonmoving party.”(Citations omitted.) Forsyth County v. Waterscape Svcs., 303 Ga. App. 623 (694 SE2d 102) (2010).

So viewed, the record shows that Southern Telecom’s predecessor entered a contract with ICG Telecom Group, Inc. (“ICGT”) to construct and operate a telecommunications network in Atlanta using Georgia Power facilities, such as power

poles, conduits and rights-of-way. Another Southern Telecom predecessor entered a contract with ICG Access Services, Inc. to construct and operate a telecommunications network in Birmingham, Alabama, using Alabama Power facilities. The contracts contained provisions that entitled the Southern Telecom predecessors to a percentage of the revenues the TW predecessors generated from the sale of telecommunications services.

A. The Atlanta Contract’s Terms.

In addition to a $5.5 million initial payment, the contract required ICGT to pay during the contract term a “Network Fee,” which it defined as a “percentage[] of ICGT’s On-Net Revenue.” . The contract defined “On-Net Revenue” as “the gross revenue . . . received by ICGT or any of its Affiliates derived directly or indirectly from the sale of Telecommunication Services provided over the ICGT Network to Telecommunications Customers located in any On-Net Building by ICGT or any of its Affiliates.” The contract defined “On-Net Building” as “any building, facility, plant, operation or structure in the Atlanta [area] directly or indirectly connected to the ICGT Network.” The contract defined “ICGT Network” as:

the digital telecommunications facilities of ICGT within the Atlanta [area], including, without limitation, the ICGT Fibers as well as other

fibers utilized by ICGT, associated equipment and other digital telecommunications facilities that directly or indirectly intersect or connect to any ICGT Fibers or Cable, whether existing on the date hereof or constructed hereafter.

(Although the contract did not define “digital telecommunications facilities,” Federal Standard 1037C defines “telecommunications facilities” as “[t]he aggregate of equipment, such as radios, telephones, teletypewriters, facsimile equipment, data equipment, cables, and switches, used for providing telecommunications services.” Telecommunications: Glossary of Telecommu nicatio n Terms at http://www.its.bldrdoc.gov/fs-1037//dir-036/_5352.htm.)

The contract goes on to distinguish between portions of the ICGT Network which were installed on Georgia Power facilities, which are called “Route Segments,” and portions installed on facilities owned by entities other than Georgia Power, called “Alternate Route Segments.” Southern Telecom was entitled to payments calculated on the basis of both, but smaller payments for Alternate Route Segments. The contract defined “Route Segments” as the portion of “fiber optic cable incorporating the ICGT Fibers, to be used by or installed for or on behalf of ICGT” on Georgia Power facilities. The contract required the parties to designate the Route Segments

on Exhibit A to the contract. Exhibit A, in turn, referred to and incorporated a map that set forth the build-out plan for the ICGT Network.

The contract provided that ICGT could propose Route Segments as additions to Exhibit A. Georgia Power could then accept or reject the proposed additions. If Georgia Power rejected a proposed addition, ICGT could use non-Georgia Power facilities, thereby creating an Alternate Route Segment. Alternate Route Segments were part of the ICGT Network, but “any On-Net Revenue generated by any On-Net Building connected to the ICGT Network by an Alternate Route Segment, would be reduced “for the purpose of calculating the Network Fee due Southern Telecom. . . .”

The contract contained a provision authorizing assignment by ICGT, should ICGT merge or sell all of its assets, “so long as the surviving entity or purchaser . . . assumes all of the obligations of ICGT.” It also provided that it would be governed by Georgia law.

Free access — add to your briefcase to read the full text and ask questions with AI

Southern Telecom, Inc. v. Tw Telecom Inc. of Georgia, L. P. F/K/A Time Warner Telecom of Georgia, L. P., (Ga. Ct. App. 2013).

Southern Telecom, Inc. v. Tw Telecom Inc. of Georgia, L. P. F/K/A Time Warner Telecom of Georgia, L. P. (Southern Telecom, Inc. v. Tw Telecom Inc. of Georgia, L. P. F/K/A Time Warner Telecom of Georgia, L. P.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Vass v. Gainesville Bank & Trust
480 S.E.2d 294 (Court of Appeals of Georgia, 1997)
Algernon Blair, Inc. v. National Surety Corporation
151 S.E.2d 724 (Supreme Court of Georgia, 1966)
Forsyth County v. WATERSCAPE SERVICES, LLC
694 S.E.2d 102 (Court of Appeals of Georgia, 2010)
Central Georgia Electric Membership Corp. v. Georgia Power Co.
121 S.E.2d 644 (Supreme Court of Georgia, 1961)
Pridgen v. AUTO-OWNERS INSURANCE COMPANY
419 S.E.2d 99 (Court of Appeals of Georgia, 1992)
Nissan Motor Acceptance Corp. v. Ross
703 So. 2d 324 (Supreme Court of Alabama, 1997)
Winkleblack v. Murphy
811 So. 2d 521 (Supreme Court of Alabama, 2001)
Georgia Power & Light Co. v. City of Waycross
181 S.E. 575 (Supreme Court of Georgia, 1935)
High Point Sprinkler Co. v. George Hyman Construction Co.
297 S.E.2d 757 (Court of Appeals of Georgia, 1982)
Techwerks, Inc. v. Retail Technologies Corp.
509 S.E.2d 84 (Court of Appeals of Georgia, 1998)
Alabama Gold Life Insurance v. Hall
58 Ala. 1 (Supreme Court of Alabama, 1877)