Southern Surety Co. v. Masonic Temple Co.

4 Ohio App. 477, 25 Ohio C.C. (n.s.) 292, 25 Ohio C.A. 292, 1915 Ohio App. LEXIS 131
CourtOhio Court of Appeals
DecidedNovember 11, 1915
StatusPublished
Cited by1 cases

This text of 4 Ohio App. 477 (Southern Surety Co. v. Masonic Temple Co.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Surety Co. v. Masonic Temple Co., 4 Ohio App. 477, 25 Ohio C.C. (n.s.) 292, 25 Ohio C.A. 292, 1915 Ohio App. LEXIS 131 (Ohio Ct. App. 1915).

Opinion

Allread, J.

The Masonic Temple Company brought suit in the court of common pleas against E. E. Bope as principal and the Southern Surety Company as surety upon a bond for the performance of a building contract entered into by Bope with The Masonic Temple Company for the construction of a mercantile and lodge building in Washington Court Blouse.

Bope defaulted, the Surety Company declined to complete the work and the Temple Company [479]*479thereupon completed the building. The action is for the loss, including damages for delay.

The Temple Company recovered a verdict and judgment for $9,078.14. The judgment is brought here for review upon petition in error.

The defenses chiefly relied upon by the Surety Company are:

1. Change in the building contract subsequent to the giving of the bond and without the knowledge or consent of the surety.

2. Payment of estimates based upon full amount instead of ninety per cent, of wrought and fifty per cent, of unwrought material.

3. Advance payments to contractor.

4. Failure to notify Surety Company of prior defaults of contractor.

5. Insufficiency of evidence to support damages for delay.

Preliminary to the general consideration of the defenses it may be stated that the rule of strictissimi juris is not to be applied in all its latitude to cases of compensated sureties, but the surety’s contract “should receive a reasonable construction in order to carry out the presumed intention of the parties as expressed by the language used.” Bryant v. The American Bonding Co., 77 Ohio St., 90.

1. The changes in the plans of the building/ complained of were largely if not wholly made at the order of the state inspector. They did not change substantially the building, but were intended to conform the same to state regulations, j The original plans included a public hall. The parties were presumed as a matter of law to contract [480]*480with reference to the state inspection laws and to contemplate that changes of a minor character might be ordered. Besides, the testimony shows that shortly thereafter, and before any substantial part of the changes were constructed; Mr. Smith, vice president of the Surety Company, was notified of the changes ordered and made no objections thereto. This was supplemented by additional evidence to the effect that after Bope?s default the list of incompletions was furnished Mr. Smith and no objections were made as to them. The Temple Company then proceeded to complete the building with the changes incorporated.

It is also objected in this connection that these changes, in order to be binding on the surety,' should also have been approved by the architect and prices, agreed upon or fixed by arbitration. Whatever might have been the effect if either Bope or the Temple Company had objected, we are not called upon to decide. Both parties to the construction contract accepted these changes, and by acquiescence of all parties the additional cost was fixed by the architect under other provisions of the contract. In view of these circumstances we do not consider that such changes constitute a defense to the Surety Company’s liability.

2. The building contract provided that payments to the contractor should be made “only upon certificates of the architects, as follows: based upon an allowance of ninety per cent of material and labor actually in place in the building, and fifty per cent of the material on ground. * * * And all payments shall be due when certificates for the same are. issued.”

[481]*481It appears that the architect did not follow this j provision strictly, and it is claimed that estimates/ based upon the full amount of material and world were given .from time to time and paid by the Temple Company.

The estimates of the architect were regular in form and did not show upon their face that they were made upon ah irregular basis. There is no,< claim of collusion or fraud upon the part of the; Temple Company, but it is claimed that the Temple Company knew of the basis upon which the certificates were made. •

This is denied and there may be some doubt as to proof of this fact, but in view of the special instructions given by the court to the jury we may ignore the conflict of evidence upon this point and assume that there was some evidence upon which the jury might have found that the Temple Company had knowledge of the actual basis of the certificates. This, therefore, brings us to the question of whether the Temple Company was bound to revise or review the estimates of the contractor before making payment.'

Counsel for the Temple Company italicize the concluding sentence that “All payments shall be due when certificates for the same are issued.” Counsel for the Surety Company emphasize the clause providing that payment shall be made only upon certificates founded upon the stipulated percentage. This question is not free from difficulty and is one upon which the authorities in other, states are in conflict. We feel it to be our duty, in view of the conflict of authority, to adopt such eon[482]*482struction as would seem to be just and reasonable and best calculated to preserve and carry out the apparent intention of the parties to the contract.

It must be kept in mind that the architect was not the agent of the Temple Company, nor was he in any manner under its control. The architect was selected by the terms of the contract as an independent authority or umpire. If the estimates were too low the contractor had no right to object, and if they were too high the owner was equally bound. So long as there was no fraud or collusion we think the Temple Company was justified in making paj^ments strictly in conformity with the architect’s estimates. Many of the authorities cited by learned counsel for the Surety Company are cases where the obligation to make payments only upon certain percentages of work and material was placed upon the owner and not upon an independent architect.

From the spirit and general import of the contract we think that both parties expected to be bound in the progress of the work by the architect’s estimates.

The Surety Company contends, and not without a show of reason, that in its bond it reserved a contingent interest m the retained percentages and deferred payments, and also the right to notice of final payment. This condition of the bond would be quite pertinent in a case where the owner had not followed strictly the progress estimates of the architect and had paid amounts in excess of the architect’s certificates, but we think it does not apply where the owner is proceeding strictly according to the architect’s estimates.

[483]*483The Surety Company, being a compensated surety, is presumed to have fashioned the conditions of its bond, and if it was desired to hold the owner to a stricter liability as to retained percentages and deferred payments such liability should have been definitely stated.

3. All the evidence offered.tends to show that the advances made to the contractor were made as loans and not as advance payments. It is true! that the understanding was that the loans were to. be repaid out of estimates when available for that; purpose.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Campbell v. State
230 S.W. 695 (Court of Criminal Appeals of Texas, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
4 Ohio App. 477, 25 Ohio C.C. (n.s.) 292, 25 Ohio C.A. 292, 1915 Ohio App. LEXIS 131, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-surety-co-v-masonic-temple-co-ohioctapp-1915.