Southern States Supply Co. v. Commercial Industrial Contractors, Inc.

329 S.E.2d 738, 285 S.C. 222, 1985 S.C. LEXIS 381
CourtSupreme Court of South Carolina
DecidedApril 8, 1985
Docket22280
StatusPublished

This text of 329 S.E.2d 738 (Southern States Supply Co. v. Commercial Industrial Contractors, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern States Supply Co. v. Commercial Industrial Contractors, Inc., 329 S.E.2d 738, 285 S.C. 222, 1985 S.C. LEXIS 381 (S.C. 1985).

Opinion

Ness, Justice:

Respondent subcontractors sought to recover retainage amounts held by appellant general contractor as a set off claim for water and sewer tap fees paid by appellant but allegedly owed by one of the subcontractors. The trial court ruled neither subcontractor was liable for the tap fees and ordered appellant to pay respondents the retainage amount plus interest from the date owed. We reverse.

Appellant Sharp Construction Company undertook as general contractor the building of a HUD housing project. It subcontracted the interior plumbing to respondent Commercial Industrial Contractors, and the utilities work to respondent G.W. Ward Company.

Ward was obligated to perform in conformity with the plans and specifications under its written subcontract agreement. The plans and specifications clearly charged Ward with the duty of paying water and sewer tap fees. Nonetheless, the trial court held a contemporaneous independent oral agreement between Sharp and Ward specifically excluded this duty.

Appellant Sharp alleges the trial court violated the parol evidence rule by considering the contemporaneous independent agreement. We agree.

Where the terms of a written agreement are unambiguous, extrinsic evidence of statements made contemporaneously with or prior to its execution are inadmissible to contradict or vary the terms. Ray v. South Carolina National Bank, Inc., 281 S. C. 170, 314 S. E. (2d) 359 (S. C. App. 1984); McLeod v. Sandy Island Corp., 265 S. C. 1, 216 S. E. (2d) 746 (1975).

Under the written subcontract agreement Ward was responsible for the tap fees. We hold the terms of the written contract were contradicted in direct violation [224]*224of the parol evidence rule. The trial judge erred in disallowing Sharp’s set off claim against Ward for tap fees previously paid.

Reversed.

Littlejohn, C. J., and Gregory, Harwell and Chandler, JJ., concur.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ray v. South Carolina National Bank, Inc.
314 S.E.2d 359 (Court of Appeals of South Carolina, 1984)
McLeod v. Sandy Island Corp.
216 S.E.2d 746 (Supreme Court of South Carolina, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
329 S.E.2d 738, 285 S.C. 222, 1985 S.C. LEXIS 381, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-states-supply-co-v-commercial-industrial-contractors-inc-sc-1985.