Southern Menhaden Co. v. How

70 So. 1000, 71 Fla. 128
CourtSupreme Court of Florida
DecidedFebruary 8, 1916
StatusPublished
Cited by9 cases

This text of 70 So. 1000 (Southern Menhaden Co. v. How) is published on Counsel Stack Legal Research, covering Supreme Court of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Menhaden Co. v. How, 70 So. 1000, 71 Fla. 128 (Fla. 1916).

Opinion

Ellis, J.

The Southern Menhaden Company exhibited its bill in the Circuit Court for Duval County against Harlan W. How and Edward S. How, Co-partners doing business under the names of Southern Engineering Company or Harlan W. How Company; Morris Engineering-Company, a Corporation; Webster Manufacturing Company, a Corporation, and Orr and Sembower, a Corporation.

The purpose of the bill seems to have been to obtain an adjudication in this proceeding as to complainants’ liability to the How Company on a certain building contract ; to ascertain the amount due if any; to restrain the How Company from prosecuting its bill in chancery against the complainants to enforce a builders’ lien'and to restrain the prosecution at law of suits by Morris Engineering Company; Webster Manufacturing Company and Orr and Sembower, material men, against the complainants to enforce liens for materials, and thus determine in. the one proceeding all the issues presented in the other causes.

The cause proceeded through the various stages of original bill, answers, cross-bills, answers thereto, and replications to the taking of testimony and a decree against the complainant, to which it objects and takes this appeal.

Every answer to the original bill contained a demur[130]*130rer on the ground that it contained no matter of equity whereon the court could grant the relief prayed, but the cause proceeded to final adjudication on its merits, and the complainant below, as appellant now, seeks a reversal of the decree.

No question of pleading or practice is involved, and there is little dispute as to the facts. The claims of the material men for materials furnished to the How Company which were used in the construction of complainant’s manufactory seem to have been agreed upon by all parties as to amount, the complainant denying that they held liens for such materials upon any part of its'plant, because at the time they served notices upon it of their intention to declare liens upon the plant the complainant owed How Company, the contractors, nothing.

The appellant contends that the decree was erroneous because the chancellor construed a clause in the building contract for liquidated damages as a penalty; that the chancellor failed to allow certain indebtedness of the How Company to complainant to be set off by complainant against How Company’s claim, and that the chancellor erred in holding that the How Company had substantially complied with their contract.

These questions are presented by the record, and we will discuss them, or so many of them as may be necessary to a determination of this cause. We will not undertake to copy the pleadings nor any part of the testimony, nor the final decree, but will give in substance so much of the proceedings as we deem essential to a clear understanding of the case.

The Southern Menhaden Company is a Florida Corporation which was organized for the purpose of engag[131]*131ing in the business of manufacturing fish oil and fertilizer from a certain species of salt water fish known as “Menhaden.” To this end it became necessary for the corporation to purchase certain machinery, erect houses in which to establish the same and provide for the shelter of their employees. While other preparations were necessary to be made such as acquiring a site for the manufacturing plant, the employment of fishermen to catch the fish and other persons to operate the plant when completed, this cause has to do only with the contract, entered into by the corporation and How Company for the furnishing and erection of the machinery, the construction of the houses, and the rights and obligations springing therefrom. The other matters are of importance only in so far as they constitute the circumstances surrounding the formation of the contract and may afford some light on the construction of the clause therein relating to the damages for delay in the completion of the contract. See Tennessee Manuf’g Co. v. James, 91 Tenn. 154, 18 S. W. Rep. 262; Gobble v. Linder, 76 Ill. 175; Sanders v. Carter, 91 Ga. 450, 17 S. E. Rep. 345; Willson v. City of Baltimore, 83 Md. 203, 34 Atl. Rep. 774; Wilkinson v. Colley, 164 Pa. St. 35, 30 Atl. Rep. 286; 8 R. C. L. p. 560.

The Menhaden Company and Harlan W. and Edward S. How on January 15, 1912, entered into- a contract whereby the How Company agreed to fhrnish to the owner the Menhaden Company, certain machinery specified in the contract, of certain capacity and efficiency, to install the same, and have the plant completely equipped and in running order and in condition to receive fish on or before the nth day of March, 1912. [132]*132The owner was to construct the wharves and buildings for the reception of the machinery pursuant to plans to be furnished by the contractors, the How Company. For the machinery and equipment to be thus furnished by the contractors the owner agreed to pay them $32,400.00, and for the erection and superintendence and engineering work in connection with the mechanical equipment the sunn of four thousand dollars.

The payments were to have been made as follows: $5,000.00 when the contractors furnished a bond for the faithful performance of the contract; $3,100.00 within days after the furnishing of the bond; $4,860.00 upon the receipt of bills of lading showing shipment of the machinery; $3,240.00 when the factory was in running order to receive fish for the manufacture of them into oil and scrap; at the same time of the last payment in cash to deilver to the contractors, six promissory notes of the owner as follows: $4,000.00 payable in four months; $2,000.00 payable in five months; $2,000.00 payable in six months; $2,000 payable in seven omnths; $2,200.00 payable in eight months; and $4,000.00 payable in nine months. The four thousand dollars for the erection and superintendence and engineering work in connection with the mechanical equipment to be paid in cash from time to time as the work progressed. The factory was to have been built at a place about the distance of Fulton on the St. Johns River from. Jacksonville. The contract contained the following clause concerning which some trouble between the parties has arisen: “That for each and every day after the said nth day of March, 1912, the said plant is not in running order in accordance with the terms and, conditions of this agreement, [133]*133through no fault of the said owner, the said contractor shall pay to the said owner the sum of seventy-five dollars per day as liquidated damages until the said plant shall be in operation in accordance with the terms and conditions hereof.” A few days later the contract was amended whereby the owner waived the giving of a bond by the contractor for the performance of the contract and to make the first cash payment of $5,000.00 when Mr. How arrived in Jacksonville, and $3,100.00 within six days thereafter in consideration for which the How Company agreed that the first note for $4,000.00 payable in four months should be withheld for thirty days and delivered upon the fulfillment of the contract “relative to the operation and efficiency of the machinery furnished” by the contractors, and the other notes should be held for the same purpose not exceeding 120 days.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re SFD @ Hollywood, LLC
411 B.R. 788 (S.D. Florida, 2009)
Mineo v. Lakeside Village of Davie, LLC
983 So. 2d 20 (District Court of Appeal of Florida, 2008)
Boswell v. Zegeye
954 So. 2d 66 (District Court of Appeal of Florida, 2007)
Action Orthopedics, Inc. v. Techmedica, Inc.
759 F. Supp. 1566 (M.D. Florida, 1991)
Lefemine v. Baron
573 So. 2d 326 (Supreme Court of Florida, 1991)
Pembroke v. Caudill
37 So. 2d 538 (Supreme Court of Florida, 1948)
Chace v. Johnson
123 So. 519 (Supreme Court of Florida, 1929)
Atlantic Gulf Fertilizer Co. v. Mayo-Lyles Store
119 So. 513 (Supreme Court of Florida, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
70 So. 1000, 71 Fla. 128, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-menhaden-co-v-how-fla-1916.