Southern Materials Company, Incorporated v. Bryan Rock and Sand Company, and American-Marietta Company, and Third-Party

308 F.2d 414, 1962 U.S. App. LEXIS 4134
CourtCourt of Appeals for the Third Circuit
DecidedSeptember 12, 1962
Docket8590
StatusPublished
Cited by2 cases

This text of 308 F.2d 414 (Southern Materials Company, Incorporated v. Bryan Rock and Sand Company, and American-Marietta Company, and Third-Party) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Materials Company, Incorporated v. Bryan Rock and Sand Company, and American-Marietta Company, and Third-Party, 308 F.2d 414, 1962 U.S. App. LEXIS 4134 (3d Cir. 1962).

Opinion

SOPER, Circuit Judge.

This suit was brought for breach of contract for the sale of land and is based on the failure of the purchaser to whom the land had been conveyed to pay the purchase price in full. The question for decision is whether the purchaser was relieved of the obligation to make payment in full by one or more circumstances set up in defense. Obviously, if none of these defenses can be sustained the purchaser should respond in damages, as was held by the District Judge.

In 1957 Bryan Rock and Sand Company, a North Carolina corporation, was the owner of land in Prince George County, Virginia, on which it operated a plant for processing stone and gravel dug from the surrounding area. Southern Material Co., Inc., a Virginia corporation, owned some 20 acres of gravel land adjacent to the holdings of Bryan Rock. Southern Materials was then engaged in the construction of the Richmond-Pe-tersburg Turnpike in the vicinity and needed gravel for this project. In this situation it served the purposes of both organizations to enter into a contract under which Bryan Rock bought the 20 acres of land from Southern Materials and agreed to pay for it in crushed gravel to be delivered to Southern Materials at Bryan Rock’s plant.

The purchase agreement was in the form of a letter under date of August 1, 1957, in which Bryan Rock set out the terms of the agreement, as follows:

“This will confirm our agreement that in payment of the purchase price of Lots 13, 20 and 21, and one-half of Lots 14 and 22, as shown on the Riverdale Subdivision, Prince George County, Virginia, which you have conveyed to us by deed of even date herewith, the receipt of which deed is hereby acknowledged, we hereby agree to deliver to you and to load on your trucks, at our plant in Prince George County, Virginia, on land adjacent to that conveyed by said deed fifty thousand (50,000) tons of 1% inch crushed gravel. Said deliveries shall be made by us to you at such rate as you may request, up to three hundred (300) tons per day (excluding such Saturdays, Sundays and legal holidays as our plant is not in operation), beginning as soon as you so request, and continuing until the entire fifty thousand (50,000) tons have been delivered to you.”

It was the intention of the parties that the entire purchase price of the land be paid by the delivery of 50,000 tons of crushed gravel in accordance with the terms of the agreement and it was stipulated at the trial that at the time of contracting the gravel was worth $1.60 per ton, amounting to $80,000 in the aggregate. The contract called for delivery of the material on Southern Materials’ trucks at Bryan Rock’s plant in Prince George County, Virginia, situated on land adjacent to that conveyed by the deed, but it did not require that the material be taken from the land conveyed, and in fact some of the material delivered was dug from other lands of Bryan Rock. Deliveries, which commenced in *416 July, 1957, and continued to November, 1958, were made into the trucks of Southern Materials at the plant as and when requested by Southern Materials, without incident. However, in March, 1958, after some 28,000 tons of gravel had been delivered, Bryan Rock made the claim that the gravel in the property conveyed appeared to be substantially less than was represented, and the acreage less also, which relieved it of its obligation to deliver the full 50,000 tons provided by the contract. Nonetheless, Bryan Rock continued its deliveries of gravel on demand, and this position was subsequently abandoned and is not pressed on this appeal.

In all 32,017.70 tons of gravel were delivered between July, 1957 and November, 1958. In the latter month road building slows down on account of the weather. This had happened in the fall and winter months of 1957 — 1958. Moreover, Southern Materials’ work on the Richmond-Petersburg Turnpike had been completed and it made no further demands for delivery since at that time it had no immediate need for the gravel in the area, and it was not economically feasible to accept the material and transport it for use elsewhere or store it for future use.

The contract specified no time within which the demand for material and delivery should be accomplished. The matter lay dormant from the fall of 1958 until June 1959 when as we shall see, Bryan Rock’s obligation to perform the balance of the contract was raised by representatives of Southern Materials. In the meantime, the control of Bryan Rock had passed to other parties. On March 20, 1959 the Superior Stone Company, a North Carolina corporation, purchased all of the common stock of Bryan Rock and in connection with the transaction obtained an agreement of the owners of the stock to indemnify the purchaser against undisclosed claims of the company. Shortly thereafter on April 19, 1959, all of the assets of Superior Stone were purchased by American Marietta Company. In this transaction American Marietta assumed Bryan Rock’s liabilities and acquired the right to the indemnity covered by the agreement given by the former stockholders of Bryan Rock to Superior Stone Company.

Thereafter American Marietta decided to liquidate the Bryan Rock Company and on July 30, 1959, in the course of the liquidation Southern Materials purchased substantially all of Bryan Rock’s property in Virginia, including its rock-crushing plant and the adjacent land which Southern Materials had sold to it in 1957 under the contract in suit. Southern Materials’ claim in the present case was not overlooked when the last mentioned transaction took place. On June 16,1959 auditors, who were examining the books of Southern Materials, notified Bryan Rock that the books showed a balance of indebtedness in the sum of $28,781.68 owing to Southern Materials by Bryan Rock for the purchase of natural resource properties and asked for confirmation. Upon receipt of this letter Godfrey Cheshire of the Superior Stone Company, who had become president of Bryan Rock, communicated with D. T. Bailey, president of Bryan Rode when the contract in suit was signed, who took the position that Southern Materials had been more than paid for the property because the land contained 3 or 4 acres less than Southern Materials had represented. This contention, as we have seen, was subsequently abandoned and is not now before us.

In subsequent correspondence Southern Materials furnished the details of the contract in suit to American Marietta and demanded payment of the balance due and it was agreed that Southern Materials could have recourse against American Marietta for any claim it had against Bryan Rock. Negotiations between the parties for a settlement came to naught, American Marietta repudiated the claim and the present suit was instituted to recover the value of the undelivered gravel. At the trial on June 12, 1961 Southern Materials without objection amended its complaint and included a demand for the delivery of 17,982.3 *417 tons of gravel in aecordánce with the agreement as an alternative to its demand for money damages. The Judge, sitting without a jury, found for the plaintiff in the sum of $28,771.68 with interest and costs but stated in his opinion that the defendant * might satisfy the plaintiff’s claim by the delivery of 17,982.3 tons of gravel at Prince George County prior to the entry of final judgment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fargo Public Library v. City of Fargo Urban Renewal Agency
185 N.W.2d 500 (North Dakota Supreme Court, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
308 F.2d 414, 1962 U.S. App. LEXIS 4134, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-materials-company-incorporated-v-bryan-rock-and-sand-company-ca3-1962.