Southern Cross Lumber & Millwork Co. v. Becker

761 S.W.2d 269, 1988 Mo. App. LEXIS 1646, 1988 WL 126129
CourtMissouri Court of Appeals
DecidedNovember 29, 1988
Docket54326
StatusPublished
Cited by22 cases

This text of 761 S.W.2d 269 (Southern Cross Lumber & Millwork Co. v. Becker) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Cross Lumber & Millwork Co. v. Becker, 761 S.W.2d 269, 1988 Mo. App. LEXIS 1646, 1988 WL 126129 (Mo. Ct. App. 1988).

Opinion

GRIMM, Presiding Judge.

In this bench-tried case, James Becker, d/b/a Becker Escrow Service, appeals from a judgment entered in favor of plaintiff Southern Cross Lumber and Millwork Company for damages resulting from a breach of fiduciary duty. We affirm.

There are three allegations of error. First, that the trial court erred in overruling Becker’s motion to dismiss because Southern’s cause of action was barred by the five-year statute of limitations, § 516.120, RSMo 1986. We disagree, because Southern filed its suit within five years after its damages were capable of ascertainment. Second, that the trial court erred in determining that Becker owed a duty to Southern not to deliver Southern’s mechanic’s lien waiver without first disbursing full payment to Southern. We disagree, because Becker, as escrow agent, had a duty not to release the lien waiver unless Southern received payment.

The third and final allegation is that the trial court erred in determining that Becker was indebted to Southern in the amount of $7,432.92 because Southern clearly acknowledged, by delivery of its lien waiver to Becker on March 27, 1981, that it was paid in full. We disagree, because there was sufficient evidence for the trial court to find that Southern had not actually received payment.

A review of the facts in the light most favorable to the verdict reveals that, beginning in 1980, Southern provided materials to David Guthrel Development Company for improvements on several lots. The lot involved here was lot 4, Oak Post Lane in Chesterfield. Lumber and materials valued at $15,026.78 were sent to lot 4.

Guthrel had a construction loan for this lot from South Side National Bank. The bank required that funds be disbursed through an escrow agency, here James Becker, d/b/a Becker Escrow Services. Becker’s procedures, according to his manager, are the same as those “used by every escrow disbursing company in the city.”

Pursuant to the escrow agreement, Gu-threl, after receiving materials from Southern, was to send Southern a signed voucher indicating the amount to be paid Southern. Southern then must send the voucher, along with a statement of account and an executed lien waiver, to Becker. Becker then was to process the voucher. If sufficient funds were available, Becker countersigned the voucher, making it negotiable. The voucher was then to be sent back to Southern to endorse and deposit like a check.

After the above procedure was followed, on January 14, 1981, Southern received $7,593.86. On March 27, 1981, Southern received a voucher from Guthrel for $7,432.92; the remaining balance due. Southern, on the same day, sent Guthrel’s *271 voucher to Becker, along with a statement of account and a signed lien waiver, for $7,432.92.

After not receiving payment of the $7,432.92, Southern filed a mechanic’s lien and petition to enforce the lien. On December 9, 1985, a circuit court found that Southern was not entitled to a mechanic’s lien because of Southern’s signed lien waiver dated March 27, 1981. On January 21, 1987, Southern filed its petition against Becker for breach of fiduciary duty.

Becker first alleges that the trial court erred in overruling his motion to dismiss because Southern’s cause of action was barred by the five-year statute of limitations, § 516.120, RSMo 1986.

Becker argues that the applicable statute of limitations began to run on either March 28, 1981, (when he allegedly wrongfully delivered Southern’s lien waiver to Guthrel) or on March 28, 1981, if not earlier (when he failed to pay Southern fully for the materials delivered). He claims that Southern’s suit had to be brought by March 28, 1986, pursuant to the five-year statute of limitations, § 516.120, RSMo 1986. Thus, Southern’s suit filed January 21, 1987, was untimely and consequently, barred.

Southern, on the other hand, contends that the statute of limitations did not begin to run until December 9, 1985. This is the date when Southern’s signed lien waiver was used in circuit court to defeat its claim for a mechanic’s lien. Thus, according to Southern, its suit was brought within five years, as § 516.120, RSMo 1986 requires.

Section 516.100 provides in pertinent part:

Civil actions, other than those for the recovery of real property, can only be commenced within the periods prescribed in the following sections, after the causes of action shall have accrued; provided, that for the purposes of sections 516.100 to 516.370, the cause of action shall not be deemed to accrue when the wrong is done or the technical breach of contract or duty occurs, but when the damage resulting therefrom is sustained and is capable of ascertainment,....

Thus, § 516.100 requires that the resulting damage be “capable of ascertainment” before the applicable statute of limitations, here § 516.120, begins to run. “Capable of ascertainment” refers to the fact of damage rather than the precise amount. Title Insurance Company of Minnesota v. Construction Escrow Service, Inc., 675 S.W.2d 881, 885 (Mo.App.E.D.1984). It has been consistently held that the time under the statute of limitations begins to run only after the right to bring and prosecute a suit to a successful conclusion has arisen. Id. at 887; Beckers-Behrens-Gist Lumber Company v. Adams, 311 S.W.2d 70, 74 (Mo.App.E.D.1958). It does not necessarily begin to run when the liability is created. Construction Escrow Service, Inc. at 887.

From the evidence, we conclude that Southern did not actually sustain damage which was “capable of ascertainment” until December 9, 1985, when its lien waiver was used to defeat its claim for a mechanic’s lien. The liability arose when Becker breached his duty and wrongfully released the lien waiver without first countersigning the voucher so Southern could be paid. However, the cause of action against Becker did not accrue until December 9, 1985, when Southern’s damage was actually sustained and able to be ascertained. The statute of limitations, then, did not begin to run until December 9, 1985.

We find further support for denying this point. It has long been the rule that the burden of establishing the defense of statue of limitations is upon the party who relies on it. Section 516.100, Note 23, V.A. M.S. Although the evidence indicates that Southern gave the lien waiver to Becker on March 27, 1981, Becker produced no evidence as to when he released the lien waiver. All that is known is that it was presented by South Side National Bank in a court proceeding on December 9, 1985. Thus, Becker’s statute of limitations defense fails for lack of proof.

The trial court correctly held that Southern’s suit was not barred since the suit was brought within the applicable time period. Point denied.

*272

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rivermont Village, Inc. v. Preferred Land Title, Inc.
371 S.W.3d 858 (Missouri Court of Appeals, 2012)
Hammack v. Coffelt Land Title, Inc.
284 S.W.3d 175 (Missouri Court of Appeals, 2009)
Taylor v. St. John's Regional Health Center
161 S.W.3d 868 (Missouri Court of Appeals, 2005)
Wandler v. Lewis
1997 SD 98 (South Dakota Supreme Court, 1997)
Rameau A. and Phyllis A. Johnson v. Commissioner
108 T.C. No. 22 (U.S. Tax Court, 1997)
Johnson v. Commissioner
108 T.C. No. 22 (U.S. Tax Court, 1997)
In Re Lauer
98 F.3d 378 (Eighth Circuit, 1996)
E. Bruce Nangle v. Leroy J. Lauer
98 F.3d 378 (Eighth Circuit, 1996)
Bakewell v. Heritage National Bank
890 S.W.2d 653 (Missouri Court of Appeals, 1994)
Hopmeier v. First American Title Insurance Co. of Mid-West
856 S.W.2d 387 (Missouri Court of Appeals, 1993)
Nuspl v. Missouri Medical Insurance Co.
842 S.W.2d 920 (Missouri Court of Appeals, 1992)
Van Stratten v. Friesen
841 S.W.2d 750 (Missouri Court of Appeals, 1992)
Dave Kolb Grading, Inc. v. Lieberman Corp.
837 S.W.2d 924 (Missouri Court of Appeals, 1992)
Newton v. B.P.S. Guard Services, Inc.
833 S.W.2d 14 (Missouri Court of Appeals, 1992)
H.B.I. Corp. v. Jimenez
803 S.W.2d 100 (Missouri Court of Appeals, 1990)
American State Bank v. Adkins
458 N.W.2d 807 (South Dakota Supreme Court, 1990)
Community Title Co. v. Safeco Insurance Co. of America
795 S.W.2d 453 (Missouri Court of Appeals, 1990)
Earls v. King
785 S.W.2d 741 (Missouri Court of Appeals, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
761 S.W.2d 269, 1988 Mo. App. LEXIS 1646, 1988 WL 126129, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-cross-lumber-millwork-co-v-becker-moctapp-1988.