Southern Crescent Rehabilitation & Retirement Center, Inc. v. Georgia Departmet of Community Health

660 S.E.2d 792, 290 Ga. App. 863, 2008 Fulton County D. Rep. 1136, 2008 Ga. App. LEXIS 358
CourtCourt of Appeals of Georgia
DecidedMarch 24, 2008
DocketA07A2330
StatusPublished
Cited by1 cases

This text of 660 S.E.2d 792 (Southern Crescent Rehabilitation & Retirement Center, Inc. v. Georgia Departmet of Community Health) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Crescent Rehabilitation & Retirement Center, Inc. v. Georgia Departmet of Community Health, 660 S.E.2d 792, 290 Ga. App. 863, 2008 Fulton County D. Rep. 1136, 2008 Ga. App. LEXIS 358 (Ga. Ct. App. 2008).

Opinion

Ruffin, Judge.

The Department of Community Health (“DCH”) cancelled a certificate of need (“CON”) that had been awarded to Southern Crescent Rehabilitation and Retirement Center, Inc. (“Southern Crescent”). Southern Crescent requested an administrative hearing to contest the cancellation. The hearing officer affirmed the cancellation, and the decision was incorporated into the final administrative decision of DCH. Southern Crescent sought judicial review, and the superior court affirmed the administrative decision. Southern Crescent then appealed to this Court. For reasons that follow, we also affirm.

The relevant facts show that on January 31,1997, DCH awarded a CON to Southern Crescent to build a 40-bed nursing home facility. The initial duration of the CON was 12 months. Before construction commenced, Southern Crescent sought and obtained several pre-construction extensions, with the last one ending on January 31, 1999. Following one extension request, Southern Crescent received a letter from DCH that stated, in relevant part, that DCH rules

*864 provide[d] for automatic extension provisions for projects involving new construction. For projects with a total project cost under $3,000,000.00 an applicant is entitled to an automatic twelve (12) month extension to the initial twelve (12) month duration of the CON if they submit certain information to the Agency during the initial twelve (12) month period. This required information includes confirmation that 1) the construction plans have been approved by the State Architect [,] ... 2) verification that construction materials and equipment are on site, and 3) the submission of a signed construction contract with beginning and ending dates.

On January 29, 1999, Southern Crescent forwarded a letter to DCH, attaching certain progress reports and a copy of the construction contract, and stating that construction materials were on site. According to the contract, construction was “scheduled to commence March 15 or once the site plan receives approval from the county [,]” and substantial completion was expected by December 15, 1999. DCH responded by letter dated February 15, 1999, stating that Southern Crescent had complied with agency rules and that the CON was now valid through January 28, 2000.

According to Omar El Sawi, the owner of Southern Crescent, at some point during the month of January 1999, work began on the site to add a sewer line. Shortly thereafter, El Sawi experienced numerous personal problems, including a divorce and a protracted illness, that hindered work on the project. Thus, no construction occurred on the project for several years. Southern Crescent made periodic inquiries into the status of its CON, and on August 31, 2000 and again on April 1, 2002, Southern Crescent received letters informing it that there was no extension required once a project “has reached the construction phase.” The second letter noted that the project “was in compliance with the initial performance standards and [had] entered the eighteen-month construction phase.” If the construction was not completed during that time, DCH requested that Southern Crescent “keep [DCH] informed of the project’s progress, estimate when it might be completed, and provide the final report at the appropriate time.” 1

On September 11, 2003, the architect for Southern Crescent submitted a “plans transmittal letter,” which showed a construction *865 start date of October 15, 2003 and an estimated completion date of August 3, 2004. Upon receipt of the letter, the State’s architect, Erik Hotton, drove by what he believed to be the construction site and saw no evidence of construction, such as equipment, access roads, or cleared trees. According to Hotton, that was his second inspection of the site. He also drove by the proposed site in 2001 and saw no signs of construction. On October 16, 2003, DCH sent El Sawi a letter informing him that the CON had expired on January 20, 1999 and was no longer valid. The letter was mailed to El Sawi at the address DCH had on file; however, it was returned to sender. On October 24, 2003, a letter was sent to the architect on the nursing home project, informing him that the CON had been cancelled. After DCH deemed the CON cancelled, construction began in earnest on the project, and the land was cleared and a construction trailer was installed on site. Thus, on October 25, 2004 — over one year later — DCH sent a cease and desist letter to El Sawi. Notwithstanding this letter, El Sawi constructed the nursing home. According to El Sawi, he never received the first letter from DCH, although he conceded that he did receive the cease and desist letter. He also conceded that he learned from the architect in December 2003 — before construction of the building began — that the CON had been cancelled.

Southern Crescent wrote DCH, contesting the cancellation of the CON and requesting a hearing. Following a hearing, the hearing officer found in favor of DCH. The officer noted the requirement of OCGA § 31-6-41 (b) that CON projects be completed within a reasonable time. The officer further noted that the administrative rules provided that, during the initial 12 months following issuance of a CON, the person holding the CON must provide the following documentation: “(i) that the construction plans have been approved by [DCH]; (ii) that a construction contract has been signed, specifically indicating beginning and completion dates; and (iii) that construction materials and equipment are on site and construction of the project has actually begun.” 2 The hearing officer found that because construction had not started by January 30, 1999 — the date the last pre-construction extension ended — the CON expired on that date.

The hearing officer’s order was adopted as the final decision of DCH. Southern Crescent then petitioned for judicial review, and the superior court affirmed. On appeal, Southern Crescent contends that the superior court erred because: (1) the administrative decision was clearly erroneous in view of the substantial evidence; (2) the administrative decision was affected by error of law; (3) DCH should have been estopped from reversing its stance after Southern Crescent *866 detrimentally relied upon letters from the agency; (4) the administrative decision was made upon unlawful procedure; and (5) the administrative decision was “arbitrary, capricious, or characterized by an abuse of discretion or clearly unwarranted exercise of discretion.” We address each contention in turn.

1. In its first argument, Southern Crescent asserts that the administrative decision was clearly erroneous. Specifically, it argues that the CON did not expire on January 30, 1999, as found by the hearing officer — a finding that was adopted as D CH’s final order and affirmed by the superior court. In reviewing this argument, we must keep in mind the standard of review. The hearing officer serves as the finder of fact. 3 And such decision of the hearing officer becomes the decision of DCH unless modified or reversed by the review board. 4 But

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Resource Life Insurance Co. v. Buckner
698 S.E.2d 19 (Court of Appeals of Georgia, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
660 S.E.2d 792, 290 Ga. App. 863, 2008 Fulton County D. Rep. 1136, 2008 Ga. App. LEXIS 358, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-crescent-rehabilitation-retirement-center-inc-v-georgia-gactapp-2008.