Southerly Side of US Rte 7 LLC

CourtVermont Superior Court
DecidedMay 27, 2016
Docket135-9-14 Vtec
StatusPublished

This text of Southerly Side of US Rte 7 LLC (Southerly Side of US Rte 7 LLC) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southerly Side of US Rte 7 LLC, (Vt. Ct. App. 2016).

Opinion

STATE OF VERMONT SUPERIOR COURT ENVIRONMENTAL DIVISION Vermont Unit Docket No. 135-9-14 Vtec

Southerly Side of US Route 7 LLC DECISION ON MOTION

Applicant Southerly Side of U.S. Route 7, LLC (“Applicant”) seeks approval of Phase IIIB of an 88-unit planned unit development (the Project) in the Town of Milton, Vermont. Phases I, II, and IIIA of the Project have been approved and constructed, with 50 of the proposed 88 units completed. The current matter involves Applicant’s Phase III permit amendment application, proposing to split Phase IIIB into two phases; the amended Phase IIIB will include construction of 30 units, with the remaining eight units to be completed in Phase IIIC. The permit amendment application also requests a waiver from Section 592.11 of the Town of Milton Zoning Regulations. The Town of Milton Development Review Board (“DRB”) denied the permit amendment application on August 14, 2014, and Applicant appealed to this Court. Now before the Court is the Town’s motion for summary judgment, arguing that because the unappealed Phase III permit includes the condition that Applicant must provide a secondary road access to the Project before any additional units will be approved, and because Applicant’s permit amendment request fails to address this condition, the current application is barred by the successive application doctrine. In response, Applicant argues that its application is a permissible permit amendment because the prior permit condition is inapplicable and thus has no preclusive effect, and, to the extent a prior preclusive decision exists, the application is permissible because it offers a substantial change over the previous approved permit.

1 Factual Background For the purpose of putting the pending motion into context, the Court recites the following facts, which it understands to be undisputed unless otherwise noted:1 1. In June 2008, Applicant submitted an application for a planned unit development (PUD) off Route 7 South in Milton, Vermont. The Project area consists of 18.56 acres and is shaped like a long rectangle with one of the two short sides paralleling the southern side of Route 7. 2. The Project was proposed to be completed in three phases. 3. Phase I, closest to Route 7, was approved by the DRB in June of 2008. Phase I includes several commercial buildings and 157 parking spaces. Phase I was later amended in 2009 and 2010 to include two residential units above one of the commercial buildings. 4. Phase II of the Project, southwest and adjacent to the Phase I area, includes 34 residential townhome units, and was approved on September 24, 2009. 5. In 2010, Applicant submitted an application for final site plan approval of Phase III of the Project (Phase III Application), the area farthest from Route 7. The Phase III application proposed an additional 52 residential units. 6. The only public access to the Project from Route 7 is provided by a private right-of-way, Southerberry Drive. The Phase III Application proposed extending the private right-of-way and adding a road within the Project area to provide access to the Phase III units. With the extension, the private right-of-way would exceed 1,000 feet. 7. At the time Applicant submitted its Phase III Application, Section 592.7 of the Town of Milton Zoning Regulations (“Regulations”) stated: The maximum length of the PRIVATE RIGHT-OF-WAY for any residential subdivision shall be one thousand (1000) linear feet in its entirety; this requirement may be waived by the Development Review Board if it is determined that the roadway proposed can provide safe access for emergency

1 We note that Applicant, the non-moving party, did not respond to the Town’s statement of undisputed facts, but rather filed its own statement of “disputed” facts. See Appellant’s Statement of Disputed Facts, filed on Nov. 30, 2015. The Town responded to Appellant’s Statement with an additional filing on Dec. 18, 2015, in which the Town specifically disputed many of Appellant’s factual representations. While it may have been clearer for Applicant to have directly responded to the Town’s statement of undisputed facts, the facts we rely on here are understood to be undisputed based on both parties’ filings.

2 vehicles. This length shall be measured from the intersection with a PUBLIC RIGHT-OF-WAY. 8. Section 592.11 provided: A PRIVATE RIGHT-OF-WAY serving more than . . . 50 dwelling units must have a LOOPED ROAD (roads having more than one separate connection to an existing PUBLIC RIGHT-OF-WAY). This requirement may be waived by the Development Review Board if it is determined that the roadway proposed can provide safe access for emergency vehicles and efficient layout of utilities. 9. In its Phase III Application, Applicant requested waivers from Section 592.7 and 592.11 of the Regulations. 10. The DRB conducted a warned public hearing on September 23, 2010, and continued the hearing to October 28, 2010. 11. The DRB issued a decision on December 9, 2010 (2010 Decision) (submitted as Town Ex. A), granting final site plan approval for Phase III of the Project, but denying Applicant’s request for waivers of Sections 592.7 and 592.11 of the Regulations. 12. In Conclusion 25 of the 2010 Decision, the DRB found: [T]he proposed roadway cannot provide safe access for the residents of Phase Three, because there is not a secondary access to a public road. Therefore, the DRB denies the requested waivers from Section 592.7 and 592.11 of the Zoning Regulations. No zoning permits shall be issued for Phase Three until such time that a secondary access can be provided to a public road. Town Ex. A at 5. 13. In Condition 6 of the 2010 Decision, the DRB held: The DRB denies the requested waivers from Section 592.7 and 592.11 of the Zoning Regulations. No zoning permits shall be issued for Phase Three until such time that a secondary access that loops back out to a public road can be provided. At such time that a secondary access can be provided to a public road, then the waivers will no longer be necessary and zoning permits for the project may be issued. Town Ex. A at 10. 14. Soon after the DRB issued its 2010 Decision, Applicant submitted revised plans and requested the DRB to reconsider its denial of the requested waivers and Condition 6. Applicant’s revised plans included a twenty-foot-wide paved emergency access connecting Phase I and Phase II, but did not provide a secondary access to a public road.

3 15. The DRB issued a decision on Applicant’s request to reconsider on February 24, 2011 (2011 Decision) (submitted as Town Ex. D), denying the request to reconsider and finding the revised plans did not satisfy Condition 6. 16. In its 2011 Decision, the DRB again held “that a secondary access to a public road must be provided for Phase Three.” Town Ex. D at 5. 17. Applicant did not appeal either the 2010 or 2011 Decisions. 18. In 2012, Applicant submitted Amendment IX, which proposed adding an emergency access to the Project through the properties to the east of the Project. 19. On June 28, 2012, the DRB issued its denial of Amendment IX (June 2012 Decision) (submitted as Town Ex. E), finding the revisions insufficient to address its concerns about a secondary access which, it clarified, meant a second publicly accessible access to U.S. Route 7. 20. Later in 2012, Applicant submitted Amendment X, proposing to include an emergency access road from Route 7 through property to the west of the Project. 21. In a decision issued on December 13, 2012 (December 2012 Decision) (submitted as Town Ex. F), the DRB denied Amendment X, stating in Conclusion 22, “[T]he Applicant’s current proposal does not address the DRB’s concerns raised during the preliminary/final approval of Southerberry Phase III, the reconsideration hearing, and Amendment IX. In the Conclusions section of the preliminary/final decision and the reconsideration, the term “secondary access” is often used.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Silsby v. Allen's Blueberry Freezer, Inc.
501 A.2d 1290 (Supreme Judicial Court of Maine, 1985)
Robertson v. Mylan Laboratories, Inc.
2004 VT 15 (Supreme Court of Vermont, 2004)
In Re Application of Carrier
582 A.2d 110 (Supreme Court of Vermont, 1990)
In Re Stowe Club Highlands
687 A.2d 102 (Supreme Court of Vermont, 1996)
In Re Hildebrand
2007 VT 5 (Supreme Court of Vermont, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
Southerly Side of US Rte 7 LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southerly-side-of-us-rte-7-llc-vtsuperct-2016.